DOB03/04/2026FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER AS PER THE NYC A DMIN CODE OF SECTION 28.301.1.NOTE AT TIME OF INSPECTION,OBSERVED AT E XP4 FIRST SETBACK PARAPET CRACKED MASONRY STONE,ALSO VERTICAL CRACK AT EXP4 3RD SETBACK.REMEDY:FIX AND/OR REPLACE
DOB06/12/2024FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
ECB02/08/2024FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8A AND 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #901877. REMEDY: FILE ACCEPTABLE REPORT.$1K due
DOB11/01/2023FAILURE TO CORRECT SWARMP CONDITIONS
DOB09/18/2023CYCLE 9A UNSAFE REPORT FILED
DOB02/22/2022FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022
ECB12/17/202127-929.1 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGN PROFESSIONAL IN OFFICE BUILDING 100 FEET OR MORE IN HEIGHT IN EXIST$144 due
DOB12/01/2021FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
DOB07/06/2021V-DOB VIOLATION - ACTIVE
DOB04/29/2021FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
DOB07/06/2020V-DOB VIOLATION - ACTIVE
DOB09/03/2019FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019
DOB05/31/2018FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017
DOB06/26/2017V-DOB VIOLATION - ACTIVE
DOB05/20/2016V-DOB VIOLATION - ACTIVE
DOB07/02/2015V-DOB VIOLATION - ACTIVE
DOB07/15/2013V-DOB VIOLATION - ACTIVE
DOB01/31/2013FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012
DOB12/07/2012V-DOB VIOLATION - ACTIVE
DOB02/10/2011V-DOB VIOLATION - ACTIVE
DOB05/07/2010V-DOB VIOLATION - ACTIVE
DOB07/09/2009V-DOB VIOLATION - ACTIVE
DOB05/27/2008V-DOB VIOLATION - ACTIVE
DOB11/30/2007V-DOB VIOLATION - ACTIVE
DOB03/16/1999V-DOB VIOLATION - ACTIVE
DOB08/29/1995V-DOB VIOLATION - ACTIVE
DOB03/18/1994V-DOB VIOLATION - ACTIVE
DOB03/18/1993V-DOB VIOLATION - ACTIVE
ECB04/20/2026FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8A AND 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #901877. REMEDY: FILE ACCEPTABLE REPORT.Hearing held — result not yet published$1K proposed
ECB07/03/2024A. C. 27-929.1, FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORNothing owed — awaiting certificate of correction
ECB11/16/2023FAILURE TO PROVIDE ADEQUATE SAFETY MEASURES SUCH AS SHED, NETTING, ETC, WHERE REQUIRED TO PROTECT PUBLIC AND PROPERTY FROM DOCUMENTED UNSAFE FACADE AS PER 1RCNY 103-04. FACADE TECHNICAL REPORT FILED AS UNSAFE BNothing owed — awaiting certificate of correction
ECB02/28/202327-929.1 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGNPROFESSIONAL IN OFFICE BLDG 100 FT OR MORE IN HEIGHT IN EXISTENCE ONNothing owed — awaiting certificate of correction
ECB03/30/202127-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HENothing owed — awaiting certificate of correction
ECB12/03/201927-929.1 A.C. 27-929.1,FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL BY 7/1/19,IN AN OFFICE BUILDINNothing owed — awaiting certificate of correction
ECB08/28/2018FAILURE TO MAINTAIN EXTERIOR BUILDING. 1)ROOF-BULKHEADS, SAGGING LINTELS, BROKEN GLASS, SEALANT @ WINDOW DEFECTIVE, BRICK JOINTS ERODED, TERRACOTTA CRACKING AND GRAZING, TAR COVERS HAVE DEFECTS. 2)AT ROOF 30THNothing owed — awaiting certificate of correction
ECB06/16/2010FAILURE TO FILE AN ARCHITECT/ENGINEER REPORT CERTIFYING EXIT/DIRECTIONAL SIGNS ARE CONNECTED TO EMERGENCY POWER SOURCE/STORAGE BATTERY EQUIPMENT.REM:FILE ARCHITECT/ENGINEER REPORTNothing owed — awaiting certificate of correction
ECB01/27/200997X10.97X10 RETURN TO SERVICENothing owed — awaiting certificate of correction
ECB01/27/200968M07.73O02.64M07.69M07.60X11.15M07.70W07.73O02 OILY 64M07 & 69M07 CROSSHEAD 60X11 SECONDARY 70W07 DOORNothing owed — awaiting certificate of correction
ECB04/17/2008FAILURE TO MAINTAIN EXTERIOR BUILDING SOUTH/EAST ELEVTION SHOWS EXTENSIVE DETERIORATING MISSING AND DETACHMENT OF PARAPET FACADE, VERTICAL CRACKS AND SEPERATING IN CORNER FACADE EAST ELEVATION SHOWS BULGING SWENothing owed — awaiting certificate of correction
ECB07/20/199475U,(75) PERFORM 5YR TEST,PROPERLY TAG DRVICE AND FILE ELV 3 FORMNothing owed — awaiting certificate of correction
ECB07/15/199475U,74T 75 PERFORM 5 YEAR TEST PROPERLY TAB DEVICE AND FILE ELV 3 FORM74 PROVIDE CITY ELEV NUMBER ON MAIN MOTOR GENERATOR CONTROLLER AND DISCONNECT SWITHCHNothing owed — awaiting certificate of correction
ECB07/05/199475U,(75)PERFORM 5 YR. TEST PROPERLY TAG DRVICE AND FILE ELV 3 FORMNothing owed — awaiting certificate of correction
ECB12/18/199119L;15L;20L;11#; 15.2ND,9TH,11TH,16TH FLOORS. 11.PROVIDE COVER.Nothing owed — awaiting certificate of correction