| Owner | Filings | Most Recent |
|---|---|---|
| VIK XS SERVICES | 11 | 07/08/2026 |
| GROUP LLC L & M BUILDERS | 1 | 03/22/2026 |
| L M BUILDERS GROUP | 2 | 03/22/2026 |
| MGX ASSOCIATES PHASE 2 CE LLC | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CURTIS + GINSBERG ARCHITECTS LLP | 4 | 07/08/2026 |
| SKYLINE ENGINEERING, LLC | 6 | 08/07/2025 |
| OSPINO ENGINEERING PLLC | 2 | 12/17/2024 |
| TOHFAZ UDDIN PE PC | 2 | 10/25/2024 |
| LOMBARDO PROFESSIONAL ENGINEERING | 3 | 10/04/2024 |
| DOKA USA | 1 | 09/18/2024 |
| JOEL PHAGOO P.E. PLLC | 2 | 08/19/2024 |
| RIGID STRUCTURAL DESIGN, LLC | 1 | 03/08/2024 |
| SULLIVAN GROUP DESIGN LLC | 1 | 06/26/2022 |
| JZN ENGINEERING, PC. | 1 | 06/21/2022 |
| GACE DPC | 2 | 09/01/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 22 | 03/21/2026 |
| AO CONSULTING AND DRAFTING | 4 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 8 | 03/21/2026 |
| Rigid Structural Design, LLC | 1 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| L & M BUILDERS GROUP LLC | General Contractor | 28 | 07/08/2026 |
| ROCKLEDGE SCAFFOLD CORP | General Contractor | 6 | 07/08/2026 |
| ROBERT GIOELLO | Electrical | 4 | 03/21/2026 |
| GLO ELECTRIC LLC 004157 | General Contractor | 4 | 03/22/2026 |
| BLETSAS PLBNG & HTG CORP | Fire Protection | 3 | 07/08/2026 |
| AURA PLUMBING INC | Fire Protection | 3 | 07/08/2026 |
| RNC INDUSTRIES LLC | General Contractor | 3 | 07/08/2026 |
| 4 BROTHERS & SONS FENCE | General Contractor | 2 | 04/09/2026 |
| PANILI PLUMBING & HTG LLC | Plumbing | 1 | 06/28/2026 |
| GLO ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| BLETSAS PLBNG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| ANTHONY G FERRY INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| VIBRANALYSIS INC., DBA VT | 6864 | 12 | 07/08/2026 |
| JZN ENGINEERING, PC. | 363 | 2 | 06/21/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | L & M BUILDERS GROUP LLC | 01/14/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | VIK XS SERVICES INC | 10/29/2025 |
| DOB NOW | Curb Cut | Signed-off | L & M BUILDERS GROUP LLC | 09/02/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 08/19/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 08/19/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 08/19/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | CRISTINA MICHAELS CONS MN | 03/06/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | CRISTINA MICHAELS CONS MN | 03/06/2025 |
| DOB NOW | Plumbing | Permit Issued | PANILI PLUMBING & HTG LLC | 02/27/2025 |
| DOB NOW | Standpipe | Signed-off | AURA PLUMBING INC | 02/27/2025 |
| DOB NOW | Sprinklers | Signed-off | AURA PLUMBING INC | 02/27/2025 |
| DOB NOW | General Construction | Permit Issued | L & M BUILDERS GROUP LLC | 02/26/2025 |
| DOB NOW | Standpipe | Signed-off | AURA PLUMBING INC | 02/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | L & M BUILDERS GROUP LLC | 02/25/2025 |
| DOB NOW | General Construction | Permit Issued | L & M BUILDERS GROUP LLC | 02/25/2025 |
| DOB NOW | Construction Fence | Signed-off | 4 BROTHERS SONS FENCE | 02/25/2025 |
| DOB NOW | Foundation | Signed-off | L & M BUILDERS GROUP LLC | 02/24/2025 |
| DOB NOW | Structural | Signed-off | L & M BUILDERS GROUP LLC | 02/05/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | VIK XS SERVICES INC | 12/19/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | VIK XS SERVICES INC | 11/19/2024 |
| DOB NOW | Mechanical Systems | Signed-off | L & M BUILDERS GROUP LLC | 11/12/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | RNC INDUSTRIES LLC | 10/04/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | RNC INDUSTRIES LLC | 10/03/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | RNC INDUSTRIES LLC | 09/20/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 08/21/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 08/20/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 08/20/2024 |
| DOB NOW | Structural | Signed-off | L & M BUILDERS GROUP LLC | 08/14/2024 |
| DOB NOW | Standpipe | Signed-off | BLETSAS PLBNG & HTG CORP | 07/17/2024 |
| DOB NOW | Sprinklers | Signed-off | BLETSAS PLBNG & HTG CORP | 07/17/2024 |
| DOB NOW | Earth Work | Signed-off | L & M BUILDERS GROUP LLC | 06/04/2024 |
| DOB NOW | Foundation | Signed-off | L & M BUILDERS GROUP LLC | 06/04/2024 |
| DOB NOW | General Construction | Permit Issued | L & M BUILDERS GROUP LLC | 05/07/2024 |
| DOB NOW | Mechanical Systems | Signed-off | L & M BUILDERS GROUP LLC | 05/07/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | L & M BUILDERS GROUP LLC | 05/07/2024 |
| DOB NOW | Support of Excavation | Signed-off | L & M BUILDERS GROUP LLC | 05/06/2024 |
| DOB NOW | Plumbing | Permit Issued | BLETSAS PLBNG & HTG CORP | 04/18/2024 |
| DOB NOW | Standpipe | Signed-off | BLETSAS PLBNG & HTG CORP | 04/18/2024 |
| DOB NOW | Mechanical Systems | Signed-off | L & M BUILDERS GROUP LLC | 04/12/2024 |
| DOB NOW | Support of Excavation | Signed-off | L & M BUILDERS GROUP LLC | 04/11/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/08/2026 | Signed-off | L & M BUILDERS GROUP LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Climatemaster TY-024BGBC0BSBS 22,500 BTU · Heat Pump Outdoor ×6 TY-048AHBC0BTBS 41,600 BTU · Heat Pump Outdoor ×4 TSH-012AGBA9TRBS 11,700 BTU · Heat Pump Outdoor ×2 TYH-036BHBC0BTBS 36,600 BTU · Heat Pump Outdoor ×2 TYH-048AHBC0BTBS 41,600 BTU · Heat Pump Outdoor ×2 Ventilation Blauberg BL02 RH2500E-S31 1,440 CFM · Erv ×6 BL02 RH1500E-S31 1,020 CFM · Erv ×4 BL01 RH1200E-S31 750 CFM · Erv ×2 BL01 RH800 E-S31 480 CFM · Erv ×2 Greenheck G-140-VG 1,750 CFM · Exhaust Fan ×2 SQ-098-VB 175 CFM · Exhaust Fan ×2 SQ-99-VG 800 CFM · Exhaust Fan ×2 Enervex BEF500x 3,000 CFM · Exhaust Fan ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/08/2026 | Signed-off | AURA PLUMBING INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/08/2026 | Permit Issued | PANILI PLUMBING & HTG LLC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/09/2025 | Complete | AMBER LITE ELECTRIC CORP. | — |
| 11/08/2024 | Complete | AMBER LITE ELECTRIC CORP. | — |
| 10/07/2024 | Complete | TUXEDO ELEC'L CONTR'G INC | — |
| 08/30/2024 | Complete | ANTHONY G FERRY INC | — |
| 08/19/2024 | Complete | ANTHONY G FERRY INC | — |
| 08/09/2024 | Complete | GLO ELECTRIC LLC | General Wiring, Lighting, HVAC Wiring, Boiler Controls |
| 06/27/2024 | Complete | AMR ELEC'L CONTRG CORP | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/08/2026 | Signed-off | L & M BUILDERS GROUP LLC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/08/2026 | Signed-off | L & M BUILDERS GROUP LLC | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/15/2026 | Pass-Final Construction Permit Withdrawal | Pass | View ↗ |
| 03/26/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 02/12/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 01/28/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/16/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/10/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 11/07/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/22/2025 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 09/22/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/08/2025 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 09/08/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/16/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/14/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/14/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/02/2025 | Fail-Final SD - Fire Pump | Fail | View ↗ |
| 06/20/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 03/31/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 02/20/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/19/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/05/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/05/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/02/2026 | Fire-Resistant Penetrations and Joints | JUAN GOMEZ | special |
| 07/02/2026 | Fenestration and door U-factor and product ratings | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Air barrier - visual inspection | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Air barrier continuity plan testing | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Vestibules | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Insulation placement and R values | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Fenestration areas | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Air barrier — testing | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Fenestration air leakage | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Protection of exposed foundation insulation | JUAN GOMEZ | energy_progress |
| 07/02/2026 | Fire-Resistance Rated Construction | JUAN GOMEZ | progress |
| 07/02/2026 | Energy Code Compliance Inspections | JUAN GOMEZ | progress |
| 10/16/2025 | Duct leakage testing, insulation and design | JUAN GOMEZ | energy_progress |
| 10/16/2025 | Exterior lighting power | JUAN GOMEZ | energy_progress |
| 10/16/2025 | HVAC-R and service water heating equipment | JUAN GOMEZ | energy_progress |
| 10/16/2025 | Electrical motors and elevators | JUAN GOMEZ | energy_progress |
| 10/16/2025 | Interior lighting power | JUAN GOMEZ | energy_progress |
| 10/16/2025 | Metering | JUAN GOMEZ | energy_progress |
| 10/16/2025 | Mechanical Systems | JUAN GOMEZ | special |
| 10/16/2025 | Final | JUAN GOMEZ | progress |
| 10/16/2025 | Lighting in dwelling units | JUAN GOMEZ | energy_progress |
| 10/16/2025 | Shutoff dampers | JUAN GOMEZ | energy_progress |
| 10/16/2025 | Maintenance information | JUAN GOMEZ | energy_progress |
| 10/16/2025 | Lighting controls | JUAN GOMEZ | energy_progress |
| 10/16/2025 | HVAC-R and service water heating system controls | JUAN GOMEZ | energy_progress |