Training school · Owner of record: ARCHITECTURAL IRON REALTY, INC · 5,204 sf lot · 2.17 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbingGeneral
Roof5p · 3 filings · 20 docs
Floor 24p · 2 filings · 20 docs
Floor 12p · 1 filing · 13 docs
Mezzanine2p · 2 filings · 20 docs
Cellar1p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ARCHITECTURAL IRON REALITY CORPO4707/08/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM ZONING, LLC.203/21/2026
A1 EXPEDITING SERVICE203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CORE FOUR CONSTRUCTION INGeneral Contractor903/21/2026
ASHLAR MECHANICAL CORPFire Protection207/08/2026
CORPORATE ELEC. GROUP INCElectrical103/22/2026
YORK SCAFFOLD EQUIPMENT CORP.General Contractor107/08/2026
PAR PLUMBING CO., INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TAMBORRA ARCHITECTURE5339105/12/2026
TWIN PEAKS INC.317309/27/2022
JMV CONSULTING ENGINEERIN804211/09/2021
MT GROUP798104/15/2021
Building Lifecycle
All (111)Filed (11)Permit Issued (7)Signed Off (2)Violation (24)Inspection (7)Objection (30)Special Inspection (30)
06/25/2026
Objection resolved — Resolved
06/25/2026
Objection resolved — Resolved
06/25/2026
Objection resolved — Resolved
06/02/2026
Objection raised — Cost
06/02/2026
Objection raised — Admin
06/02/2026
Objection raised — Admin
05/12/2026
Filed — Alteration
Q01078333-I1
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/09/2024
Special inspection requirement — Final
07/09/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Nicholas Tamborra
07/09/2024
Special inspection requirement — Concrete - Cast-In-Place
Nicholas Tamborra
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/09/2022
Signed off — Alteration
New partitions, ceilings, and LED lighting per plans filed herewith. No change to existing use, occupancy, or egress.
Q00572906-I1
10/04/2022
Special inspection requirement — Final
James Counts
10/04/2022
Special inspection requirement — Lighting controls
MIKHAIL ZEYGMAN
10/04/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIKHAIL ZEYGMAN
10/04/2022
Special inspection requirement — Structural Cold-Formed Steel
MIKHAIL ZEYGMAN
10/04/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
MIKHAIL ZEYGMAN
10/02/2022
Objection raised — Other
10/02/2022
Objection resolved — Addressed
09/27/2022
Filed — Alteration
New partitions, ceilings, and LED lighting per plans filed herewith. No change to existing use, occupancy, or egress.
Q00572906-P2
09/26/2022
Special inspection requirement — Final
James Counts
09/26/2022
Special inspection requirement — Lighting controls
MIKHAIL ZEYGMAN
09/26/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
MIKHAIL ZEYGMAN
09/26/2022
Special inspection requirement — Structural Cold-Formed Steel
MIKHAIL ZEYGMAN
09/26/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIKHAIL ZEYGMAN
08/27/2022
Filed — Alteration
REMOVE AND RELOCATE PLUMBING FIXTURES IN THE BUILDING; EXTEND GAS PIPING ON ROOF LEVEL. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00573102-P2
08/17/2022
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
08/09/2022
Objection resolved — Addressed
07/28/2022
Filed — Alteration
REMOVE AND RELOCATE PLUMBING FIXTURES IN THE BUILDING; EXTEND GAS PIPING ON ROOF LEVEL. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00573102-P1
07/28/2022
Objection raised — P-1.3
07/27/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/22/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/14/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/10/2022
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/17/2022
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/06/2022
Objection resolved — Addressed
05/05/2022
Objection raised — Scope
05/03/2022
Filed — Alteration
New partitions, ceilings, and LED lighting per plans filed herewith. No change to existing use, occupancy, or egress.
Q00572906-P1
05/02/2022
Special inspection requirement — Lighting controls
MIKHAIL ZEYGMAN
05/02/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIKHAIL ZEYGMAN
05/02/2022
Special inspection requirement — Structural Cold-Formed Steel
MIKHAIL ZEYGMAN
05/02/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
MIKHAIL ZEYGMAN
05/02/2022
Special inspection requirement — Structural Steel - Details
MIKHAIL ZEYGMAN
05/02/2022
Special inspection requirement — Final
James Counts
04/28/2022
Permit issued — Sprinklers
Q00573110-I1-EW-SP
04/01/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/15/2022
Permit issued — Sprinklers
Q00573110-I1-EW-SP
02/14/2022
Permit issued — Structural
Q00572906-I1-ST
02/14/2022
Permit issued — General Construction
Q00572906-I1-GC
02/09/2022
Permit issued — Mechanical Systems
Q00573118-I1-MS
02/01/2022
Permit issued — Plumbing
Q00573102-I1-PL
12/14/2021
Objection resolved — Addressed
12/14/2021
Objection resolved — Addressed
12/10/2021
Objection resolved — Addressed
12/09/2021
Objection raised — Scope
12/07/2021
Objection resolved — Addressed
12/07/2021
Objection resolved — Addressed
11/17/2021
Objection resolved — Addressed
11/12/2021
Objection raised — Energy
Latest 60 of 111 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offASHLAR MECHANICAL CORP04/28/2022
DOB NOWSprinklersSigned-offASHLAR MECHANICAL CORP02/15/2022
DOB NOWStructuralSigned-offCORE FOUR CONSTRUCTION IN02/14/2022
DOB NOWGeneral ConstructionSigned-offCORE FOUR CONSTRUCTION IN02/14/2022
DOB NOWMechanical SystemsSigned-offCORE FOUR CONSTRUCTION IN02/09/2022
DOB NOWPlumbingSigned-offPAR PLUMBING CO., INC02/01/2022
DOB NOWSupported ScaffoldSigned-offYORK SCAFFOLD EQUIPMENT CORP.07/08/2021
BISOTISSUEDSD BUILDERS AND CONSTRUCT02/03/2021
BIS—ISSUEDS. ZEZULA RENOVATION INC12/01/2011
BIS—ISSUEDBERGER SIGN FABRICATION, INC04/01/2004
BISEQRE-ISSUEDSTRUCTURE TONE, LLC10/31/2003
BIS—ISSUEDSTRUCTURE TONE, LLC10/31/2003
BISPLISSUEDGEORGE BRESLAW & SONS INC.04/11/2003
BISMHISSUEDSTRUCTURE TONE, LLC04/03/2003
BISSPISSUEDABCO-PEERLESS SPRKLR CORP03/24/2003
BISEQISSUEDSTRUCTURE TONE, LLC01/27/2003
BIS—ISSUEDSTRUCTURE TONE, LLC01/27/2003
BISOTISSUEDSTRUCTURE TONE, LLC01/24/2003
BISPLISSUEDMAIN LINE PLG02/07/1996
BISOTISSUEDHENICK LANE ,INC11/09/1992
1 project · most recent 11/09/2021
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
11/09/2021Signed-offCORE FOUR CONSTRUCTION INAir Conditioning Systems, Heating Systems
Cooling
Mitsubishi Electric TPLFYP018FM140A 18,000 BTU · Vrf Indoor ×6
NTXCKS09A112A 8,500 BTU · Ahu ×4
MXZ3C30NAZ 120,000 BTU · Vrf Outdoor ×1
MXZ3C330NAZ 28,400 BTU · Ahu ×1
NTXCKS0112A 11,400 BTU · Ahu ×1
NTXCKS12A112A 11,400 BTU · Ahu ×1
TUHYP1203AN40AN 284,000 BTU · Vrf Outdoor ×1
Trane YHC074F3RZA2606C1A1B 70,980 BTU · Rooftop Unit ×2
YSC120H3RZA2606C1A1B 107,810 BTU · Rooftop Unit ×2
Heating
Trane OAGD120F3-000000CC-AIM00AF0002000B0 18 tons · Rooftop Unit ×1
1 project · most recent 08/27/2022
Gas Water/Sanitary
FiledStatusContractorScope
08/27/2022Signed-offPAR PLUMBING CO., INCGas, Water/Sanitary
1 project · most recent 02/17/2022
General Wiring
FiledStatusContractorScope
02/17/2022Permit IssuedCORPORATE ELEC. GROUP INCGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
08/17/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
07/27/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/22/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/14/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/10/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/17/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/01/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
07/09/2024Final—progress
07/09/2024Structural Stability – Alterations of existing buildingsNicholas Tamborraspecial
07/09/2024Concrete - Cast-In-PlaceNicholas Tamborraspecial
10/04/2022FinalJames Countsprogress
10/04/2022Lighting controlsMIKHAIL ZEYGMANenergy_progress
10/04/2022Fire-Resistant Penetrations and JointsMIKHAIL ZEYGMANspecial
10/04/2022Structural Cold-Formed SteelMIKHAIL ZEYGMANspecial
10/04/2022Structural Stability – Alterations of existing buildingsMIKHAIL ZEYGMANspecial
09/26/2022FinalJames Countsprogress
09/26/2022Lighting controlsMIKHAIL ZEYGMANenergy_progress
09/26/2022Structural Stability – Alterations of existing buildingsMIKHAIL ZEYGMANspecial
09/26/2022Structural Cold-Formed SteelMIKHAIL ZEYGMANspecial
09/26/2022Fire-Resistant Penetrations and JointsMIKHAIL ZEYGMANspecial
05/02/2022Lighting controlsMIKHAIL ZEYGMANenergy_progress
05/02/2022Fire-Resistant Penetrations and JointsMIKHAIL ZEYGMANspecial
05/02/2022Structural Cold-Formed SteelMIKHAIL ZEYGMANspecial
05/02/2022Structural Stability – Alterations of existing buildingsMIKHAIL ZEYGMANspecial
05/02/2022Structural Steel - DetailsMIKHAIL ZEYGMANspecial
05/02/2022FinalJames Countsprogress
11/05/2021HVAC-R and service water piping design and insulationJoseph Vutoenergy_progress
11/05/2021HVAC-R and service water heating system controlsJoseph Vutoenergy_progress
11/05/2021Maintenance informationJoseph Vutoenergy_progress
11/05/2021HVAC-R and service water heating equipmentJoseph Vutoenergy_progress
08/09/2021FinalJoseph Vutoprogress
08/09/2021Mechanical SystemsJoseph Vutospecial
Latest 25 of 30.
▾Documents — 119 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch10
08/27/2026Q00551061-I1Request digital key ↗
08/27/2026Q00573102-I1Request digital key ↗
08/27/2026Q00573102-P2Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/27/2026Q00434313-I1Request digital key ↗
08/27/2026Q00434313-P1Request digital key ↗
▸Applications & Permits6
▸BISWORK PERMIT APPLICATION3
02/03/2021440653320Open ↗
03/19/2012420361067Open ↗
12/02/2011420361067Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
01/21/2021440653320Open ↗
05/27/2011420361067Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
02/08/2012420361067Open ↗
▸Seals & Professional Certifications47
▸DOB NOWSpecial Inspector Seal & Signature16
09/25/2026Q00434313-I1Open ↗
09/25/2026Q00434313-I1Open ↗
09/25/2026Q00434313-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature13
09/25/2026Q00434313-I1Open ↗
09/02/2026Q00572906-P1Open ↗
09/02/2026Q00572906-P1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/27/2026Q00434313-P1Open ↗
08/27/2026Q00434313-I1Open ↗
08/27/2026Q00573102-I1Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
08/31/2012420361067Open ↗
12/02/2011420361067Open ↗
05/27/2011420361067Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
01/21/2021440653320Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
01/21/2021440653320Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
01/21/2021440653320Open ↗
▸Trade Schedules & Equipment5
▸BISSELF-CERT PLUMBING NOTICE2
09/17/2012420361067Open ↗
08/31/2012420361067Open ↗
▸BISSPRINKLER INSP REPORT : FP-852
09/10/2012420361067Open ↗
08/31/2012420361067Open ↗
▸BISSCHEDULE B - PLUMBING1
05/27/2011420361067Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
05/27/2011420361067Open ↗
▸Environmental & Asbestos20
▸DOB NOWOER: Notice to Proceed9
08/13/2026Q00573118-I1Open ↗
08/13/2026Q00572906-P2Open ↗
08/13/2026Q00572906-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/27/2026Q00434313-I1Open ↗
08/27/2026Q00434313-P1Open ↗
08/15/2026Q00572906-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/27/2026Q00573102-I1Open ↗
08/13/2026Q00573118-I1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
05/27/2011420361067Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
01/21/2021440653320Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
01/21/2021440653320Open ↗
▸DOB NOWOER: Notice of Satisfaction1
08/13/2026Q00572906-I1Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
02/03/2021440653320Open ↗
01/21/2021440653320Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026Q00573118-I1Open ↗
08/13/2026Q00572906-I1Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
08/31/2012420361067Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
01/21/2021440653320Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
02/03/2021440653320Open ↗
01/28/2021440653320Open ↗
01/21/2021440653320Open ↗
▸Approvals, Objections & Sign-offs12
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter9
08/27/2026Q00573102-I1Open ↗
08/27/2026Q00573102-P2Open ↗
08/27/2026Q00573110-I1Open ↗
Showing 3 of 9 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
10/05/2012420361067Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
05/27/2011420361067Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
05/27/2011420361067Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
01/21/2021440653320Open ↗
08/31/2012420361067Open ↗
05/27/2011420361067Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET1
05/27/2011420361067Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
01/21/2021440653320Open ↗
▸BISADDITIONAL INFORMATION1
02/02/2021440653320Open ↗
▸Other Documents1
▸BISPLOT DIAGRAM1
05/27/2011420361067Open ↗