💬 Discuss this project
1965Year Built
10Stories
D7Building Class
M1-3/R7XZoning
67,949 sfGross Floor Area
130Units
LL97 CoveredRent Stabilized0 Active Violations
Elevator apt, semi-fireproof with stores · Owner of record: 39th Ave Holdings 1 · 16,248 sf lot · 4.18 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsConversion and 9 Stories Residential Addition to Existing 1 2 filings
RoofShoring and bracing of existing 1-story building1p · 1 filing
Floor 9Unit 9B
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1Shoring and bracing of existing 1-story building4p · 2 filings
MezzanineElevator removal and opening closure1p · 1 filing · 10 docs
CellarShoring and bracing of existing 1-story building6p · 2 filings
Site & exteriorHeavy duty sidewalk shed3 filings
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Ahrc703/21/2026
Developing NYS203/21/2026
39th Ave Holdings 1103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/02/2022$19.1M—Ahrc NYC New Projects → 39TH AVE HOLDINGS 1 LLC$281/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY Building Associates1112/18/2025
Associates710/09/2024
Paul Perdek, Prof. Engineering208/25/2023
Tohfaz Uddin PE207/27/2023
Severud Associates507/19/2023
Howard I. Shapiro & Associates203/29/2023
Enthink Engineers203/16/2023
Fna Engineering Services212/20/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Moses Katz Associates5003/21/2026
AE Design Solution403/21/2026
Howard I Shapiro Associates403/21/2026
Synergy Building Consultants203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Developing NY StateGeneral Contractor2707/08/2026
Developing NY StateScaffold707/08/2026
Safety Fire SprinklerFire Protection407/08/2026
Bayport ConstructionScaffold403/21/2026
Colgate EnterpriseScaffold207/08/2026
Metro Contracting NYScaffold207/08/2026
Prime Piping & HeatingPlumbing207/08/2026
Mpi PlumbingPlumbing107/08/2026
Nash Electric ServicesElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Big Apple Group NY A Rma91682112/18/2025
Tohfaz Uddin P.E2001106/20/2023
Fna Engineering Services7846203/22/2022
Building Lifecycle
All (233)Filed (33)Permit Issued (31)Signed Off (17)Violation (26)Inspection (16)Objection (80)Special Inspection (30)
04/03/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-I1
03/27/2026
Violation issued (HPD, closed)
B
01/08/2026
Special inspection requirement — Air barrier — testing
Soorjbally Harilall
01/08/2026
Special inspection requirement — Maintenance information
Soorjbally Harilall
01/08/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Soorjbally Harilall
01/08/2026
Special inspection requirement — Lighting controls
Soorjbally Harilall
01/08/2026
Special inspection requirement — Lighting in dwelling units
Soorjbally Harilall
01/08/2026
Special inspection requirement — Fenestration air leakage
Soorjbally Harilall
01/08/2026
Special inspection requirement — Insulation placement and R values
Soorjbally Harilall
01/08/2026
Special inspection requirement — Exterior lighting power
Soorjbally Harilall
01/08/2026
Special inspection requirement — Protection of exposed foundation insulation
Soorjbally Harilall
01/08/2026
Special inspection requirement — Electrical motors and elevators
Soorjbally Harilall
01/08/2026
Special inspection requirement — Interior lighting power
Soorjbally Harilall
01/08/2026
Special inspection requirement — Fire-Resistance Rated Construction
Soorjbally Harilall
01/08/2026
Special inspection requirement — Metering
Soorjbally Harilall
01/08/2026
Special inspection requirement — Fenestration areas
Soorjbally Harilall
01/08/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
SOORJBALLY HARILALL
01/08/2026
Special inspection requirement — Air barrier - visual inspection
Soorjbally Harilall
01/08/2026
Special inspection requirement — Concrete - Cast-In-Place
SOORJBALLY HARILALL
01/08/2026
Special inspection requirement — Energy Code Compliance Inspections
Soorjbally Harilall
01/08/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
SOORJBALLY HARILALL
01/08/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Soorjbally Harilall
12/18/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-A6
12/17/2025
Special inspection requirement — Fenestration areas
Soorjbally Harilall
12/17/2025
Special inspection requirement — Fire-Resistance Rated Construction
Soorjbally Harilall
12/17/2025
Special inspection requirement — Fenestration air leakage
Soorjbally Harilall
12/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
SOORJBALLY HARILALL
12/17/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
SOORJBALLY HARILALL
12/17/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Soorjbally Harilall
12/17/2025
Special inspection requirement — Energy Code Compliance Inspections
Soorjbally Harilall
12/17/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Soorjbally Harilall
12/17/2025
Special inspection requirement — Concrete - Cast-In-Place
SOORJBALLY HARILALL
12/17/2025
Special inspection requirement — Interior lighting power
Soorjbally Harilall
06/16/2025
Violation issued (HPD, closed)
A
02/18/2025
Signed off — Alteration
Q00835920-I1
02/17/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-S7
02/17/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-S8
01/08/2025
Signed off — Alteration
Q00837779-I1
12/09/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-S6
11/26/2024
Objection resolved — Addressed
11/21/2024
Objection resolved — Addressed
11/21/2024
Objection resolved — Addressed
11/15/2024
Objection raised — Other
11/15/2024
Objection raised — Other
11/07/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-A4
10/18/2024
Objection raised — Energy
10/16/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/09/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-A3
10/09/2024
Violation issued (ECB, closed)
Construction
10/09/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
09/25/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-S5
09/18/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-Z1
09/18/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-S2
09/18/2024
Signed off — Alteration
Installation of 7,000# temporary dual cars personnel/material hoists per plan and application submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q00893173-I1
09/04/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-S4
08/29/2024
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
08/23/2024
Objection resolved — Addressed
08/15/2024
Objection resolved — Addressed
08/15/2024
Objection resolved — Addressed
08/14/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Temporary standpipe application in conjunction with vertical addition
Q00684765-S3
Latest 60 of 233 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offPrime Piping & Heating03/29/2024
DOB NOWSidewalk ShedSigned-offMetro Contracting NY03/07/2024
DOB NOWConstruction FenceSigned-offDeveloping NY State03/04/2024
DOB NOWCurb CutSigned-offDeveloping NY State02/02/2024
DOB NOWStructuralSigned-offDeveloping NY State01/08/2024
DOB NOWMechanical SystemsSigned-offDeveloping NY State08/07/2023
DOB NOWSprinklersSigned-offSafety Fire Sprinkler08/02/2023
DOB NOWGeneral ConstructionPermit IssuedDeveloping NY State07/31/2023
DOB NOWStructuralSigned-offDeveloping NY State07/31/2023
DOB NOWStandpipeSigned-offSafety Fire Sprinkler07/31/2023
DOB NOWProtection and Mechanical MethodsSigned-offColgate Enterprise07/28/2023
DOB NOWSupported ScaffoldSigned-offBayport Construction07/25/2023
DOB NOWGeneral ConstructionPermit IssuedDeveloping NY State07/13/2023
DOB NOWProtection and Mechanical MethodsSigned-offColgate Enterprise06/21/2023
DOB NOWStructuralSigned-offDeveloping NY State05/30/2023
DOB NOWSupported ScaffoldSigned-offBayport Construction04/07/2023
DOB NOWConstruction FenceSigned-offDeveloping NY State03/30/2023
DOB NOWPlumbingSigned-offPrime Piping & Heating03/21/2023
DOB NOWSidewalk ShedSigned-offMetro Contracting NY03/07/2023
DOB NOWStructuralSigned-offDeveloping NY State02/24/2023
DOB NOWStructuralSigned-offDeveloping NY State02/13/2023
DOB NOWGeneral ConstructionPermit IssuedDeveloping NY State01/25/2023
DOB NOWFoundationSigned-offDeveloping NY State12/30/2022
DOB NOWSupport of ExcavationSigned-offDeveloping NY State12/13/2022
DOB NOWStandpipeSigned-offSafety Fire Sprinkler11/29/2022
DOB NOWPlumbingSigned-offYG Services08/03/2022
DOB NOWSprinklersSigned-offSafety Fire Sprinkler08/01/2022
DOB NOWGeneral ConstructionSigned-offDeveloping NY State07/21/2022
DOB NOWEarth WorkSigned-offDeveloping NY State05/06/2022
DOB NOWSupport of ExcavationSigned-offDeveloping NY State04/14/2022
DOB NOWConstruction FenceSigned-offDeveloping NY State04/06/2022
BISOTISSUEDFPS Contracting02/09/2004
BISOTISSUEDFPS Contracting02/02/2004
BISEQISSUEDYork Scaffold Equipment12/10/2003
BISPLISSUEDJD Masters Plumbing & Heating10/31/2003
BISOTISSUEDFPS Contracting10/31/2003
BISPLISSUEDIntercity Plumbing & Heating05/21/2003
BISOTISSUEDPlaza Construction04/02/2003
BISPLISSUEDTMS Plumbing & Heating06/25/1993
BISMHISSUEDED Brady Construction05/28/1993
+ 3 more permits on file
1 project · most recent 12/18/2025
Air Conditioning Systems Heating and Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
12/18/2025Signed-offDeveloping NY StateAir Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Daikin FTK12BXVJU 12,000 BTU · Fan Coil Indoor ×1
RK12BXVJU 12,000 BTU · Condensing Unit ×1
Heat / Cool
Daikin FXAQ07PVJU 7,500 BTU · Vrf Indoor ×169
FXAQ12PVJU 12,000 BTU · Vrf Indoor ×84
FXAQ18PVJU 18,000 BTU · Vrf Indoor ×50
RXTQ36TBVJUA 36,000 BTU · Vrf Outdoor ×46
FXAQ09PVJU 9,500 BTU · Vrf Indoor ×39
RXTQ48TBVJUA 48,000 BTU · Vrf Outdoor ×12
FXMQ36PBVJU 36,000 BTU · Vrf Indoor ×3
FXMQ30PBVJU 30,000 BTU · Vrf Indoor ×2
FXMQ48PBVJU 48,000 BTU · Vrf Indoor ×1
RXTQ60TBVJUA 60,000 BTU · Vrf Outdoor ×1
Heating
Berko SRA 1012DS 3,412 BTU · Electric Heater ×157
Qmark CSH-07A 7,860 BTU · Baseboard ×41
MUH03-8 10,200 BTU · Electric Heater ×4
Neptronic DEH-1 1 kW · Electric Heater ×2
DEH-2 2 kW · Electric Heater ×1
Ventilation
Pennbarry DX16Q2GP 2,000 CFM · Exhaust Fan ×18
DX13QGP 680 CFM · Exhaust Fan ×8
DW13QGP 360 CFM · Exhaust Fan ×2
SX085RCGP 200 CFM · Exhaust Fan ×2
SX275BC 10,560 CFM · Exhaust Fan ×1
Panasonic FV-0511VQ1 50 CFM · Exhaust Fan ×14
FV-11115VQ1 150 CFM · Exhaust Fan ×1
FV-30VQ3 290 CFM · Exhaust Fan ×1
Oxygen8 NOVA A16-H-I-ERV 600 CFM · Erv ×2
NOVA B22-V-0-ERV 800 CFM · Erv ×1
N/A N/A 255 CFM · Exhaust Fan ×1
1 project · most recent 12/18/2025
Sprinkler System
FiledStatusContractorScope
12/18/2025Signed-offSafety Fire SprinklerSprinkler System
1 project · most recent 12/18/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
12/18/2025Signed-offPrime Piping & HeatingGas, Storm, Water/Sanitary
7 projects · most recent 01/28/2026
General Wiring
FiledStatusContractorScope
01/28/2026CompleteDynamic Electrical Contractors—
09/09/2025CompleteDynamic Electrical ContractorsGeneral Wiring
08/14/2025CompleteDynamic Electrical ContractorsGeneral Wiring
07/10/2024CompleteEqual Electrical ContGeneral Wiring
07/28/2023CompleteDynamic Electrical Contractors—
06/20/2023CompleteNash Electric Services—
03/07/2023CompleteRichard Neu—
1 project · most recent 12/18/2025
Steel Concrete
FiledStatusContractorScope
12/18/2025Signed-offPrime Piping & HeatingSteel, Concrete
1 project · most recent 12/18/2025
Fence
FiledStatusContractorScope
12/18/2025Signed-offPrime Piping & HeatingFence
1 project · most recent 12/18/2025
Dewatering Earthwork
FiledStatusContractorScope
12/18/2025Signed-offPrime Piping & HeatingDewatering, Earthwork
▾Field Inspections (DOB CAP) — 16
DateTypeResultReport
10/16/2024Pass-Final CND-Occupancy InspectionPassView ↗
10/09/2024Fail-Final CND-Occupancy InspectionFailView ↗
08/29/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
07/08/2024Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve TestCertifiedView ↗
07/08/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/08/2024Certified StandPipe-Fire Pump (SD)-Fire Pump TestCertifiedView ↗
07/08/2024Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
07/01/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/01/2024Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
12/14/2023Pass-Final PL - More than 10 Requested FloorsPassView ↗
08/24/2023Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
08/24/2023Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
05/23/2023Pass-Final PL - UndergroundPassView ↗
12/15/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/30/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/23/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
01/08/2026Lighting in dwelling unitsSoorjbally Harilallenergy_progress
01/08/2026Fire-Resistance Rated ConstructionSoorjbally Harilallprogress
01/08/2026Energy Code Compliance InspectionsSoorjbally Harilallprogress
01/08/2026Exterior Insulation and Finish Systems (EIFS)Soorjbally Harilallspecial
01/08/2026Structural Stability – Alterations of existing buildingsSOORJBALLY HARILALLspecial
01/08/2026Alternative Materials - OTCR Buildings Bulletin NumberSOORJBALLY HARILALLspecial
01/08/2026Concrete - Cast-In-PlaceSOORJBALLY HARILALLspecial
01/08/2026Lighting controlsSoorjbally Harilallenergy_progress
01/08/2026Electrical motors and elevatorsSoorjbally Harilallenergy_progress
01/08/2026Fenestration air leakageSoorjbally Harilallenergy_progress
01/08/2026Fenestration and door U-factor and product ratingsSoorjbally Harilallenergy_progress
01/08/2026Exterior lighting powerSoorjbally Harilallenergy_progress
01/08/2026MeteringSoorjbally Harilallenergy_progress
01/08/2026Interior lighting powerSoorjbally Harilallenergy_progress
01/08/2026Air barrier — testing Soorjbally Harilallenergy_progress
01/08/2026Fenestration areasSoorjbally Harilallenergy_progress
01/08/2026Insulation placement and R valuesSoorjbally Harilallenergy_progress
01/08/2026Protection of exposed foundation insulationSoorjbally Harilallenergy_progress
01/08/2026Maintenance informationSoorjbally Harilallenergy_progress
01/08/2026Air barrier - visual inspectionSoorjbally Harilallenergy_progress
12/17/2025Fenestration air leakageSoorjbally Harilallenergy_progress
12/17/2025Protection of exposed foundation insulationSoorjbally Harilallenergy_progress
12/17/2025Lighting controlsSoorjbally Harilallenergy_progress
12/17/2025Lighting in dwelling unitsSoorjbally Harilallenergy_progress
12/17/2025Exterior Insulation and Finish Systems (EIFS)Soorjbally Harilallspecial
Latest 25 of 150.
▾Documents — 251 on file (BIS + DOB NOW)
▸Plans & Drawings33
▸DOB NOWPlans/Sketch33
08/26/2026Q00684765-A6Request digital key ↗
08/26/2026Q00684765-A3Request digital key ↗
08/26/2026Q00684765-P6Request digital key ↗
Showing 3 of 33 on file for this type
▸Applications & Permits8
▸BISPLAN / WORK APPROVAL APPLICATION7
06/07/2024440712597Open ↗
11/02/2023440712597Open ↗
11/01/2023440712597Open ↗
Showing 3 of 7 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
11/03/2023440712597Open ↗
▸Zoning, Tax Lot & Property Records27
▸DOB NOWRestrictive Declaration/Easement 116
08/26/2026Q00684765-A6Open ↗
08/26/2026Q00684765-P5Open ↗
08/15/2026Q00684765-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram5
08/26/2026Q00684765-A6Open ↗
08/15/2026Q00684765-I1Open ↗
08/15/2026Q00684765-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZoning Exhibit form (1-5)5
08/26/2026Q00684765-A6Open ↗
08/15/2026Q00684765-I1Open ↗
08/15/2026Q00684765-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026Q00684765-I1Open ↗
▸Seals & Professional Certifications110
▸DOB NOWSpecial Inspector Seal & Signature46
10/03/2026Q00684765-I1Open ↗
10/03/2026Q00684765-I1Open ↗
10/03/2026Q00684765-I1Open ↗
Showing 3 of 46 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature33
08/26/2026Q00684765-S5Open ↗
08/26/2026Q00684765-A6Open ↗
08/26/2026Q00684765-A4Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWProgress Inspector Seal & Signature29
10/03/2026Q00684765-I1Open ↗
10/03/2026Q00684765-I1Open ↗
09/01/2026Q00684765-P8Open ↗
Showing 3 of 29 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/16/2023440712597Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
05/16/2023440712597Open ↗
▸Trade Schedules & Equipment6
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)5
08/26/2026Q00684765-A6Open ↗
08/15/2026Q00684765-I1Open ↗
08/15/2026Q00684765-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWStandpipe Alarms Drawings1
08/15/2026Q00684765-I1—
▸Safety & Tenant Protection5
▸BISBPP: STREET TREES SITE PLAN1
11/03/2023440712597Open ↗
▸BISSTREET TREE CHECKLIST1
11/03/2023440712597Open ↗
▸DOB NOWStreet Tree Sign Off1
08/15/2026Q00684765-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/15/2026Q00684765-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/15/2026Q00684765-I1Open ↗
▸Environmental & Asbestos26
▸DOB NOWDEP ACP-5: Asbestos Assessment Report26
08/26/2026Q00684765-A3Open ↗
08/26/2026Q00684765-P6Open ↗
08/26/2026Q00684765-P5Open ↗
Showing 3 of 26 on file for this type
▸Energy Compliance3
▸DOB NOWPreliminary Commissioning Report Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
08/15/2026Q00684765-I1Open ↗
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT2
08/14/2026Q00684765-S2Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWTR4 Plot Diagram1
08/14/2026Q00684765-S2Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/14/2026Q00684765-S2Open ↗
▸DOB NOWConcrete Testing Exception Report1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs2
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION2
06/20/2024440712597Open ↗
06/20/2024440712597Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
11/03/2023440712597Open ↗
▸Other Documents23
▸DOB NOWProperty Ownership Certification6
08/26/2026Q00684765-A6Open ↗
08/15/2026Q00684765-I1Open ↗
08/15/2026Q00684765-P8Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/26/2026Q00684765-A6Open ↗
08/15/2026Q00684765-I1Open ↗
08/15/2026Q00684765-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial5
08/26/2026Q00684765-A6Open ↗
08/15/2026Q00684765-I1Open ↗
08/15/2026Q00684765-P2Open ↗
Showing 3 of 5 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION2
05/16/2023440712597Open ↗
05/16/2023440712597Open ↗
▸DOB NOWAdjoining Owners Notification2
08/14/2026Q00684765-S2Open ↗
Showing 1 of 2 on file for this type
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
11/03/2023440712597Open ↗
▸DOB NOWProject Specific General Liability (PGL1)1
08/15/2026Q00684765-I1Open ↗
▸DOB NOWFinal Survey1
08/15/2026Q00684765-I1Open ↗