| Owner | Filings | Most Recent |
|---|---|---|
| JEM REALTY MANAGEMENT | 18 | 07/08/2026 |
| JEM REALTY | 51 | 07/08/2026 |
| BILLY ENTERPRISES INC | 5 | 03/22/2026 |
| CONSTRUCTION SVS CON NY | 5 | 03/22/2026 |
| GOTHAM 149 REALTY | 31 | 03/22/2026 |
| START ELEVATOR INDUSTRIES | 1 | 03/22/2026 |
| GOTHAM 149TH REALTY LLC | 1 | 03/22/2026 |
| FORTUNE ESTATES | 19 | 03/22/2026 |
| THE OWNER OF | 1 | 03/22/2026 |
| M B CONTRACTING | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LCW ENGINEERING, P.C. | 3 | 11/07/2025 |
| BRUNSWICK ENGINEERING LLC | 2 | 04/14/2025 |
| CHUN FENG, ARCHITECT | 2 | 03/12/2024 |
| RAAD | 1 | 07/07/2022 |
| IW ARCHITECTURE, PLLC | 4 | 01/11/2022 |
| ALLAN KLEIN PA | 2 | 09/14/2021 |
| ARQUITECTURA VARELA | 2 | 08/27/2021 |
| MURRAY ENGINEERING PC | 2 | 08/04/2021 |
| HNY CONSULTING ENGINEERS LLC | 5 | 08/03/2021 |
| KEVIN C. GORE, AIA ARCHITECT | 2 | 08/03/2021 |
| RUSSELL M. BAUMANN, ARCHITECT | 2 | 07/15/2021 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 11/09/2020 |
| LESTER KATZ, NCARB | 1 | 05/28/2020 |
| V. SHAMES, P.E. | 1 | 12/10/2019 |
| LEON SKVIRSKY PE | 2 | 03/22/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 16 | 03/21/2026 |
| GREEN LIGHT EXPEDITING LLC | 8 | 03/21/2026 |
| NEW YORK SIGN CONSULTANTS | 8 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| BUILDING BROTHERS | 4 | 03/21/2026 |
| HIGH QUALITY 338 | 4 | 03/21/2026 |
| SKY MANAGEMENT GROUP | 2 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 2 | 03/21/2026 |
| M W EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DWORKIN CONSTRUCTION CORP. | General Contractor | 14 | 07/08/2026 |
| CONSTRUCTION SVS CON NY | General Contractor | 6 | 03/21/2026 |
| MAUCERI SIGN | Scaffold | 4 | 07/08/2026 |
| FC NEWLAND GENERAL CONTRA | General Contractor | 4 | 07/08/2026 |
| HIGH QUALITY CONSTRUCTION | General Contractor | 4 | 03/21/2026 |
| ENER-CON TECHNICAL SERVIC | General Contractor | 3 | 03/21/2026 |
| BILLY ENTERPRISES INC | General Contractor | 3 | 03/21/2026 |
| G&B PLUMBING&HEATING CORP | Plumbing | 2 | 07/08/2026 |
| GENOVESE, JOSEPH | Electrical | 2 | 03/21/2026 |
| GOING SIGN SVCNG | Scaffold | 2 | 07/08/2026 |
| GMD SHIPYARD CORP | Electrical | 2 | 03/21/2026 |
| RAMDATH, JAIDATH | Electrical | 2 | 03/21/2026 |
| SPENELLI, RICHARD | Electrical | 2 | 03/21/2026 |
| MORELL BUILDERS INC | General Contractor | 1 | 07/08/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 1 | 07/08/2026 |
| KA&C MECH LLC | Plumbing | 1 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 1 | 07/08/2026 |
| JIMENEZ LUIS | Electrical | 1 | 03/21/2026 |
| IRVING BAPTISTE | Electrical | 1 | 03/21/2026 |
| LAWRENCE MOMERN | Electrical | 1 | 03/21/2026 |
| LUIS JIMENEZ | Electrical | 1 | 03/21/2026 |
| YOUNG CHOE | Electrical | 1 | 03/21/2026 |
| CRAIG SAMUELS | Electrical | 1 | 03/21/2026 |
| EPOCH CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| BRONXDALE ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LCW ENGINEERING, PC | 1103 | 2 | 11/07/2025 |
| WINTON GROUP ARCHITECTURE | 4343 | 2 | 04/14/2025 |
| SQ. ARCH, LLC | 4802 | 2 | 03/12/2024 |
| NKM ENGINEERING PLLC | 6244 | 1 | 03/12/2024 |
| RAAD | 7727 | 1 | 07/07/2022 |
| JOSEPH MARTINES PE, PLLC | 1428 | 6 | 09/14/2021 |
| MURRAY ENGINEERING PC | 1434 | 2 | 08/04/2021 |
| CONCRETE SOLUTIONS LAB CO | 5344 | 2 | 08/03/2021 |
| GREENLINE DEVELOPERS, LLC | 3447 | 1 | 12/10/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | KALE CONSTRUCTION INC | 11/12/2025 |
| DOB NOW | Plumbing | Permit Issued | WATSON'S PLBG, HTG, & BDG | 11/06/2025 |
| DOB NOW | General Construction | Permit Issued | EPOCH CONSTRUCTION INC | 08/25/2025 |
| DOB NOW | Plumbing | Signed-off | KA&C MECH LLC | 04/10/2025 |
| DOB NOW | General Construction | Signed-off | HIGH QUALITY CONSTRUCTION | 03/19/2024 |
| DOB NOW | Mechanical Systems | Signed-off | HIGH QUALITY CONSTRUCTION | 03/19/2024 |
| DOB NOW | Plumbing | Signed-off | AMERICAN STANDARD P&H CORORP. | 03/14/2024 |
| DOB NOW | Mechanical Systems | Signed-off | MORELL BUILDERS INC | 02/14/2023 |
| DOB NOW | Sign | Signed-off | MAUCERI SIGN CO., INC | 01/20/2022 |
| DOB NOW | Sign | Signed-off | MAUCERI SIGN CO., INC | 01/12/2022 |
| DOB NOW | Sign | Signed-off | MAUCERI SIGN CO., INC | 01/11/2022 |
| DOB NOW | Sign | Signed-off | MAUCERI SIGN CO., INC | 01/11/2022 |
| DOB NOW | Plumbing | Signed-off | DARINKO PLUMBING CO | 11/09/2021 |
| DOB NOW | Mechanical Systems | Signed-off | DWORKIN CONSTRUCTION CORP. | 10/20/2021 |
| DOB NOW | Construction Fence | Signed-off | DWORKIN CONSTRUCTION CORP. | 10/20/2021 |
| DOB NOW | Structural | Signed-off | DWORKIN CONSTRUCTION CORP. | 10/20/2021 |
| DOB NOW | General Construction | Signed-off | DWORKIN CONSTRUCTION CORP. | 10/20/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | CONSTRUCTION SVS CON NY | 08/30/2021 |
| DOB NOW | Construction Fence | Permit Issued | CONSTRUCTION SVS CON NY | 08/25/2021 |
| DOB NOW | Plumbing | Signed-off | DARINKO PLUMBING CO | 07/28/2021 |
| DOB NOW | Construction Fence | Signed-off | DWORKIN CONSTRUCTION CORP. | 07/26/2021 |
| DOB NOW | Structural | Signed-off | DWORKIN CONSTRUCTION CORP. | 07/23/2021 |
| DOB NOW | Mechanical Systems | Signed-off | DWORKIN CONSTRUCTION CORP. | 07/22/2021 |
| DOB NOW | General Construction | Signed-off | DWORKIN CONSTRUCTION CORP. | 07/22/2021 |
| DOB NOW | General Construction | Signed-off | FC NEWLAND GENERAL CONTRA | 07/01/2021 |
| DOB NOW | General Construction | Signed-off | FC NEWLAND GENERAL CONTRA | 06/22/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | BILLY ENTERPRISES INC | 11/10/2020 |
| DOB NOW | Mechanical Systems | Signed-off | ENER-CON TECHNICAL SERVIC | 12/11/2019 |
| DOB NOW | Sign | Signed-off | POLSINELLI, HENRY | 03/26/2018 |
| DOB NOW | Sign | Signed-off | POLSINELLI, HENRY | 01/03/2018 |
| BIS | OT | ISSUED | CREATE NYC CONTRACTING | 05/03/2019 |
| BIS | MH | ISSUED | AQEL SHEET METAL INC | 04/25/2019 |
| BIS | OT | ISSUED | SJ EMPIRE CORP | 03/28/2018 |
| BIS | OT | ISSUED | THE VENETIAN GROUP LLC | 08/29/2017 |
| BIS | MH | ISSUED | THE VENETIAN GROUP LLC | 08/29/2017 |
| BIS | PL | ISSUED | J. CAIAZZO PLBG & HTG COR | 08/18/2017 |
| BIS | OT | ISSUED | THE VENETIAN GROUP LLC | 08/15/2017 |
| BIS | MH | ISSUED | THE VENETIAN GROUP LLC | 08/15/2017 |
| BIS | EQ | ISSUED | THE VENETIAN GROUP LLC | 08/15/2017 |
| BIS | OT | ISSUED | BROOKLYN HOME IMPROVEMENT | 06/06/2017 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/07/2025 | Permit Issued | KALE CONSTRUCTION INC | Ventilation Systems | Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/07/2025 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/07/2025 | Permit Issued | WATSON'S PLBG, HTG, & BDG | Gas, Plumbing-Sprinkler, Water/Sanitary |
| 04/14/2025 | Signed-off | KA&C MECH LLC | Gas, Water/Sanitary |
| 05/28/2020 | — | — | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2021 | Complete | LTC ELEC'L CONTR'G LLC | General Wiring |
| 03/08/2021 | Complete | WILLDAN ELECTRICAL OF NY | — |
| 03/04/2021 | Complete | WILLDAN ELECTRICAL OF NY | — |
| 03/13/2020 | Complete | WILLDAN ELECTRICAL OF NY | — |
| 10/21/2019 | Complete | BRONXDALE ELECTRIC INC | General Wiring |
| 03/04/2019 | Complete | WILLDAN ELECTRICAL OF NY | General Wiring |
| 12/19/2018 | Permit Issued | THE GOING SERVICING CO IN | — |
| 12/19/2018 | Permit Issued | THE GOING SERVICING CO IN | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2021 | Permit Issued | CONSTRUCTION SVS CON NY | Sidewalk Shed |
| 08/25/2021 | Permit Issued | CONSTRUCTION SVS CON NY | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/07/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/11/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/09/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/05/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/23/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/23/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/17/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/11/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/21/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/10/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/10/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/03/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/24/2025 | Shutoff dampers | luis wong | energy_progress |
| 07/24/2025 | Energy Code Compliance Inspections | luis wong | progress |
| 07/24/2025 | HVAC-R and service water piping design and insulation | luis wong | energy_progress |
| 07/24/2025 | HVAC-R and service water heating equipment | luis wong | energy_progress |
| 07/24/2025 | Mechanical Systems | luis wong | special |
| 07/24/2025 | Final | luis wong | progress |
| 07/24/2025 | Energy Code Compliance Inspections | luis wong | progress |
| 07/24/2025 | Fire-Resistant Penetrations and Joints | luis wong | special |
| 07/24/2025 | Final | luis wong | progress |
| 04/13/2025 | HVAC-R and service water piping design and insulation | Vladimir Kaushansky | energy_progress |
| 04/13/2025 | HVAC-R and service water heating system controls | Vladimir Kaushansky | energy_progress |
| 04/13/2025 | HVAC-R and service water heating equipment | Vladimir Kaushansky | energy_progress |
| 04/13/2025 | Fire-Resistant Penetrations and Joints | Vladimir Kaushansky | special |
| 04/13/2025 | Maintenance information | Vladimir Kaushansky | energy_progress |
| 04/13/2025 | Post-installed Anchors | Vladimir Kaushansky | special |
| 03/06/2024 | Mechanical Systems | NARESH MAHANGU | special |
| 03/06/2024 | Fenestration air leakage | Chun Feng | energy_progress |
| 03/06/2024 | HVAC-R and service water piping design and insulation | Chun Feng | energy_progress |
| 03/06/2024 | Duct leakage testing, insulation and design | Chun Feng | energy_progress |
| 03/06/2024 | HVAC-R and service water heating system controls | Chun Feng | energy_progress |
| 03/06/2024 | HVAC-R and service water heating equipment | Chun Feng | energy_progress |
| 03/06/2024 | Insulation placement and R values | Chun Feng | energy_progress |
| 03/06/2024 | Fenestration areas | Chun Feng | energy_progress |
| 03/06/2024 | Final | Chun Feng | progress |
| 03/06/2024 | Fire-Resistant Penetrations and Joints | Chun Feng | special |