| Owner | Filings | Most Recent |
|---|---|---|
| 1 OAK CONTRACTING | 32 | 07/08/2026 |
| SBGC | 3 | 03/22/2026 |
| COLGATE ENTERPRISE | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/19/2019 | $15.2M | — | GANESH MANAGEMENT LLC → LIC OWNER LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| MOTTOLA RINI ENGINEERS | 6 | 01/09/2026 |
| FOGARTY FINGER ARCHITECTURE PLLC | 1 | 10/03/2024 |
| MIRELLA BOSELLI ARCHITECT | 1 | 07/09/2024 |
| TOHFAZ UDDIN PE PC | 1 | 09/15/2020 |
| DEROSIER ENGINEERING, LLC | 1 | 05/15/2020 |
| KZ ENGINEERING, P.C | 2 | 04/24/2020 |
| VENTROP ENGINEERING CONSULTING GROU | 1 | 01/18/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 18 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| COLGATE ENTERPRISE CORP | General Contractor | 7 | 07/08/2026 |
| COOPER WORKS INC | General Contractor | 5 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 3 | 07/08/2026 |
| ACCURATE MECHANICAL INC | Fire Protection | 1 | 06/27/2026 |
| M.R. ELEC'L SERVICE LLC | Electrical | 1 | 03/22/2026 |
| SBGC LLC | General Contractor | 1 | 07/08/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| METROSPEC SIA | 6420 | 6 | 01/09/2026 |
| MOTTOLA RINI ENGINEERS, P | 3251 | 4 | 07/28/2025 |
| ANGELOS GEORGOPOULOS, P.C | 2955 | 1 | 07/09/2024 |
| ATLANTIC ENGINEERINGLABOR | 1381 | 1 | 01/18/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | COOPER WORKS | 11/07/2025 |
| DOB NOW | Mechanical Systems | Signed-off | COOPER WORKS | 05/02/2025 |
| DOB NOW | Plumbing | Signed-off | ANTHONY DISABATO | 04/14/2025 |
| DOB NOW | General Construction | Permit Issued | COOPER WORKS | 04/14/2025 |
| DOB NOW | Sprinklers | Signed-off | ACCURATE MECHANICAL INC | 12/23/2024 |
| DOB NOW | Structural | Signed-off | COOPER WORKS | 12/20/2024 |
| DOB NOW | Standpipe | Signed-off | A M B MECHANICAL INC | 09/16/2021 |
| DOB NOW | Curb Cut | Signed-off | SBGC LLC | 05/25/2021 |
| DOB NOW | Construction Fence | Signed-off | COLGATE ENTERPRISE CORP | 04/01/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | COLGATE ENTERPRISE CORP | 04/01/2021 |
| DOB NOW | Standpipe | Signed-off | A M B MECHANICAL INC | 12/01/2020 |
| DOB NOW | Supported Scaffold | Signed-off | COLGATE ENTERPRISE CORP | 09/16/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | COLGATE ENTERPRISE CORP | 04/27/2020 |
| DOB NOW | Construction Fence | Signed-off | COLGATE ENTERPRISE CORP | 04/27/2020 |
| DOB NOW | Standpipe | Signed-off | A M B MECHANICAL INC | 03/19/2020 |
| BIS | PL | ISSUED | PRIME PIPING & HEATING IN | 04/14/2022 |
| BIS | OT | ISSUED | SBGC LLC | 04/12/2022 |
| BIS | — | ISSUED | SBGC LLC | 07/23/2021 |
| BIS | PL | ISSUED | RIGID PLUMBING CONT INC | 03/05/2021 |
| BIS | OT | ISSUED | SBGC LLC | 10/16/2020 |
| BIS | — | ISSUED | SBGC LLC | 10/13/2020 |
| BIS | EQ | ISSUED | COLGATE ENTERPRISE CORP | 09/25/2020 |
| BIS | EQ | ISSUED | COLGATE ENTERPRISE CORP | 08/21/2020 |
| BIS | PL | ISSUED | PRIME PIPING & HEATING IN | 05/20/2020 |
| BIS | — | ISSUED | 1 OAK CONTRACTING LLC | 05/18/2020 |
| BIS | — | ISSUED | 1 OAK CONTRACTING LLC | 03/18/2020 |
| BIS | OT | ISSUED | 1 OAK CONTRACTING LLC | 02/24/2020 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/09/2026 | Signed-off | COOPER WORKS INC | Air Conditioning Systems, Ventilation Systems | Cooling Mitsubishi Electric MXZ-SM60NAM2-U1 60,000 BTU · Vrf Outdoor ×2 MXZ-SM96TAM-U1 96,000 BTU · Vrf Outdoor ×2 MXZ-SM96TAM-UA 96,000 BTU · Vrf Outdoor ×1 Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/09/2026 | Signed-off | ACCURATE MECHANICAL INC | 84 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/09/2026 | Signed-off | QPR MECHANICAL INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2025 | Complete | GREEN APPLE ELECL SVCS LL | General Wiring |
| 10/21/2024 | Permit Issued | HYLAN DATACOM & ELECL LLC | 1 meters, 1 new_meters |
| 08/18/2024 | Complete | GREEN APPLE ELECL SVCS LL | General Wiring |
| 01/20/2022 | Complete | M.R. ELEC'L SERVICE LLC | General Wiring |
| 08/14/2020 | Complete | NASH ELECTRIC SERVICES IN | — |
| 07/15/2020 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 04/23/2020 | Complete | NASH ELECTRIC SERVICES IN | — |
| 03/18/2020 | Complete | M.R. ELEC'L SERVICE LLC | 1 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/14/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/20/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/16/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/01/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/26/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/18/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/21/2022 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 09/22/2022 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/02/2026 | Tenant Protection Plan Compliance | JOSEPH YOUNG | special |
| 02/02/2026 | Fenestration and door U-factor and product ratings | JOSEPH YOUNG | energy_progress |
| 02/02/2026 | Fenestration air leakage | JOSEPH YOUNG | energy_progress |
| 02/02/2026 | Fenestration areas | JOSEPH YOUNG | energy_progress |
| 02/02/2026 | Lighting controls | JOSEPH YOUNG | energy_progress |
| 02/02/2026 | Air barrier - visual inspection | JOSEPH YOUNG | energy_progress |
| 02/02/2026 | Interior lighting power | JOSEPH YOUNG | energy_progress |
| 02/02/2026 | Fire-Resistance Rated Construction | JOSEPH YOUNG | progress |
| 02/02/2026 | Final | JOSEPH YOUNG | progress |
| 02/02/2026 | Fire-Resistant Penetrations and Joints | JOSEPH YOUNG | special |
| 01/08/2026 | Tenant Protection Plan Compliance | Michael Risbergs | special |
| 01/08/2026 | Fire-Resistant Penetrations and Joints | Michael Risbergs | special |
| 01/08/2026 | Final | Michael Risbergs | progress |
| 01/08/2026 | Fire-Resistance Rated Construction | Michael Risbergs | progress |
| 01/08/2026 | Air barrier - visual inspection | JOSEPH YOUNG | energy_progress |
| 01/08/2026 | Fenestration and door U-factor and product ratings | JOSEPH YOUNG | energy_progress |
| 01/08/2026 | Interior lighting power | JOSEPH YOUNG | energy_progress |
| 01/08/2026 | Fenestration air leakage | JOSEPH YOUNG | energy_progress |
| 01/08/2026 | Lighting controls | JOSEPH YOUNG | energy_progress |
| 01/08/2026 | Fenestration areas | JOSEPH YOUNG | energy_progress |
| 08/28/2025 | HVAC-R and service water heating equipment | Anthony Rini, III | energy_progress |
| 08/28/2025 | HVAC-R and service water piping design and insulation | Anthony Rini, III | energy_progress |
| 08/28/2025 | HVAC-R and service water heating system controls | Anthony Rini, III | energy_progress |
| 08/28/2025 | Tenant Protection Plan Compliance | JOSEPH YOUNG | special |
| 08/28/2025 | Fire-Resistant Penetrations and Joints | Anthony Rini, III | special |