| Firm | Filings | Most Recent |
|---|---|---|
| ERIC SAFYAN ARCHITECT PC | 3 | 01/15/2026 |
| BARRY STRUCTURAL ENGINEERING, PLLC | 2 | 11/01/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| JOSEPH FELLNER | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| C.I. CONTRACTING CORP | General Contractor | 3 | 04/09/2026 |
| L.L.G. PLBG & HTG INC | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BARRY STRUCTURAL ENGINEER | 749 | 3 | 11/01/2025 |
| ERIC SAFYAN ARCHITECTPC | 3248 | 1 | 09/22/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | L.L.G. PLBG & HTG INC | 01/07/2026 |
| DOB NOW | General Construction | Permit Issued | C.I. CONTRACTING CORP | 01/06/2026 |
| DOB NOW | Foundation | Signed-off | C.I. CONTRACTING CORP | 11/19/2025 |
| DOB NOW | Structural | Signed-off | C.I. CONTRACTING CORP | 11/18/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/15/2026 | Permit Issued | C.I. CONTRACTING CORP | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/15/2026 | Permit Issued | L.L.G. PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/07/2025 | Permit Issued | SCIENTIFIC ELEC. CO. INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/15/2026 | Permit Issued | L.L.G. PLBG & HTG INC | Steel, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/25/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/16/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/23/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/16/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 12/08/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/15/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/05/2026 | Permanent certificate | Eric Safyan | energy_progress |
| 01/05/2026 | Maintenance information | Eric Safyan | energy_progress |
| 01/05/2026 | Energy Code Compliance Inspections | Eric Safyan | progress |
| 01/05/2026 | HVAC-R and service water heating system controls | Eric Safyan | energy_progress |
| 01/05/2026 | HVAC-R and service water piping design and insulation | Eric Safyan | energy_progress |
| 01/05/2026 | HVAC-R and service water heating equipment | Eric Safyan | energy_progress |
| 10/08/2025 | Structural Stability – Alterations of existing buildings | MICHAEL BARRY | special |
| 10/08/2025 | Structural Steel - Welding | MICHAEL BARRY | special |
| 10/08/2025 | Structural Steel - High Strength Bolting | MICHAEL BARRY | special |
| 10/08/2025 | Structural Steel - Details | MICHAEL BARRY | special |
| 10/08/2025 | Structural Stability – Alterations of existing buildings | MICHAEL BARRY | special |
| 10/08/2025 | Concrete - Cast-In-Place | MICHAEL BARRY | special |
| 10/08/2025 | Construction Utilizing CLT or SCL, Type IV | MICHAEL BARRY | special |
| 10/06/2025 | Final | MICHAEL BARRY | progress |
| 10/06/2025 | Final | MICHAEL BARRY | progress |
| 10/06/2025 | Footing and Foundation | MICHAEL BARRY | progress |
| 09/19/2025 | Fenestration air leakage | Eric Safyan | energy_progress |
| 09/19/2025 | Lighting in dwelling units | Eric Safyan | energy_progress |
| 09/19/2025 | Protection of exposed foundation insulation | Eric Safyan | energy_progress |
| 09/19/2025 | Insulation placement and R values | Eric Safyan | energy_progress |
| 09/19/2025 | Fenestration areas | Eric Safyan | energy_progress |
| 09/19/2025 | Permanent certificate | Eric Safyan | energy_progress |
| 09/19/2025 | Fenestration and door U-factor and product ratings | Eric Safyan | energy_progress |
| 09/19/2025 | Maintenance information | Eric Safyan | energy_progress |
| 09/19/2025 | Air barrier - visual inspection | Eric Safyan | energy_progress |