| Owner | Filings | Most Recent |
|---|---|---|
| Department of Health & Mental Hygiene | 189 | 07/08/2026 |
| Harlem Hospital Center | 13 | 03/21/2026 |
| Hospital Health | 3 | 03/21/2026 |
| NYC School Construction Authority | 1 | 03/22/2026 |
| Rdeinc | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| WSP | 23 | 04/08/2026 |
| Murdoch Engineering | 11 | 03/12/2026 |
| JFK Associates | 3 | 10/23/2025 |
| Howard I Shapiro & Associates | 4 | 08/19/2025 |
| Allen Dialberto PE | 24 | 04/22/2025 |
| Universal Builders Supply | 10 | 02/24/2025 |
| Sean P. Cunningham PE | 3 | 12/26/2024 |
| LERA Consulting Structural Engineering | 3 | 10/23/2024 |
| Skidmore Owings & Merrill | 1 | 06/11/2024 |
| KZ Engineering | 1 | 06/05/2023 |
| Age Engineering | 3 | 05/19/2022 |
| 360 Engineering | 6 | 02/28/2022 |
| Wavic Engineering | 2 | 05/19/2021 |
| Ikra Consulting | 2 | 09/24/2020 |
| Paul Perdek, Prof. Engineering | 2 | 01/02/2020 |
| Asif Jamil, RA | 1 | 03/29/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Howard I Shapiro Associates | 8 | 03/21/2026 |
| Dennis Kim | 22 | 03/21/2026 |
| Eurocelt Expediting | 20 | 03/21/2026 |
| Louis Striar | 22 | 03/21/2026 |
| Outsource Consultants | 14 | 03/21/2026 |
| High Point Piping Protection | 6 | 03/21/2026 |
| Professional Design Consultants | 4 | 03/21/2026 |
| Russo Development Enterprises | 3 | 03/21/2026 |
| AE Design Solution | 4 | 03/21/2026 |
| Rennon Construction | 2 | 03/21/2026 |
| Welkin Enterprises | 4 | 03/21/2026 |
| Synergy Building Consultants | 1 | 03/21/2026 |
| AK Consulting Services | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Universal Builders Supply | Scaffold | 16 | 07/08/2026 |
| Current Fire Protection | Fire Protection | 11 | 07/08/2026 |
| Greg Logistics | Scaffold | 10 | 07/08/2026 |
| Skanska USA Building | General Contractor | 8 | 07/08/2026 |
| Rennon Construction | Scaffold | 6 | 07/08/2026 |
| PJP Installers | Scaffold | 6 | 07/08/2026 |
| Active Signs | Sign hanger | 6 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 4 | 07/08/2026 |
| Russo Development Enterprises | Scaffold | 3 | 03/21/2026 |
| Welkin Enterprises | Plumbing | 2 | 07/08/2026 |
| Northeast Electrical Contractors | Electrical | 2 | 03/22/2026 |
| Pace Plumbing | Plumbing | 2 | 07/08/2026 |
| R & R Scaffolding | Scaffold | 1 | 04/09/2026 |
| Russo Development Enterprises | General Contractor | 1 | 07/08/2026 |
| Starr Industries | Scaffold | 1 | 07/08/2026 |
| Stanco System Electrical Cont | Electrical | 1 | 03/22/2026 |
| Multi-Phase Electrical Services | Electrical | 1 | 03/22/2026 |
| Alafogiannis Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Magriples James | Electrical | 1 | 03/21/2026 |
| Jemco Electric Contractors | Electrical | 1 | 03/21/2026 |
| Lintech Electric | Electrical | 1 | 03/22/2026 |
| Pal Environmental Safety | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Bureau Veritas Na | 6902 | 29 | 12/22/2025 |
| Advanced Engineering & | 1224 | 2 | 08/29/2025 |
| 360 Engineering | 7496 | 4 | 02/28/2022 |
| Age Engineering | 6695 | 2 | 09/02/2021 |
| Wavic Engineering | 1733 | 1 | 03/11/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | Active Signs | 03/20/2026 |
| DOB NOW | Sign | Signed-off | Active Signs | 02/09/2026 |
| DOB NOW | Sign | Signed-off | Active Signs | 02/06/2026 |
| DOB NOW | Sign | Signed-off | Active Signs | 02/06/2026 |
| DOB NOW | Sign | Signed-off | Active Signs | 02/06/2026 |
| DOB NOW | Sign | Signed-off | Active Signs | 02/06/2026 |
| DOB NOW | Plumbing | Permit Issued | Par Plumbing Co | 10/22/2025 |
| DOB NOW | Boiler Equipment | Signed-off | RB Heating Consulting Group | 09/04/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | R & R Scaffolding | 08/19/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | Spyder Window Cleaning | 08/18/2025 |
| DOB NOW | Sprinklers | Signed-off | Current Fire Protection I | 05/06/2025 |
| DOB NOW | Standpipe | Signed-off | Current Fire Protection I | 05/06/2025 |
| DOB NOW | Standpipe | Signed-off | Current Fire Protection I | 05/06/2025 |
| DOB NOW | Boiler Equipment | Signed-off | Alafogiannis Plumbing & Heating | 04/17/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | Universal Build Supp | 04/08/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | Spyder Window Cleaning | 03/14/2025 |
| DOB NOW | Construction Fence | Signed-off | Universal Build Supp | 02/20/2025 |
| DOB NOW | Structural | Signed-off | Skanska USA Building | 02/13/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Skanska USA Building | 02/13/2025 |
| DOB NOW | Sprinklers | Signed-off | Current Fire Protection I | 01/02/2025 |
| DOB NOW | Boiler Equipment | Signed-off | RB Heating Consulting Group | 12/19/2024 |
| DOB NOW | Supported Scaffold | Signed-off | Universal Build Supp | 11/14/2024 |
| DOB NOW | Plumbing | Permit Issued | Par Plumbing Co | 11/04/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Universal Build Supp | 10/17/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Greg Logistics | 09/29/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | Greg Logistics | 09/27/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | Greg Logistics | 09/27/2024 |
| DOB NOW | Boiler Equipment | Signed-off | RB Heating Consulting Group | 08/01/2024 |
| DOB NOW | Supported Scaffold | Signed-off | Universal Build Supp | 07/30/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Pal Environmental Safety | 07/22/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | Greg Logistics | 07/18/2024 |
| DOB NOW | Sprinklers | Signed-off | Current Fire Protection I | 05/06/2024 |
| DOB NOW | Standpipe | Signed-off | Current Fire Protection I | 05/06/2024 |
| DOB NOW | Standpipe | Signed-off | Current Fire Protection I | 05/06/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Universal Build Supp | 04/11/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Greg Logistics | 04/02/2024 |
| DOB NOW | Plumbing | Permit Issued | Par Plumbing Co | 02/29/2024 |
| DOB NOW | Construction Fence | Signed-off | Universal Build Supp | 02/29/2024 |
| DOB NOW | Structural | Signed-off | Skanska USA Building | 02/06/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Skanska USA Building | 02/06/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/08/2026 | — | — | Ventilation Systems | — |
| 10/29/2025 | Signed-off | Skanska USA Building | Air Conditioning Systems, Associated Ducts and Piping, Cooling Towers, Generators | Cooling __Junk__ ×18 Mitsubishi Electric PUHY-EP96TNU-A1 6,700 CFM · Vrf Outdoor ×8 PKFY-P30NKMU-E2 6,700 CFM · Vrf Indoor ×8 PFFY-P18NEMU-E 459 CFM · Vrf Indoor ×6 PFFY-P12-NEMU-E 299 CFM · Vrf Indoor ×2 PKFY-P06NLMU-E 299 CFM · Vrf Indoor ×2 PQHY-P72YLMU-A1 6 tons · Vrf Outdoor ×2 York (9-1, 8-1, 7-1, 6-1, 5-1, 3-4) FHF-D 33,400 BTU · Fan Coil Indoor ×12 (10-2, 4-1, 3-3, 2-1, 1-1) FHF-D 30,900 BTU · Fan Coil Indoor ×10 (1-1, 1-2, 1-3) AHD-12 51,920 BTU · Exhaust Fan ×6 (3-6,2-2,2-3) FHF-D 13,600 CFM · Fan Coil Indoor ×6 (10-1, 3-5) FHF-D 23,750 CFM · Fan Coil Indoor ×4 (2-1,2) AVD 76,125 BTU · Exhaust Fan ×4 Above Air (3-1,2) MCC-018X-4-000-EC-DFB-CV-4R-1A 49,000 BTU ×4 Cemline W410USG2448-CBO-7 600 kW · Generator ×4 Heating Haakon N/A 270,800 BTU ×6 Modine (CR-LT-1) J0000003358, (CR-HT-1) J0000003359 2,662 CFM · Radiant ×4 Ventilation Carrier 42BHE06HG4R60603CE 17,874 BTU · Fan Coil Indoor ×18 Haakkon Z-D-35E-080 28,000 CFM · Ahu ×12 Refrigeration — 19DV-H23H234425H5 710 tons · Chiller ×12 York YZ-MA068BV063P102HAS 710 tons · Chiller ×8 Cooling Tower Ducts & Piping Greenheck VECTOR-CS-30-10-11 10,000 CFM · Exhaust Fan ×18 VECTOR-CS-44-10-11 32,000 CFM · Exhaust Fan ×18 ( 1-6) VEKTOR-C5-44-400-X 32,000 CFM · Exhaust Fan ×12 (1-4) VK--CD-30-STACK 12,000 CFM · Exhaust Fan ×8 Other Greenheck (EXF-BSL3R-R-5 & EXF-BSL3R-R-6) VK--CD-15-STACK 2,500 CFM · Exhaust Fan ×4 Generators Caterpillar 3516E 3,000 kW · Generator ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/23/2025 | Signed-off | Current Fire Protection I | 1,811 heads, 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/23/2025 | — | — | — |
| 10/21/2025 | Permit Issued | Par Plumbing Co | Gas, Medical Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2026 | Complete | B & G Electrical Contracting of NY I | General Wiring |
| 04/09/2026 | Complete | G-Squared Electric | General Wiring |
| 11/17/2025 | Complete | Marcel Electrical Contracting | — |
| 11/13/2025 | Complete | Milad Contracting | — |
| 07/31/2025 | Complete | Fred Geller Electrical | 3 meters, 3 new_meters |
| 06/13/2025 | Permit Issued | Fred Geller Electrical | General Wiring |
| 10/25/2024 | Complete | Fred Geller Electrical | — |
| 06/12/2023 | Complete | Multi-Phase Electrical Services | 1 meters, 1 new_meters |
| 04/26/2023 | Complete | Fred Geller Electrical | — |
| 06/20/2022 | Complete | Egg Electric | — |
| 12/02/2021 | Complete | Northeast Electrical Contractors | — |
| 11/30/2021 | Complete | Northeast Electrical Contractors | — |
| 06/17/2021 | Complete | Stanco System Electrical Cont | — |
| 07/30/2020 | Complete | Northeast Electrical Contractors | — |
| 01/14/2020 | Complete | Stanco System Electrical Cont | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2025 | Permit Issued | Greg Logistics | Suspended Scaffold (SC) |
| 02/25/2025 | Signed-off | Greg Logistics | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/31/2025 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 11/14/2025 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 11/14/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/09/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/07/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/28/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/23/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/21/2025 | Pass-Final PL - Co-Generator | Pass | View ↗ |
| 05/07/2025 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 03/10/2025 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 03/07/2025 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 02/26/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/26/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 02/24/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/13/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/12/2025 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 02/10/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/10/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/07/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 06/07/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 02/11/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/11/2022 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 02/11/2022 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/07/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 04/07/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 04/07/2026 | Shutoff dampers | — | energy_progress |
| 03/30/2026 | Final | — | progress |
| 03/30/2026 | Mechanical Systems | — | special |
| 03/13/2026 | Final | JERE MURDOCH | progress |
| 03/13/2026 | Final | JERE MURDOCH | progress |
| 03/13/2026 | Final | JERE MURDOCH | progress |
| 03/13/2026 | Final | JERE MURDOCH | progress |
| 03/12/2026 | Final | JERE MURDOCH | progress |
| 03/05/2026 | Final | JERE MURDOCH | progress |
| 03/05/2026 | Final | JERE MURDOCH | progress |
| 03/05/2026 | Final | JERE MURDOCH | progress |
| 03/05/2026 | Final | JERE MURDOCH | progress |
| 01/09/2026 | Fuel-Oil Storage and Fuel-Oil Piping Systems | IBRAHIM MOURAD | special |
| 01/09/2026 | Heating Systems | IBRAHIM MOURAD | special |
| 01/09/2026 | Maintenance information | IBRAHIM MOURAD | energy_progress |
| 01/09/2026 | HVAC and service water heating system controls | IBRAHIM MOURAD | energy_progress |
| 01/09/2026 | HVAC and service water heating equipment | IBRAHIM MOURAD | energy_progress |
| 12/24/2025 | Heating Systems | IBRAHIM MOURAD | special |
| 12/22/2025 | Heating Systems | IBRAHIM MOURAD | special |
| 12/22/2025 | HVAC and service water heating equipment | IBRAHIM MOURAD | energy_progress |
| 12/22/2025 | HVAC and service water heating system controls | IBRAHIM MOURAD | energy_progress |
| 12/22/2025 | Maintenance information | IBRAHIM MOURAD | energy_progress |
| 12/22/2025 | Fuel-Oil Storage and Fuel-Oil Piping Systems | IBRAHIM MOURAD | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| New York City Public Health Laboratory | Laboratory | Cellar, Floors 1–10, Mezzanine, Roof | Project M01380275 Project M01305187 Project M01305189 Project M01305190 Project M01305191 Project M01305192 Project M01305193 Project M00739729 Project M00711734 Project M00369013 Project M00369021 Project M00341220 |
| Public Health Lab | Laboratory | Floors 4–9, Roof | Project M01081451 Project M00994581 |