| Owner | Filings | Most Recent |
|---|---|---|
| 1163 FULTON REALTY | 88 | 07/08/2026 |
| OWNER'S REP | 10 | 07/08/2026 |
| THB CUSTOM BUILDERS | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MARK WEINBERGER ARCHITECT PLLC | 8 | 10/03/2025 |
| CHOSEN MEP, CORP. | 8 | 06/30/2025 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 12/06/2023 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 5 | 11/02/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| XPDITE GROUP LLC (104) | 21 | 03/21/2026 |
| THE GREEN STUDIO | 1 | 03/21/2026 |
| XPDITE GROUP 103 | 6 | 03/21/2026 |
| XPDITE GROUP LLC 104 | 3 | 03/21/2026 |
| MILLENNIUM DESIGNS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| THB CUSTOM BUILDERS INC | General Contractor | 26 | 07/08/2026 |
| YAFE MEOD CORP | General Contractor | 9 | 07/08/2026 |
| SAT CONSTRUCTION SERVICES | General Contractor | 7 | 07/08/2026 |
| GWT ENTERPRISES INC | General Contractor | 6 | 03/21/2026 |
| REAL LAND GROUP LLC | General Contractor | 5 | 07/08/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 4 | 07/08/2026 |
| EMPIRE PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| FRIED ELECTRIC CO. | Electrical | 2 | 03/22/2026 |
| PIPING & PLUMBING SOLUTIO | Fire Protection | 2 | 07/08/2026 |
| DNA PLUMBING CONTR. INC | Plumbing | 1 | 07/08/2026 |
| ENERCHARGE ELECTRIC CONT | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TROLYDIA TESTING & INSPEC | 4422 | 17 | 10/03/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | THB CUSTOM BUILDERS INC | 05/21/2025 |
| DOB NOW | General Construction | Permit Issued | THB CUSTOM BUILDERS INC | 02/14/2025 |
| DOB NOW | General Construction | Permit Issued | THB CUSTOM BUILDERS INC | 02/13/2025 |
| DOB NOW | Construction Fence | Signed-off | THB CUSTOM BUILDERS INC | 02/11/2025 |
| DOB NOW | Plumbing | Signed-off | EMPIRE PLUMBING INC | 01/16/2025 |
| DOB NOW | Sprinklers | Signed-off | EMPIRE PLUMBING INC | 01/16/2025 |
| DOB NOW | Structural | Permit Issued | THB CUSTOM BUILDERS INC | 09/18/2024 |
| DOB NOW | General Construction | Permit Issued | THB CUSTOM BUILDERS INC | 05/09/2024 |
| DOB NOW | Construction Fence | Signed-off | THB CUSTOM BUILDERS INC | 02/28/2024 |
| DOB NOW | Mechanical Systems | Signed-off | THB CUSTOM BUILDERS INC | 02/27/2024 |
| DOB NOW | Foundation | Signed-off | THB CUSTOM BUILDERS INC | 02/27/2024 |
| DOB NOW | Plumbing | Signed-off | EMPIRE PLUMBING INC | 01/18/2024 |
| DOB NOW | Sprinklers | Signed-off | EMPIRE PLUMBING INC | 01/18/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | GWT ENTERPRISES INC | 01/09/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | GWT ENTERPRISES INC | 01/09/2024 |
| DOB NOW | Supported Scaffold | Signed-off | MANHATTAN D ENTERPRISES | 12/06/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 12/06/2023 |
| DOB NOW | Plumbing | Signed-off | DNA PLUMBING CONTR. INC | 10/12/2023 |
| DOB NOW | General Construction | Permit Issued | THB CUSTOM BUILDERS INC | 09/05/2023 |
| DOB NOW | Mechanical Systems | Signed-off | THB CUSTOM BUILDERS INC | 08/23/2023 |
| DOB NOW | Earth Work | Signed-off | THB CUSTOM BUILDERS INC | 08/23/2023 |
| DOB NOW | Construction Fence | Signed-off | THB CUSTOM BUILDERS INC | 08/23/2023 |
| DOB NOW | Structural | Permit Issued | THB CUSTOM BUILDERS INC | 08/23/2023 |
| DOB NOW | General Construction | Permit Issued | YAFE MEOD CORP | 08/07/2023 |
| DOB NOW | Mechanical Systems | Signed-off | YAFE MEOD CORP | 08/04/2023 |
| DOB NOW | Structural | Permit Issued | YAFE MEOD CORP | 08/01/2023 |
| DOB NOW | Foundation | Signed-off | YAFE MEOD CORP | 07/21/2023 |
| DOB NOW | Construction Fence | Signed-off | YAFE MEOD CORP | 05/12/2023 |
| DOB NOW | Construction Fence | Signed-off | SAT CONSTRUCTION SERVICES | 03/30/2023 |
| DOB NOW | Support of Excavation | Signed-off | SAT CONSTRUCTION SERVICES | 03/30/2023 |
| DOB NOW | Structural | Permit Issued | SAT CONSTRUCTION SERVICES | 03/30/2023 |
| DOB NOW | Structural | Permit Issued | REAL LAND GROUP LLC | 03/03/2023 |
| DOB NOW | Support of Excavation | Signed-off | REAL LAND GROUP LLC | 01/10/2023 |
| DOB NOW | Construction Fence | Signed-off | REAL LAND GROUP LLC | 11/28/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/03/2025 | Permit Issued | THB CUSTOM BUILDERS INC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM120TAM-U1 129,000 BTU · Split System ×4 MXZ-SM60NAM-U1 66,000 BTU · Split System ×2 MXZ-SM72NAM2-U1 80,000 BTU · Vrf Outdoor ×2 PAZ-A42NKA7 46,000 BTU · Split System ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/03/2025 | Signed-off | PIPING & PLUMBING SOLUTIO | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/03/2025 | Signed-off | PIPING & PLUMBING SOLUTIO | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/11/2025 | Complete | ENERCHARGE ELECTRIC CONT | General Wiring |
| 11/24/2025 | Complete | FRIED ELECTRIC CO. | General Wiring |
| 12/07/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| 03/19/2019 | Complete | PLATINUM PWR ELECTL CONT | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/03/2025 | Permit Issued | THB CUSTOM BUILDERS INC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/03/2025 | Permit Issued | THB CUSTOM BUILDERS INC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/18/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/05/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 08/21/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/30/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/30/2025 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 06/26/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/20/2025 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 01/10/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/07/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/15/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/18/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/05/2025 | Construction Operations Influencing Adjacent Structures | EDWARD TOROSSIAN | special |
| 11/05/2025 | Air barrier — testing | JAIME MOYA | energy_progress |
| 11/05/2025 | Fenestration areas | JAIME MOYA | energy_progress |
| 11/05/2025 | Air barrier - visual inspection | JAIME MOYA | energy_progress |
| 11/05/2025 | Permanent certificate | JAIME MOYA | energy_progress |
| 11/05/2025 | Maintenance information | JAIME MOYA | energy_progress |
| 11/05/2025 | Lighting in dwelling units | JAIME MOYA | energy_progress |
| 11/05/2025 | Electrical motors and elevators | JAIME MOYA | energy_progress |
| 11/05/2025 | Metering | JAIME MOYA | energy_progress |
| 11/05/2025 | Fenestration air leakage | JAIME MOYA | energy_progress |
| 11/05/2025 | Electric vehicle service equipment requirements | JAIME MOYA | energy_progress |
| 11/05/2025 | Insulation placement and R values | JAIME MOYA | energy_progress |
| 11/05/2025 | Protection of exposed foundation insulation | JAIME MOYA | energy_progress |
| 11/05/2025 | Fenestration and door U-factor and product ratings | JAIME MOYA | energy_progress |
| 11/05/2025 | Interior lighting power | JAIME MOYA | energy_progress |
| 11/05/2025 | Energy Code Compliance Inspections | JAIME MOYA | progress |
| 11/05/2025 | Fire-Resistance Rated Construction | EDWARD TOROSSIAN | progress |
| 11/05/2025 | Exterior Insulation and Finish Systems (EIFS) | EDWARD TOROSSIAN | special |
| 11/05/2025 | Fire-Resistant Penetrations and Joints | EDWARD TOROSSIAN | special |
| 11/05/2025 | Structural Stability – Alterations of existing buildings | EDWARD TOROSSIAN | special |
| 09/22/2025 | Air barrier - visual inspection | JAIME MOYA | energy_progress |
| 09/22/2025 | Construction Operations Influencing Adjacent Structures | EDWARD TOROSSIAN | special |
| 09/22/2025 | Exterior Insulation and Finish Systems (EIFS) | EDWARD TOROSSIAN | special |
| 09/22/2025 | Fire-Resistant Penetrations and Joints | EDWARD TOROSSIAN | special |
| 09/22/2025 | Structural Stability – Alterations of existing buildings | EDWARD TOROSSIAN | special |