← Back
BuildNYC
Two family brick
406 WILLOUGHBY AVENUE
BROOKLYN · BIN 3429498
💬 Discuss this project
1931Year Built
3Stories
B1Building Class
R6BZoning
9,689 sfGross Floor Area
2Units
0 Active ViolationsFDNY Report ↗
Two family brick · 3,240 sf lot · 2.99 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofScope of Work: Alteration and Vertical Enlargement to Existi117p · 2 filings · 20 docs
Floor 3Scope of Work: Alteration and Vertical Enlargement to Existi108p · 1 filing · 20 docs
Floor 2Scope of Work: Alteration and Vertical Enlargement to Existi108p · 1 filing · 20 docs
Floor 1Sidewalk improvement and replacement113p · 3 filings · 20 docs
CellarScope of Work: Alteration and Vertical Enlargement to Existi111p · 1 filing · 20 docs
Site & exteriorScope of Work: Alteration and Vertical Enlargement to Existi44p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1163 Fulton Realty8807/08/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Xpdite Group LLC (104)2103/21/2026
Millennium Designs of New York103/21/2026
Xpdite Group 103603/21/2026
Xpdite Group LLC 104303/21/2026
Millennium Designs103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
THB Custom BuildersGeneral Contractor1907/08/2026
Yafe MeodGeneral Contractor807/08/2026
THB Custom BuildersScaffold707/08/2026
Sat Construction ServicesGeneral Contractor603/21/2026
GWT EnterprisesScaffold603/21/2026
Real Land GroupGeneral Contractor407/08/2026
Manhattan D EnterprisesScaffold407/08/2026
Piping & Plumbing SolutionsFire Protection207/08/2026
Fried Electric CoElectrical203/22/2026
Empire PlumbingPlumbing207/08/2026
Real Land GroupScaffold107/08/2026
Yafe MeodScaffold107/08/2026
DNA Plumbing ContractorsPlumbing107/08/2026
Enercharge Electric ContElectrical103/22/2026
Sat Construction ServicesScaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Trolydia Testing & Inspec44221710/03/2025
Building Lifecycle
08/22/2026
Elevator Category 1 inspection report filed
03/13/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
APPLICATION FILED HEREWITH, TO VERTICAL ENLARGMENT EXISTING COMMERCIAL BUILDING AND CONVERT INTO A THREE (3) STORY RESIDENTIAL BUILDING
B08053369-I1
11/05/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
EDWARD TOROSSIAN
11/05/2025
Special inspection requirement — Permanent certificate
JAIME MOYA
11/05/2025
Special inspection requirement — Electrical motors and elevators
JAIME MOYA
133 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offTHB Custom Builders05/21/2025
DOB NOWGeneral ConstructionPermit IssuedTHB Custom Builders02/14/2025
DOB NOWGeneral ConstructionPermit IssuedTHB Custom Builders02/13/2025
DOB NOWConstruction FenceSigned-offTHB Custom Builders02/11/2025
DOB NOWSprinklersSigned-offEmpire Plumbing01/16/2025
DOB NOWPlumbingSigned-offEmpire Plumbing01/16/2025
DOB NOWStructuralPermit IssuedTHB Custom Builders09/18/2024
DOB NOWGeneral ConstructionPermit IssuedTHB Custom Builders05/09/2024
DOB NOWConstruction FenceSigned-offTHB Custom Builders02/28/2024
DOB NOWFoundationSigned-offTHB Custom Builders02/27/2024
DOB NOWMechanical SystemsSigned-offTHB Custom Builders02/27/2024
DOB NOWSprinklersSigned-offEmpire Plumbing01/18/2024
DOB NOWPlumbingSigned-offEmpire Plumbing01/18/2024
DOB NOWSupported ScaffoldSigned-offGWT Enterprises01/09/2024
DOB NOWSupported ScaffoldSigned-offGWT Enterprises01/09/2024
DOB NOWSupported ScaffoldSigned-offManhattan D Enterprises12/06/2023
DOB NOWSupported ScaffoldSigned-offManhattan D Enterprises12/06/2023
DOB NOWPlumbingSigned-offDNA Plumbing Contractors10/12/2023
DOB NOWGeneral ConstructionPermit IssuedTHB Custom Builders09/05/2023
DOB NOWEarth WorkSigned-offTHB Custom Builders08/23/2023
DOB NOWConstruction FenceSigned-offTHB Custom Builders08/23/2023
DOB NOWMechanical SystemsSigned-offTHB Custom Builders08/23/2023
DOB NOWStructuralPermit IssuedTHB Custom Builders08/23/2023
DOB NOWGeneral ConstructionPermit IssuedYafe Meod08/07/2023
DOB NOWMechanical SystemsSigned-offYafe Meod08/04/2023
DOB NOWStructuralPermit IssuedYafe Meod08/01/2023
DOB NOWEarth WorkSigned-offYafe Meod07/21/2023
DOB NOWConstruction FenceSigned-offYafe Meod05/12/2023
DOB NOWStructuralPermit IssuedSat Construction Services03/30/2023
DOB NOWSupport of ExcavationSigned-offSat Construction Services03/30/2023
DOB NOWConstruction FenceSigned-offSat Construction Services03/30/2023
DOB NOWStructuralPermit IssuedReal Land Group03/03/2023
DOB NOWSupport of ExcavationSigned-offReal Land Group01/10/2023
DOB NOWConstruction FenceSigned-offReal Land Group11/28/2022
1 project · most recent 10/03/2025
Heating and Air Conditioning Systems
FiledStatusContractorScope
10/03/2025Permit IssuedTHB Custom BuildersHeating and Air Conditioning Systems
1 project · most recent 10/03/2025
Sprinkler System
FiledStatusContractorScope
10/03/2025Signed-offPiping & Plumbing SolutionsSprinkler System
1 project · most recent 10/03/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
10/03/2025Signed-offPiping & Plumbing SolutionsGas, Storm, Water/Sanitary
4 projects · most recent 12/11/2025
General Wiring
FiledStatusContractorScope
12/11/2025CompleteEnercharge Electric ContGeneral Wiring
11/24/2025CompleteFried Electric CoGeneral Wiring
12/07/2023CompleteSolas Electrical—
03/19/2019CompletePlatinum PWR Electl Cont—
1 project · most recent 10/03/2025
Steel Concrete
FiledStatusContractorScope
10/03/2025Permit IssuedTHB Custom BuildersSteel, Concrete
1 project · most recent 10/03/2025
Earthwork
FiledStatusContractorScope
10/03/2025Permit IssuedTHB Custom BuildersEarthwork
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
09/18/2025Pass-Final CND-Occupancy InspectionPassView ↗
09/05/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
08/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/30/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/30/2025Fail-Final PL - Up to 9 Requested FloorsFailView ↗
06/26/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/20/2025Fail-Final PL - Up to 9 Requested FloorsFailView ↗
05/15/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
03/18/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 147
DateRequirementInspectorRole
11/05/2025Maintenance informationJAIME MOYAenergy_progress
11/05/2025Air barrier — testing JAIME MOYAenergy_progress
11/05/2025Lighting in dwelling unitsJAIME MOYAenergy_progress
11/05/2025Fenestration areasJAIME MOYAenergy_progress
11/05/2025Air barrier - visual inspectionJAIME MOYAenergy_progress
11/05/2025Permanent certificateJAIME MOYAenergy_progress
11/05/2025Construction Operations Influencing Adjacent StructuresEDWARD TOROSSIANspecial
11/05/2025Structural Stability – Alterations of existing buildingsEDWARD TOROSSIANspecial
11/05/2025Fire-Resistant Penetrations and JointsEDWARD TOROSSIANspecial
11/05/2025Exterior Insulation and Finish Systems (EIFS)EDWARD TOROSSIANspecial
11/05/2025Fire-Resistance Rated ConstructionEDWARD TOROSSIANprogress
11/05/2025Energy Code Compliance InspectionsJAIME MOYAprogress
11/05/2025Interior lighting powerJAIME MOYAenergy_progress
11/05/2025Fenestration and door U-factor and product ratingsJAIME MOYAenergy_progress
11/05/2025Protection of exposed foundation insulationJAIME MOYAenergy_progress
11/05/2025Insulation placement and R valuesJAIME MOYAenergy_progress
11/05/2025Electric vehicle service equipment requirementsJAIME MOYAenergy_progress
11/05/2025Fenestration air leakageJAIME MOYAenergy_progress
11/05/2025MeteringJAIME MOYAenergy_progress
11/05/2025Electrical motors and elevatorsJAIME MOYAenergy_progress
09/22/2025Interior lighting powerJAIME MOYAenergy_progress
09/22/2025Construction Operations Influencing Adjacent StructuresEDWARD TOROSSIANspecial
09/22/2025Exterior Insulation and Finish Systems (EIFS)EDWARD TOROSSIANspecial
09/22/2025Fire-Resistant Penetrations and JointsEDWARD TOROSSIANspecial
09/22/2025Structural Stability – Alterations of existing buildingsEDWARD TOROSSIANspecial
Latest 25 of 147.
212 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account