← Back
BuildNYC
Three families
407 STUYVESANT AVENUE
BROOKLYN · BIN 3047783
💬 Discuss this project
1892Year Built
3Stories
C0Building Class
R6BZoning
3,410 sfGross Floor Area
3Units
Rent Stabilized0 Active ViolationsFDNY Report ↗
Three families · 2,000 sf lot · 1.71 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 1Miller Gass Duplex18p · 2 filings · 20 docs
CellarMiller Gass Duplex2p · 2 filings · 20 docs
BasementMiller Gass Duplex10p · 2 filings · 20 docs
Sub-BasementMiller Gass Duplex10p · 2 filings · 20 docs
Site & exterior1p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/03/2021$2.3M—STARS T&T NY, LLC → Private party$682/sf building
01/23/2014$1.5M—Private party → Private party$440/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Denise Lee Architect510/03/2023
Gasbarro Structural Engineering106/19/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
L & J Design Group1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
G & S Construction VenturGeneral Contractor907/08/2026
G & S Construction Venturspecialty_contractor303/21/2026
EH Plumbing & HeatingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Edward F Zevallos1025510/03/2023
Gasbarro Structural Engineering5919306/19/2023
Building Lifecycle
06/13/2024
Signed off — Alteration
RENOVATION OF KITCHEN AND ADDITION OF HALF BATHROOM AS PER PLANS.
B08030912-I1
06/12/2024
Permit renewed — General Construction
Renewed without changes
B08030912-I1-GC
06/10/2024
Signed off — Alteration
PARTIAL RENOVATION OF BASEMENT AND 1ST FLOOR. REMOVE AND INSTALL NEW PARTITIONS, RELOCATE BATHROOM, REAR YARD HORIZONTAL ADDITION AS PER PLANS.
B08054824-I1
06/10/2024
Signed off — Alteration
RENOVATION OF KITCHEN AND ADDITION OF HALF BATHROOM AS PER PLANS.
B08030912-S1
06/10/2024
Signed off — Alteration
PARTIAL RENOVATION OF BASEMENT AND 1ST FLOOR. REMOVE AND INSTALL NEW PARTITIONS, RELOCATE BATHROOM, REAR YARD HORIZONTAL ADDITION AS PER PLANS.
B08054824-S2
64 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offG & S Construction Ventur06/12/2024
DOB NOWMechanical SystemsSigned-offG & S Construction Ventur10/16/2023
DOB NOWGeneral ConstructionSigned-offG & S Construction Ventur10/12/2023
DOB NOWFoundationSigned-offG & S Construction Ventur10/03/2023
DOB NOWGeneral ConstructionSigned-offG & S Construction Ventur06/29/2023
DOB NOWPlumbingSigned-offEH Plumbing & Heating04/17/2023
DOB NOWGeneral ConstructionSigned-offG & S Construction Ventur04/07/2023
3 projects · most recent 03/06/2026
General Wiring
FiledStatusContractorScope
03/06/2026CompleteMac Elect'l Contracting—
03/06/2026CompleteMac Elect'l ContractingGeneral Wiring
10/26/2021CompleteVere ElectricGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
05/24/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/19/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/22/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 27
DateRequirementInspectorRole
09/27/2023FinalDENISE REOprogress
09/27/2023Mechanical SystemsEdward Zevallosspecial
06/12/2023Construction Operations Influencing Adjacent StructuresThomas Gasbarrospecial
06/12/2023MasonryThomas Gasbarrospecial
06/12/2023Post-installed AnchorsThomas Gasbarrospecial
06/12/2023Structural Cold-Formed SteelThomas Gasbarrospecial
06/12/2023Subgrade InspectionsThomas Gasbarrospecial
06/12/2023Structural Steel - DetailsThomas Gasbarrospecial
06/12/2023Structural Stability – Alterations of existing buildingsThomas Gasbarrospecial
06/12/2023Concrete - Cast-In-PlaceThomas Gasbarrospecial
06/09/2023FinalThomas Gasbarroprogress
06/09/2023Footing and FoundationThomas Gasbarroprogress
06/08/2023Fire-Resistant Penetrations and JointsEdward Zevallosspecial
06/01/2023Fire-Resistant Penetrations and JointsEdward Zevallosspecial
01/04/2023Air barrier - visual inspectionDENISE REOenergy_progress
01/04/2023Energy Code Compliance InspectionsDENISE REOprogress
01/04/2023Insulation placement and R valuesDENISE REOenergy_progress
01/04/2023Fenestration air leakageDENISE REOenergy_progress
01/04/2023Fenestration and door U-factor and product ratingsDENISE REOenergy_progress
01/04/2023Lighting in dwelling unitsDENISE REOenergy_progress
12/14/2022Structural Stability – Alterations of existing buildingsThomas Gasbarrospecial
12/14/2022FinalDENISE REOprogress
12/14/2022Fire-Resistant Penetrations and JointsEdward Zevallosspecial
12/14/2022Construction Operations Influencing Adjacent StructuresThomas Gasbarrospecial
11/29/2022Structural Stability – Alterations of existing buildingsThomas Gasbarrospecial
Latest 25 of 27.
56 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account