| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01417013 ↗ | 54 DOUGLASS STREET BROOKLYN | Alteration | Permit Issued | 06/15/2026 | 07/24/2026 | Contractor CENTAURI DEVELOPMENT INC | RENOVATION OF 1-FAMILY DWELLING. REMOVE AND INSTALL INSTERIOR PARTITIONS, DOORS, WINDOWS AND FINISHES. CREATE DORMER ROOF AT REAR OF THE HOU… |
| M01341793 ↗ | 1435 LEXINGTON AVENUE MANHATTAN | Alteration | Permit Issued | 04/20/2026 | 07/22/2026 | Design ARCHITECTURE WORKSHOP PC Contractor GANIC PLUMBING & HTG INC | REMOVE AND INSTALL PLUMBING FIXTURES. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M01176507 ↗ | 2101 BROADWAY ATRIUM MANHATTAN | Alteration | Permit Issued | 04/10/2025 | 06/26/2026 | Design ARCHITECTURE WORKSHOP PC Contractor SUBURBANA CORP | RELOCATION OF PLUMBING FIXTURES IN BATHROOM AND KITCHEN. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M01188708 ↗ | 415 EAST 80 STREET MANHATTAN | Alteration | Permit Issued | 05/13/2025 | 06/26/2026 | Design ARCHITECTURE WORKSHOP PC Contractor ALB-BROS CONSTR CORP | Replacement and relocation of plumbing fixtures. Remove on kitchen. NO CHANGE TO USE, EGRESS OR OCCUPANCY |
| M01339126 ↗ | 1 CENTRE STREET MANHATTAN | Alteration | Permit Issued | 01/14/2026 | 05/20/2026 | Design DCAS Owner DCAS Contractor CONTRACT & HOSPITALITY | Remove and install interior partitions and doors at 21 FL north side. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| M01356166 ↗ | 310 RIVERSIDE DRIVE MANHATTAN | Alteration | Permit Issued | 03/06/2026 | 04/17/2026 | Design ARCHITECTURE WORKSHOP PC Contractor KBRNY, INC | Renovation apt 1801/1815. Remove and install interior partitions, doors and finishes. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| Name | Projects together | Most recent |
|---|---|---|
| EDWARD F ZEVALLOS ARCHITECT, PC | 33 | 06/15/2026 |
| ARCHITECTURE WORKSHOP PC | 15 | 04/20/2026 |
| DENISE LEE ARCHITECT | 8 | 10/03/2023 |
| DCAS | 3 | 01/14/2026 |
| ELLEN ROCHE | 2 | 02/03/2023 |
| GARY ROSARD ARCHITECT | 2 | 07/26/2021 |
| GREGORY T. WAUGH AIA | 2 | 02/17/2025 |
| LJI PROJECTS | 2 | 08/19/2021 |
| SCHMID ENGINEERING SERVICES, PLLC | 2 | 09/22/2021 |
| ALAN R SCHWARTZ PE CONS ENG | 1 | 03/30/2026 |
| BFB ARCHITECT, PC | 1 | 01/13/2020 |
| G. PEROTTO ASSOCIATES | 1 | 04/23/2021 |
| GASBARRO STRUCTURAL ENGINEERING | 1 | 10/03/2023 |
| KTA ENGINEERING | 1 | 03/30/2026 |
| Nancy Karg Architect | 1 | 06/21/2024 |
| OGP ARCHITECTS, LLP | 1 | 03/18/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| 360 PRESTIGE CONTRACTING | 3 | 05/31/2023 |
| CONTRACT & HOSPITALITY | 3 | 01/14/2026 |
| NEW ENTITY LLC | 3 | 11/13/2024 |
| SMART PLBG & HTG CORP | 3 | 11/13/2024 |
| ALB-BROS CONSTR CORP | 2 | 05/13/2025 |
| BH INTERIORS INC | 2 | 08/27/2021 |
| DAVARO CONTRACTING LLC | 2 | 05/13/2021 |
| G & S CONSTRUCTION VENTUR | 2 | 10/03/2023 |
| MPH CONSTRUCTION INC | 2 | 12/11/2020 |
| NEW GREEN MOVEMENT INT'L, | 2 | 08/19/2021 |
| NICE PLUMBING CORP | 2 | 05/17/2022 |
| P.H. WORKS INC | 2 | 05/06/2022 |
| PEGASUS P&H CORP | 2 | 06/13/2024 |
| ABR PLBG&HTG CONTR INC | 1 | 08/01/2021 |
| ALMAR PLUMBING & HTG CORP | 1 | 02/05/2025 |
| AQUA PLUMBING & HTNG CORP | 1 | 07/26/2021 |
| ASPIRO RENOVATIONS LLC | 1 | 11/08/2022 |
| AWL INDUSTRIES INC | 1 | 07/24/2025 |
| BIG APPLE SEWER & DRAIN I | 1 | 12/17/2021 |
| CEGF & G PLUMBING CORP | 1 | 02/03/2023 |
| CENTAURI DEVELOPMENT INC | 1 | 06/15/2026 |
| COBALT MECHANICAL INC | 1 | 10/27/2021 |
| CORNERSTONE CONSTRUCTION | 1 | 04/21/2021 |
| COTTAM HEATING & AIR COND | 1 | 06/21/2024 |
| D.J.G COMPANY US INC | 1 | 08/01/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| DCAS | 3 | 01/14/2026 |
| EBMG LLC | 2 | 07/14/2023 |
| HARLEM PROPERTY MANAGEMENT | 2 | 10/27/2021 |
| RIVEREDGE | 2 | 06/06/2023 |
| 171 TENANTS CORP. | 1 | 12/17/2024 |
| FirstService Residential | 1 | 10/15/2024 |
| GORJIAN REAL ESTATE GROUP | 1 | 08/27/2021 |
| MATTHEW ADAM PROPERTIES | 1 | 05/31/2023 |
| NEW ENTITY LLC | 1 | 11/29/2023 |
| ONE LINCOLN SQUARE CONDOMINIUM | 1 | 10/21/2021 |
| ORSID REALTY CORP | 1 | 04/14/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| EDWARD F ZEVALLOS ARCHITECT, PC | 16 | 04/20/2026 |
| ADAM MAISER | 3 | 08/19/2021 |
| HAQUE AND ASSOCIATES LLC | 3 | 10/18/2023 |
| L & J DESIGN GROUP | 3 | 10/03/2023 |
| BOUTIQKEY LLC | 1 | 05/31/2023 |
| G + DESIGN CONSULTANTS | 1 | 03/18/2026 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01417013 ↗ | 54 DOUGLASS STREET BROOKLYN | Alteration | Permit Issued | 06/15/2026 | 07/24/2026 | Contractor CENTAURI DEVELOPMENT INC | RENOVATION OF 1-FAMILY DWELLING. REMOVE AND INSTALL INSTERIOR PARTITIONS, DOORS, WINDOWS AND FINISHES. CREATE DORMER ROOF AT REAR OF THE HOU… |
| M01341793 ↗ | 1435 LEXINGTON AVENUE MANHATTAN | Alteration | Permit Issued | 04/20/2026 | 07/22/2026 | Design ARCHITECTURE WORKSHOP PC Contractor GANIC PLUMBING & HTG INC | REMOVE AND INSTALL PLUMBING FIXTURES. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M01176507 ↗ | 2101 BROADWAY ATRIUM MANHATTAN | Alteration | Permit Issued | 04/10/2025 | 06/26/2026 | Design ARCHITECTURE WORKSHOP PC Contractor SUBURBANA CORP | RELOCATION OF PLUMBING FIXTURES IN BATHROOM AND KITCHEN. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M01188708 ↗ | 415 EAST 80 STREET MANHATTAN | Alteration | Permit Issued | 05/13/2025 | 06/26/2026 | Design ARCHITECTURE WORKSHOP PC Contractor ALB-BROS CONSTR CORP | Replacement and relocation of plumbing fixtures. Remove on kitchen. NO CHANGE TO USE, EGRESS OR OCCUPANCY |
| M01339126 ↗ | 1 CENTRE STREET MANHATTAN | Alteration | Permit Issued | 01/14/2026 | 05/20/2026 | Design DCAS Owner DCAS Contractor CONTRACT & HOSPITALITY | Remove and install interior partitions and doors at 21 FL north side. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| M01356166 ↗ | 310 RIVERSIDE DRIVE MANHATTAN | Alteration | Permit Issued | 03/06/2026 | 04/17/2026 | Design ARCHITECTURE WORKSHOP PC Contractor KBRNY, INC | Renovation apt 1801/1815. Remove and install interior partitions, doors and finishes. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M01372602 ↗ | 169 WEST 95 STREET MANHATTAN | Alteration | Filed — no permit on record | 04/14/2026 | — | Design ARCHITECTURE WORKSHOP PC Owner Orsid Realty Corp | — |
| B01008558 ↗ | 24 STRONG PLACE BROOKLYN | Alteration | Permit Issued | 03/05/2024 | 04/10/2026 | Design KTA ENGINEERING Contractor WMG RENOVATION CORP | MODIFICATIONS TO INTERIOR BEARING WALL AND REMOVAL OF NON-STRUCTURAL PARTITIONS AT THE SECOND FLOOR ONLY |
| M01370180 ↗ | 220 WEST 19 STREET MANHATTAN | Alteration | Signed-off | 03/18/2026 | 03/25/2026 | Design OGP ARCHITECTS, LLP Contractor HEAVY DUTY BUILDERS LLC Filer G + DESIGN CONSULTANTS | APPLICATION IS FILED FOR INTERIOR DEMOLITION ANDRENOVATION IN CELLAR THAT DOESN'T AFFECT USE, EGRESS OROCCUPANCY OF THE SPACE, AND THEREFORE… |
| M01040756 ↗ | 2101 BROADWAY ATRIUM MANHATTAN | Alteration | Permit Issued | 09/23/2024 | 02/11/2026 | Contractor ALMAR PLUMBING & HTG CORP | RELOCATION OF PLUMBING FIXTURES. INSTALL NEW BATHROOM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| B01032756 ↗ | 1156 FULTON STREET BROOKLYN | Alteration | Permit Issued | 04/23/2024 | 12/23/2025 | Contractor SIMONSAYS CORP | RENOVATION OF COMMERCIAL AND RESIDENTIAL BUILDING. REMOVE AND INSTALL INTERIOR PARTITIONS, DOORS AND FINISHES. INSTALL MECHANICAL UNITS AND … |
| M01150930 ↗ | 171 WEST 79 STREET MANHATTAN | Alteration | Signed-off | 12/17/2024 | 12/11/2025 | Owner 171 TENANTS CORP. Contractor DELTA-SIGMA MECH CORP | Replace plumbing fixtures in kitchen and bathrooms. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| M01197372 ↗ | 1 CENTRE STREET MANHATTAN | Alteration | Permit Issued | 05/22/2025 | 10/27/2025 | Design DCAS Owner DCAS Contractor AWL INDUSTRIES INC | Remove and install interior partitions, floors and ceilings. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M01278410 ↗ | 1 CENTRE STREET MANHATTAN | Alteration | Permit Issued | 09/19/2025 | 09/26/2025 | Design DCAS Owner DCAS Contractor CONTRACT & HOSPITALITY | REMOVE AND INSTALL INTERIOR PARITIONS, DOORS AND CEILINGS AT 12 FLOOR DATA CENTER. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| M00902880 ↗ | 465 GREENWICH STREET MANHATTAN | Alteration | Signed-off | 07/14/2023 | 07/02/2025 | Contractor NEW ENTITY LLC | REPLACEMENT OF CONDENSING UNIT ON ROOF, AND AIR HANDLING UNIT ON APT 5 ON THE 5TH FLOOR AT EXISTING LOCATIONS. NO CHANGE TO USE, EGRESS OR … |
| B01032763 ↗ | 1156 FULTON STREET BROOKLYN | Alteration | Signed-off | 04/23/2024 | 05/29/2025 | Contractor A&H EXPRESS PLBG&HTG CORP | REMOVE AND INSTALL PLAUMBIGN FIXTURES. NO CHANGE TO USE, EGRESS, OR OCCUPANCY |
| M01058599 ↗ | 31 WEST 69 STREET MANHATTAN | Alteration | Signed-off | 07/03/2024 | 02/07/2025 | Contractor JOHN FITZGERALD PLBG &HTG | REMOVE AND INSTALL PLUMBING FIXTURES. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| B01123501 ↗ | 360 FURMAN STREET BROOKLYN | Alteration | Signed-off | 10/15/2024 | 12/27/2024 | Owner FIRSTSERVICE RESIDENTIAL Contractor SUNRISE RENOVATION INC | INSTALLATION OF INTERIOR PARITITONS, DOORS, LIGHTING AND FINISHES. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| X00883584 ↗ | 2575 PALISADE AVENUE BRONX | Alteration | Signed-off | 06/06/2023 | 11/01/2024 | Owner RIVEREDGE Contractor RANDY ROSE CORP | Combination of apt 10J and 10K. Remove and install interior partitions, doors and ceilings. Install AC unit and associated air handler and… |
| M00910391 ↗ | 132 EAST 19 STREET MANHATTAN | Alteration | Signed-off | 03/11/2024 | 10/23/2024 | Design ARCHITECTURE WORKSHOP PC Contractor Z-DAR CONTRACTING INC | COMBINATION OF APT'S 7E AND 7W AS PER TPPN 3/97, REMOVE AND INSTALL INTERIOR PARTITIONS, DOORS AND FINISHES. REPLACE FLUE AT EXISTING CHIM… |
| M01057515 ↗ | 177 9 AVENUE MANHATTAN | Alteration | Signed-off | 07/09/2024 | 10/10/2024 | Design ARCHITECTURE WORKSHOP PC Contractor PETER SIMON RESTORATION.C | Interior renovation of Apt. 2C. Remove and install interior partitions, doors and finishes. NO CHANGE TO USE EGRESS, OR OCCUPANCY. |
| M01084553 ↗ | 233 WEST 99 STREET MANHATTAN | Alteration | Signed-off | 08/20/2024 | 09/18/2024 | Design GREGORY T. WAUGH AIA Contractor HYDROKINETIC PLBG & HTG I | Kitchen renovation in apt. 7D. Relocate plumbing fixtures. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M01084552 ↗ | 233 WEST 99 STREET MANHATTAN | Alteration | Signed-off | 08/20/2024 | 09/11/2024 | Design GREGORY T. WAUGH AIA Contractor HOME BY ME INC | INTERIOR KITCHEN RENOVATION OF APT. 7D. REMOVE AND INSTALL INTERIOR PARTITIONS, DOORS AND FINISHES. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| X01069768 ↗ | 6035 LIEBIG AVENUE BRONX | Alteration | Signed-off | 06/21/2024 | 07/25/2024 | Design Nancy Karg Architect Contractor COTTAM HEATING AIR COND | Installation of 2 condensing units and associated air handlers. No change to use, egress, or occupancy. |
| M01034867 ↗ | 336 WEST END AVENUE MANHATTAN | Alteration | Signed-off | 06/13/2024 | 07/23/2024 | Contractor AQUEDUCT MECHANICAL CORP | INSTALL NEW SHOWER IN BATHROOM IN APT. 2BC. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| M01034849 ↗ | 336 WEST END AVENUE MANHATTAN | Alteration | Signed-off | 06/13/2024 | 07/18/2024 | Contractor RENOVYT, INC | Bathroom renovation in APT. 2BC, turn closet into a shower. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| B08030912 ↗ | 407 STUYVESANT AVENUE BROOKLYN | Alteration | Signed-off | 11/29/2022 | 06/12/2024 | Design DENISE LEE ARCHITECT Contractor G & S CONSTRUCTION VENTUR Filer L & J DESIGN GROUP | RENOVATION OF KITCHEN AND ADDITION OF HALF BATHROOM AS PER PLANS. |
| B00968991 ↗ | 71 BAY RIDGE AVENUE BROOKLYN | Alteration | Filed — no permit on record | 11/29/2023 | — | Owner NEW ENTITY LLC | — |
| M00947256 ↗ | 91 AUDUBON AVENUE MANHATTAN | Alteration | Signed-off | 10/18/2023 | 10/25/2023 | Contractor DKR CONSTRUCTION CO CORP Filer HAQUE AND ASSOCIATES LLC | INTERIOR RENOVATION OF A DUPLEX APARTMENT AT THE 1ST AND 2ND FLOOR ONLY INCLUDING REMOVAL OF INTERIOR PARTITION, NEW INTERIOR PARTITION, AND… |
| B08054824 ↗ | 407 STUYVESANT AVENUE BROOKLYN | Alteration | Signed-off | 01/05/2023 | 10/16/2023 | Design DENISE LEE ARCHITECT Contractor G & S CONSTRUCTION VENTUR Filer L & J DESIGN GROUP | PARTIAL RENOVATION OF BASEMENT AND 1ST FLOOR. REMOVE AND INSTALL NEW PARTITIONS, RELOCATE BATHROOM, REAR YARD HORIZONTAL ADDITION AS PER PLA… |
| X00883591 ↗ | 2575 PALISADE AVENUE BRONX | Alteration | Signed-off | 06/06/2023 | 10/10/2023 | Owner RIVEREDGE Contractor HUDSON PLBG AND HTG CO IN | Relocation and replacement of plumbing fixtures in Apt. 10J/K. |
| B00905564 ↗ | 303 SARATOGA AVENUE BROOKLYN | Alteration | Signed-off | 07/20/2023 | 08/14/2023 | Contractor LAMBO CONSTRUCTION, INC | Filing for mechanical work as per plans filed. Installation of two AHU and 1 CU units. No change of use, egress of occupancy. |
| M00873161 ↗ | 126 WEST 11 STREET MANHATTAN | Alteration | Signed-off | 05/31/2023 | 07/14/2023 | Design DENISE LEE ARCHITECT Owner MATTHEW ADAM PROPERTIES Contractor 360 PRESTIGE CONTRACTING Filer BOUTIQKEY LLC | PLUMBING RENOVATION OF AN EXISTING APARTMENT ON THE THIRD FLOOR. AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, AND OCCUPANCY. |
| M00723143 ↗ | 27 LEONARD STREET MANHATTAN | Alteration | Signed-off | 05/17/2022 | 04/14/2023 | Design ARCHITECTURE WORKSHOP PC Contractor NICE PLUMBING CORP | Replacement of plumbing fixtures. |
| M00852224 ↗ | 200 WEST 24 STREET MANHATTAN | Alteration | Signed-off | 03/29/2023 | 04/11/2023 | Owner EBMG LLC Contractor ORBIT PLBG & HTG INC | Replace and relocate plumbing fixtures in apt. 6A. No change to use, egress or occupancy. |
| M00723130 ↗ | 27 LEONARD STREET MANHATTAN | Alteration CO | Permit Issued | 05/17/2022 | 04/10/2023 | Design ARCHITECTURE WORKSHOP PC Contractor DEVLIN INTERIORS INC | Interior renovation to remove and install partitions, doors, ceilings and finishes. increase the number of habitable rooms to 4. NO CHANGE… |
| M00852182 ↗ | 200 WEST 24 STREET MANHATTAN | Alteration | Filed — no permit on record | 03/29/2023 | — | Owner EBMG LLC | — |
| Q08022948 ↗ | 20 MARKWOOD PLACE QUEENS | Alteration | Signed-off | 11/08/2022 | 02/23/2023 | Design ELLEN ROCHE Contractor ASPIRO RENOVATIONS LLC | Interior renovation of cellar. Install interior partitions, doors and finishes. Replace existing stair. NO CHANGE TO USE, EGRESS, OR OCCU… |
| Q08022953 ↗ | 20 MARKWOOD PLACE QUEENS | Alteration | Signed-off | 11/08/2022 | 01/11/2023 | Design ELLEN ROCHE Contractor BELL CONST SERV INC | INSTALLATION OF PLUMBING FIXTURES. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| M00732046 ↗ | 264 RIVERSIDE DRIVE MANHATTAN | Alteration | Signed-off | 05/16/2022 | 08/24/2022 | Design ARCHITECTURE WORKSHOP PC Contractor T & T PLUMBING INC | Remove and install plumbing fixtures at Apt. 11F. |
| M00732007 ↗ | 264 RIVERSIDE DRIVE MANHATTAN | Alteration | Signed-off | 05/16/2022 | 08/17/2022 | Design ARCHITECTURE WORKSHOP PC Contractor ALB-BROS CONSTR CORP | Interior renovation of apt. 11F. Remove and install interior partitions, doors and finishes. No change to use, egress, or occupancy. |
| M00725632 ↗ | 345 WEST 13 STREET MANHATTAN | Alteration | Signed-off | 06/06/2022 | 08/16/2022 | Contractor NEW ENTITY LLC | Remove and installation of partitions and finishes. No change to use, egress, or occupancy. |
| M00433187 ↗ | 39 EAST 12 STREET MANHATTAN | Alteration | Signed-off | 12/04/2020 | 06/29/2022 | Design ARCHITECTURE WORKSHOP PC Contractor WAWEL PLBG AND HTG CORP | REMOVE, INSTALL, REPLACE AND RELOCATE PLUMBING FIXTURES. |
| B00561472 ↗ | 454A 17 STREET BROOKLYN | Alteration | Signed-off | 08/01/2021 | 06/21/2022 | Contractor DJG COMPANY US INC | RENOVATION OF 2 FAMILY TOWNHOUSE. PARTITIONS, DOORS AND AC UNITS. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00506926 ↗ | 930 5 AVENUE MANHATTAN | Alteration | Signed-off | 05/05/2021 | 06/14/2022 | Contractor P.H. WORKS INC | REMOVE, RELOCATE AND INSTALL PLUMBING FIXTURES IN APT. 18A. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| B00479590 ↗ | 24 ST CHARLES PLACE BROOKLYN | Alteration | Signed-off | 03/09/2021 | 05/11/2022 | Contractor DAVARO CONTRACTING | REMOVE AND INSTALL INTERIOR PARTITIONS, DOORS AND FINISHES. NO CHANGE TO USE, EGESS, OR OCCUPANCY. |
| M00537872 ↗ | 39 EAST 12 STREET MANHATTAN | Alteration | Signed-off | 06/16/2021 | 04/08/2022 | Design LJI PROJECTS Contractor NGM VISION GROUP INC Filer ADAM MAISER | INTERIOR RENAVATION AND COMBINATION OF APARTMENTS #208 AND #209 ON 2ND FLOOR OF AN EXISTING RESIDENTIAL BUILDING. NO CHANGE IN USE, OCCUPANC… |
| M00506876 ↗ | 930 5 AVENUE MANHATTAN | Alteration | Permit Issued | 05/05/2021 | 04/06/2022 | Contractor P.H. WORKS INC | INSTALLATION OF THRU-WALL HVAC UNITS IN APT. 18A. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| M00614715 ↗ | 330 WEST 145 STREET MANHATTAN | Alteration | Signed-off | 10/27/2021 | 03/08/2022 | Design ARCHITECTURE WORKSHOP PC Contractor AMERICAN STANDARD P&H CORORP. | Remove, relocate and replace plumbing fixtures. No change to use, egress, or occupancy. |
| M00614675 ↗ | 330 WEST 145 STREET MANHATTAN | Alteration | Signed-off | 10/27/2021 | 02/17/2022 | Design ARCHITECTURE WORKSHOP PC Contractor GC LEADER CONSTRUCTION CO | Renovation of apt. PH5 on 8th floor. Remove and install interior partitions, doors and finishes. No change to use, egress, or occupancy. |
| B00634345 ↗ | 189 19 STREET BROOKLYN | Alteration | Filed — no permit on record | 11/26/2021 | — | Design DENISE LEE ARCHITECT Filer L & J DESIGN GROUP | — |
| M00584598 ↗ | 314 WEST 58 STREET MANHATTAN | Alteration | Signed-off | 08/27/2021 | 11/16/2021 | Contractor BH INTERIORS | Modification of existing storefront, no structural work. |
| M00577457 ↗ | 1122 1 AVENUE MANHATTAN | Alteration | Signed-off | 08/17/2021 | 11/15/2021 | Contractor BH INTERIORS | RENOVATION OF EXISTING BAR. REMOVE AND INSTALL FLOORING, FINISHES AND CABINETRY. MODIFY STOREFRONT AT EXISTIGN OPENING. NO CHANGE TO USE, … |
| M00578042 ↗ | 1122 1 AVENUE MANHATTAN | Alteration | Signed-off | 08/17/2021 | 09/16/2021 | Contractor METROTECH MECHANICAL CORP | Replace and install new plumbing fixtures. No change to use, egress, or occupancy. |
| M00537878 ↗ | 39 EAST 12 STREET MANHATTAN | Alteration | Signed-off | 08/19/2021 | 09/15/2021 | Design LJI PROJECTS Contractor NGM VISION GROUP INC Filer ADAM MAISER | MECHANICAL WORK IN CONJUNCTION TO APARTMENTS #208 AND #209 ON 2ND FLOOR OF AN EXISTING RESIDENTIAL BUILDING. NO CHANGE IN USE, OCCUPANCY, OR… |
| M00578540 ↗ | 144 COLUMBUS AVENUE MANHATTAN | Alteration | Signed-off | 08/19/2021 | 09/13/2021 | Contractor SMART PLBG & HTG CORP | Replace, relocate and new plumbing fixtures. |
| B00252763 ↗ | 125 CHAUNCEY STREET BROOKLYN | Alteration | Signed-off | 12/09/2019 | 08/30/2021 | Contractor M. SPINELLI PLB & HTG INC | Add the gas work previously approved but not listed on the application. |
| M00578492 ↗ | 144 COLUMBUS AVENUE MANHATTAN | Alteration | Permit Issued | 08/19/2021 | 08/30/2021 | Contractor NEW ENTITY LLC | Renovation of apt. 9C. Remove and install interior partitions, doors, ceilings and finishes. No change to use, egress, or occupancy. |
| B00567919 ↗ | 454A 17 STREET BROOKLYN | Alteration | Signed-off | 08/01/2021 | 08/03/2021 | Contractor ABR PLBG&HTG CONTR INC | Replace and relocate plumbing fixtures. |
| B00519989 ↗ | 24 ST CHARLES PLACE BROOKLYN | Alteration CO | Permit Issued | 05/13/2021 | 07/19/2021 | Contractor DAVARO CONTRACTING | Convert existing 3-family dwelling to 2-family dwelling. Remove and install interior partitions, doors and finishes. Install AC units and … |
| B00355063 ↗ | 135 CARLTON AVE BROOKLYN | Alteration | Signed-off | 06/12/2020 | 06/24/2021 | Design DENISE LEE ARCHITECT Contractor MPH CONSTRUCTION INC | In conjunction with renovation of existing duplex apartment, Mechanical work only. |
| M00436762 ↗ | 304 WEST 88 STREET MANHATTAN | Alteration | Signed-off | 12/11/2020 | 06/22/2021 | Design DENISE LEE ARCHITECT Contractor MPH CONSTRUCTION INC Filer DEZIGNPLUS | In conjunction with renovation of existing apartment on the 2nd Floor APT# 2B. mechanical work only. |
| M00502916 ↗ | 20 WEST 77 STREET MANHATTAN | Alteration | Permit Issued | 04/20/2021 | 05/19/2021 | Design GARY ROSARD ARCHITECT Contractor AQUA PLUMBING & HTNG CORP Filer HAQUE AND ASSOCIATES LLC | PLUMBING WORK FILED IN CONJUNCTION WITH THE RENOVATION IN THE APARTMENT 12A ON THE 12TH FLOOR. NO CHANGE OF USE, OCCUPANCY OR EGRESS. GC WOR… |
| B00480047 ↗ | 24 ST CHARLES PLACE BROOKLYN | Alteration | Signed-off | 03/09/2021 | 05/10/2021 | Contractor BIG APPLE SEWER & DRAIN I | Remove and replace plumbing fixtures. No change to use, egress or occupancy. |
| Q00198478 ↗ | 20 MARKWOOD PLACE QUEENS | Alteration | Signed-off | 08/19/2019 | 05/10/2021 | Design G. PEROTTO ASSOCIATES Contractor HOCHSEL INC Filer G.PEROTTO ASSOCIATES | install three split system condensers in open space at east side of dwelling |
| M00502627 ↗ | 20 WEST 77 STREET MANHATTAN | Alteration | Permit Issued | 04/21/2021 | 05/07/2021 | Design GARY ROSARD ARCHITECT Contractor CORNERSTONE CONSTRUCTION Filer HAQUE AND ASSOCIATES LLC | INTERIOR RENOVATION OF THE KITCHEN AND BATHROOM AREA AT THE EXISTING APARTMENT #12A ON THE 12TH FLOOR INCLUDING MINOR FRAMING AND PLUMBING W… |
| M00494316 ↗ | 507 WEST 111 STREET MANHATTAN | Alteration | Signed-off | 04/08/2021 | 04/22/2021 | Design DENISE LEE ARCHITECT Contractor 360 PRESTIGE CONTRACTING | INTERIOR RENOVATION OF AN EXISTING APARTMENT 64 ON 6TH FLOOR OF AN EXISTING RESIDENTIAL BUILDING. ARCHITECTURAL WORK ONLY. NO CHANGE IN USE,… |
| M00494327 ↗ | 507 WEST 111 STREET MANHATTAN | Alteration | Signed-off | 04/08/2021 | 04/22/2021 | Design DENISE LEE ARCHITECT Contractor 360 PRESTIGE CONTRACTING Filer ADAM MAISER | MECHANICAL WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF AN EXISTING APARTMENT 64 ON 6TH FLOOR OF AN EXISTING RESIDENTIAL BUILDING. NO CHA… |
| B00252756 ↗ | 125 CHAUNCEY STREET BROOKLYN | Alteration | Signed-off | 12/09/2019 | 03/09/2021 | Contractor THOMAS MARTIN DESIGN & B* | INSTALLATION OF AC UNITS AND EXHAUST FANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. |
| M00269450 ↗ | 5 WEST 65 STREET MANHATTAN | Alteration | Signed-off | 01/13/2020 | 03/03/2021 | Design BFB ARCHITECT, PC Contractor MARATHON MECHANICAL LLC | GENERAL PLUMBING MODIFICATIONS IN CONNECTION WITH INTERIOR APARTMENT RENOVATION FOR UNIT 27G; THERE IS NO CHANGE TO OCCUPANCY USE OR EGRESS … |
| M00400218 ↗ | 560 3 AVENUE MANHATTAN | Alteration | Signed-off | 11/09/2020 | 12/04/2020 | Design ARCHITECTURE WORKSHOP PC Contractor AQUEDUCT MECHANICAL CORP Filer JAM CONSULTANTS, INC. | Installation of new shower and washing machine. Removal of one bath tub. Replace one sink and one dishwasher. Relocate one toilet and lavato… |
| B00416136 ↗ | 306 2 STREET BROOKLYN | Alteration | Signed-off | 10/28/2020 | 11/13/2020 | Contractor SMART PLBG & HTG CORP | REVISE GAS DRYER TO ELECTRIC DRYER, THERE IS NO GAS WORK. |
| M00369438 ↗ | 225 CENTRAL PARK WEST MANHATTAN | Alteration | Signed-off | 07/20/2020 | 07/31/2020 | Contractor NICE PLUMBING CORP | REPLACEMENT OF PLUMBING FIXTURES AT KITCHEN AND BATHROOMS. NEW WASHING MACHINE. |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 06/15/2026 | Fire-Resistant Penetrations and Joints | 54 DOUGLASS STREET | Edward Zevallos | special |
| 06/15/2026 | Fenestration and door U-factor and product ratings | 54 DOUGLASS STREET | Edward Zevallos | energy_progress |
| 06/15/2026 | Fenestration air leakage | 54 DOUGLASS STREET | Edward Zevallos | energy_progress |
| 06/15/2026 | Lighting in dwelling units | 54 DOUGLASS STREET | Edward Zevallos | energy_progress |
| 06/15/2026 | Final | 54 DOUGLASS STREET | Edward Zevallos | progress |
| 06/15/2026 | Fire-Resistant Penetrations and Joints | 54 DOUGLASS STREET | Edward Zevallos | special |
| 03/16/2026 | Final | 169 WEST 95 STREET | Robert Garneau | progress |
| 03/16/2026 | Lighting in dwelling units | 169 WEST 95 STREET | — | energy_progress |
| 03/16/2026 | Fire-Resistant Penetrations and Joints | 169 WEST 95 STREET | Edward Zevallos | special |
| 03/10/2026 | Energy Code Compliance Inspections | 220 WEST 19 STREET | Edward Zevallos | progress |
| 03/10/2026 | Final | 220 WEST 19 STREET | Edward Zevallos | progress |
| 03/10/2026 | Fire-Resistant Penetrations and Joints | 220 WEST 19 STREET | Edward Zevallos | special |
| 03/10/2026 | Interior lighting power | 220 WEST 19 STREET | Edward Zevallos | energy_progress |
| 03/10/2026 | Lighting controls | 220 WEST 19 STREET | Edward Zevallos | energy_progress |
| 03/10/2026 | Fire-Resistance Rated Construction | 220 WEST 19 STREET | Edward Zevallos | progress |
| 02/05/2026 | Fire-Resistant Penetrations and Joints | 310 RIVERSIDE DRIVE | Edward Zevallos | special |
| 02/05/2026 | Final | 310 RIVERSIDE DRIVE | Robert Garneau | progress |
| 02/05/2026 | Lighting in dwelling units | 310 RIVERSIDE DRIVE | Robert Garneau | energy_progress |
| 01/02/2026 | Fire-Resistant Penetrations and Joints | 1435 LEXINGTON AVENUE | Edward Zevallos | special |
| 01/02/2026 | Fire-Resistant Penetrations and Joints | 1435 LEXINGTON AVENUE | Edward Zevallos | special |
| 01/02/2026 | Final | 1435 LEXINGTON AVENUE | Eric Ansel | progress |
| 01/02/2026 | Lighting in dwelling units | 1435 LEXINGTON AVENUE | Eric Ansel | energy_progress |
| 09/15/2025 | Fire-Resistant Penetrations and Joints | 1156 FULTON STREET | Edward Zevallos | special |
| 09/15/2025 | Fire-Resistant Penetrations and Joints | 1156 FULTON STREET | Edward Zevallos | special |
| 09/15/2025 | Mechanical Systems | 1156 FULTON STREET | Edward Zevallos | special |
| 09/15/2025 | Final | 1156 FULTON STREET | Edward Zevallos | progress |
| 09/15/2025 | Lighting controls | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 09/15/2025 | HVAC-R and service water heating system controls | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 09/15/2025 | HVAC-R and service water heating equipment | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 09/15/2025 | Fenestration and door U-factor and product ratings | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 09/15/2025 | HVAC-R and service water piping design and insulation | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 09/15/2025 | Fenestration air leakage | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 08/30/2025 | Mechanical Systems | 1156 FULTON STREET | Edward Zevallos | special |
| 08/30/2025 | Final | 1156 FULTON STREET | Edward Zevallos | progress |
| 08/30/2025 | HVAC-R and service water heating equipment | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 08/30/2025 | Fire-Resistant Penetrations and Joints | 1156 FULTON STREET | Edward Zevallos | special |
| 08/30/2025 | Lighting controls | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 08/30/2025 | HVAC-R and service water heating system controls | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 08/30/2025 | Fenestration air leakage | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 08/30/2025 | HVAC-R and service water piping design and insulation | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 08/30/2025 | Fire-Resistant Penetrations and Joints | 1156 FULTON STREET | Edward Zevallos | special |
| 08/30/2025 | Fenestration and door U-factor and product ratings | 1156 FULTON STREET | Edward Zevallos | energy_progress |
| 06/18/2025 | Fire-Resistant Penetrations and Joints | 1 CENTRE STREET | Edward Zevallos | special |
| 06/18/2025 | Fire-Resistance Rated Construction | 1 CENTRE STREET | Edward Zevallos | progress |
| 06/18/2025 | Final | 1 CENTRE STREET | — | progress |
| 05/05/2025 | Fire-Resistant Penetrations and Joints | 31 WEST 69 STREET | Edward Zevallos | special |
| 03/26/2025 | Fire-Resistant Penetrations and Joints | 1 CENTRE STREET | Edward Zevallos | special |
| 03/02/2025 | Final | 415 EAST 80 STREET | Robert Garneau | progress |
| 03/02/2025 | Lighting in dwelling units | 415 EAST 80 STREET | Robert Garneau | energy_progress |
| 03/02/2025 | Fire-Resistant Penetrations and Joints | 415 EAST 80 STREET | Edward Zevallos | special |