| Owner | Filings | Most Recent |
|---|---|---|
| MEMORIAL SLOAN KETTERING -1275 Y | 71 | 03/21/2026 |
| MEMORIAL HOSPITAL FOR CANCEER | 38 | 03/21/2026 |
| SKI REALTY | 9 | 03/21/2026 |
| MEMORIAL SLOAN HOSPITAL | 6 | 03/21/2026 |
| PRESTIGE CONSTRUCTION SERVICES | 6 | 03/21/2026 |
| 866 THIRD AVENUE CONDOMINIUM | 6 | 03/21/2026 |
| MSKCC | 3 | 03/21/2026 |
| METROPOLITAN ENTERPRISES | 1 | 03/21/2026 |
| MEMORIAL HOSPITAL | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AKF ENGINEERS, LLP | 15 | 04/30/2026 |
| GALLIGAN ASSOCIATES, LLC | 1 | 12/04/2025 |
| EFH ARCHITECTURE | 5 | 11/20/2025 |
| HORACIO REPETTO | 1 | 02/06/2025 |
| JAROS BAUM & BOLLES | 1 | 04/06/2023 |
| BRAND ACCESS SOLUTIONS | 3 | 09/20/2022 |
| LIZARDOS ENGINEERING | 2 | 04/16/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| RPO | 38 | 03/21/2026 |
| RESOLUTION EXPEDITING | 2 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 6 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 6 | 03/21/2026 |
| RIGGINING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MICHAEL ANTHONY CONTRACTING | General Contractor | 9 | 07/08/2026 |
| SAFWAY ATLANTIC, LLC | General Contractor | 8 | 07/08/2026 |
| JGN CONSTRUCTION CORP | General Contractor | 5 | 04/09/2026 |
| TRISTATE PLBG SVCS CORP | Plumbing | 5 | 07/08/2026 |
| ALLIANCE PLUMBING CORP | Plumbing | 4 | 07/08/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 4 | 03/22/2026 |
| L.F. DRISCOLL COMPANY LLC | General Contractor | 4 | 07/08/2026 |
| CONSIGLI CONSTRUCTION CO | General Contractor | 4 | 07/08/2026 |
| ASHLAR MECHANICAL CORP | Fire Protection | 3 | 09/09/2026 |
| KRAUS, JOSEPH | Electrical | 2 | 03/21/2026 |
| STEFL, J | Electrical | 1 | 03/21/2026 |
| ADCO ELEC'L CORP | Electrical | 1 | 03/22/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 1 | 07/08/2026 |
| NICHOLAS STEFANOU | Electrical | 1 | 03/21/2026 |
| INTERSTATE MECH SVCS INC | General Contractor | 1 | 04/09/2026 |
| MAGOOLAGHAN, ROBERT | Electrical | 1 | 03/21/2026 |
| LUPINSKI, MAREK | Electrical | 1 | 03/21/2026 |
| JOSHUA ANDERSON | Electrical | 1 | 03/21/2026 |
| GUTHRIE, VEROLD | Electrical | 1 | 03/21/2026 |
| FLORENTINE ARTISTIC IRON | Electrical | 1 | 03/21/2026 |
| SCHWERDTFEGER, MARCUS | Electrical | 1 | 03/21/2026 |
| CHAYUT, ALLEN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECTONIC ENGINEERING CONS | 106 | 16 | 04/30/2026 |
| O'ROURKE ENGINEERING, LLC | 5873 | 1 | 12/04/2025 |
| BUREAU VERITAS NA | 6902 | 2 | 04/16/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | ASHLAR MECHANICAL CORP | 09/08/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | MICHAEL ANTHONY CONTRACTING | 07/02/2026 |
| DOB NOW | General Construction | Permit Issued | MICHAEL ANTHONY CONTRACTING | 07/02/2026 |
| DOB NOW | General Construction | Signed-off | CONSIGLI CONSTRUCTION CO | 05/15/2026 |
| DOB NOW | Mechanical Systems | Signed-off | CONSIGLI CONSTRUCTION CO | 05/15/2026 |
| DOB NOW | Plumbing | Permit Issued | ALLIANCE PLUMBING CORP | 04/28/2026 |
| DOB NOW | General Construction | Signed-off | MICHAEL ANTHONY CONTRACTING | 01/09/2026 |
| DOB NOW | Mechanical Systems | Signed-off | MICHAEL ANTHONY CONTRACTING | 12/22/2025 |
| DOB NOW | Mechanical Systems | Signed-off | INTERSTATE MECH SVCS | 12/17/2025 |
| DOB NOW | General Construction | Permit Issued | MICHAEL ANTHONY CONTRACTING | 12/17/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | MICHAEL ANTHONY CONTRACTING | 12/17/2025 |
| DOB NOW | Sprinklers | Signed-off | TRISTATE PLBG SVCS CORP | 08/12/2025 |
| DOB NOW | Plumbing | Signed-off | SIRINA FIRE PROT CORP | 08/12/2025 |
| DOB NOW | General Construction | Signed-off | CONSIGLI CONSTRUCTION CO | 05/13/2025 |
| DOB NOW | Mechanical Systems | Signed-off | CONSIGLI CONSTRUCTION CO | 05/13/2025 |
| DOB NOW | Plumbing | Signed-off | CARDOZA PLUMBING WMBE | 04/08/2025 |
| DOB NOW | General Construction | Signed-off | JGN CONSTRUCTION CORP | 12/31/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JGN CONSTRUCTION CORP | 12/27/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | L.F. DRISCOLL COMPANY LLC | 04/24/2024 |
| DOB NOW | Plumbing | Signed-off | CARDOZA PLUMBING WMBE | 01/22/2024 |
| DOB NOW | General Construction | Permit Issued | L.F. DRISCOLL COMPANY LLC | 01/18/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 01/16/2024 |
| DOB NOW | Plumbing | Signed-off | CARDOZA PLUMBING WMBE | 12/15/2023 |
| DOB NOW | Mechanical Systems | Signed-off | JGN CONSTRUCTION CORP | 12/11/2023 |
| DOB NOW | General Construction | Signed-off | JGN CONSTRUCTION CORP | 12/11/2023 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | SAFWAY ATLANTIC, LLC | 09/27/2023 |
| DOB NOW | Supported Scaffold | Permit Issued | SAFWAY ATLANTIC, LLC | 09/27/2023 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | SAFWAY ATLANTIC, LLC | 09/27/2023 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | SAFWAY ATLANTIC, LLC | 09/20/2022 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | SAFWAY ATLANTIC, LLC | 05/12/2022 |
| DOB NOW | Supported Scaffold | Permit Issued | SAFWAY ATLANTIC, LLC | 05/12/2022 |
| DOB NOW | Sprinklers | Signed-off | ASHLAR MECHANICAL CORP | 05/10/2021 |
| DOB NOW | Standpipe | Signed-off | ASHLAR MECHANICAL CORP | 03/02/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | MICHAEL ANTHONY CONTRACTING | 06/04/2020 |
| DOB NOW | Mechanical Systems | Permit Issued | MICHAEL ANTHONY CONTRACTING | 04/24/2020 |
| BIS | SP | ISSUED | CURRENT FIRE PROTECTION INC | 11/03/2025 |
| BIS | SP | ISSUED | CURRENT FIRE PROTECTION INC | 10/21/2024 |
| BIS | SP | ISSUED | CURRENT FIRE PROTECTION INC | 10/13/2023 |
| BIS | PL | ISSUED | PAR PLUMBING CO., INC | 03/30/2023 |
| BIS | SP | ISSUED | CURRENT FIRE PROTECTION INC | 10/18/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/23/2026 | Signed-off | MICHAEL ANTHONY CONTRACTI | Heating Systems | Heating Titus ×1 |
| 12/04/2025 | Signed-off | INTERSTATE MECH SVCS INC | Others | Other __Junk__ AQ4L-PFS 4,851,400 BTU · Heat Exchanger ×2 |
| 07/15/2024 | Permit Issued | L.F. DRISCOLL COMPANY LLC | Air Conditioning Systems | Cooling Liebert MTC38W 47,000 BTU · Wshp ×2 |
| 04/06/2023 | — | — | Associated Ducts and Piping | Ducts & Piping N/A n/a Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/30/2026 | Signed-off | SIRINA FIRE PROT CORP | 314 heads |
| 03/23/2026 | Permit Issued | ASHLAR MECHANICAL CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/30/2026 | Signed-off | TRISTATE PLBG SVCS CORP | Medical Gas, Water/Sanitary |
| 03/23/2026 | Permit Issued | CARDOZA PLUMBING WMBE | Medical Gas, Water/Sanitary |
| 07/15/2024 | Signed-off | ALLIANCE PLUMBING CORP | Medical Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/18/2026 | Complete | NJS ELEC'L SERVICES CORP. | General Wiring |
| 06/19/2025 | Complete | HARLEY ELECTRIC CO., INC. | General Wiring |
| 09/16/2024 | Complete | ADCO ELEC'L CORP | General Wiring |
| 01/26/2024 | Permit Issued | E-J ELEC. INSTALLATION CO | 6 meters, 1 new_meters |
| 04/28/2020 | Complete | NJS ELEC'L SERVICES CORP. | General Wiring |
| 01/26/2020 | Permit Issued | TOM FITZPATRICK ELECTRICA | HVAC Wiring |
| 12/04/2019 | Complete | MEM. SLOAN-KETTERING CANC | General Wiring |
| 10/23/2019 | Complete | MEM. SLOAN-KETTERING CANC | — |
| 09/04/2018 | Permit Issued | HARLEY ELECTRIC CO., INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/11/2022 | Permit Issued | SAFWAY ATLANTIC, LLC | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/12/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/17/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/17/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/05/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/30/2026 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 04/30/2026 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 04/30/2026 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| 04/15/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/31/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/31/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/01/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/24/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 10/17/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/16/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/15/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/02/2025 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 07/02/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/27/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/05/2024 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 11/05/2024 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/05/2026 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 05/05/2026 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 05/05/2026 | Sprinkler Systems | GEORGE GHEBRYAL | special |
| 04/29/2026 | Sprinkler Systems | GEORGE GHEBRYAL | special |
| 04/29/2026 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 04/29/2026 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 03/20/2026 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 03/20/2026 | Sprinkler Systems | GEORGE GHEBRYAL | special |
| 03/20/2026 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 01/20/2026 | HVAC-R and service water piping design and insulation | GEORGE GHEBRYAL | energy_progress |
| 01/20/2026 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 01/20/2026 | Mechanical Systems | GEORGE GHEBRYAL | special |
| 01/20/2026 | Exhaust and Vent Systems in Plenums and Ducts | GEORGE GHEBRYAL | special |
| 01/20/2026 | Duct leakage testing, insulation and design | GEORGE GHEBRYAL | energy_progress |
| 01/20/2026 | Final | GEORGE GHEBRYAL | progress |
| 01/06/2026 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 01/06/2026 | Sprinkler Systems | GEORGE GHEBRYAL | special |
| 01/06/2026 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 12/03/2025 | HVAC-R and service water heating equipment | PETER MOKRIS | energy_progress |
| 12/03/2025 | Maintenance information | PETER MOKRIS | energy_progress |
| 12/03/2025 | Fire-Resistant Penetrations and Joints | BRIAN O'ROURKE | special |
| 12/03/2025 | Mechanical Systems | BRIAN O'ROURKE | special |
| 12/03/2025 | Energy Code Compliance Inspections | PETER MOKRIS | progress |
| 12/03/2025 | Final | PETER MOKRIS | progress |
| 12/03/2025 | HVAC-R and service water piping design and insulation | PETER MOKRIS | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| MSKCC Anti-tumor & Gene Editing Lab | Laboratory | Floor 3 | Project M01130144 |