| Owner | Filings | Most Recent |
|---|---|---|
| Montperia | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MY Architect | 2 | 05/28/2026 |
| Howard I Shapiro & Associates | 4 | 04/07/2026 |
| Tohfaz Uddin PE | 2 | 03/06/2026 |
| FL&M Engineering Design & Inspection | 3 | 02/25/2026 |
| Ejc Engineering | 8 | 12/08/2025 |
| Potential Engineering | 1 | 10/23/2025 |
| Grand Millennium Consulting Engineering | 4 | 09/26/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 Expediting Service | 4 | 03/21/2026 |
| Next Step Building Solutions | 2 | 03/21/2026 |
| JM Zoning | 25 | 03/21/2026 |
| Howard I Shapiro Associates | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JLS Group Construction | Scaffold | 12 | 08/20/2026 |
| JLS Group Construction | General Contractor | 12 | 10/09/2026 |
| Safepipe Plumbing | Fire Protection | 3 | 07/08/2026 |
| Parksite Construction | General Contractor | 2 | 04/09/2026 |
| MC Superstructure | Scaffold | 1 | 04/09/2026 |
| Spring Scaffolding | Scaffold | 1 | 04/09/2026 |
| Safepipe Plumbing | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Ark Engineering | 7261 | 11 | 05/28/2026 |
| Professional Solutions GR | 1756 | 1 | 10/23/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | JLS Group Construction | 10/08/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | JLS Group Construction | 08/18/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JLS Group Construction | 08/12/2026 |
| DOB NOW | Construction Fence | Permit Issued | JLS Group Construction | 07/20/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | JLS Group Construction | 04/07/2026 |
| DOB NOW | General Construction | Permit Issued | JLS Group Construction | 02/12/2026 |
| DOB NOW | Standpipe | Permit Issued | Bellerose Plumbing & Heating | 02/02/2026 |
| DOB NOW | Sprinklers | Permit Issued | Bellerose Plumbing & Heating | 02/02/2026 |
| DOB NOW | Standpipe | Permit Issued | Bellerose Plumbing & Heating | 02/02/2026 |
| DOB NOW | Structural | Permit Issued | Parksite Construction | 01/30/2026 |
| DOB NOW | General Construction | Permit Issued | Parksite Construction | 01/27/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Spring Scaffolding | 01/27/2026 |
| DOB NOW | Plumbing | Permit Issued | Bellerose Plumbing & Heating | 01/25/2026 |
| DOB NOW | Structural | Permit Issued | JLS Group Construction | 01/14/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | MC Superstructure | 01/14/2026 |
| DOB NOW | Foundation | Signed-off | JLS Group Construction | 01/09/2026 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | JLS Group Construction | 12/04/2025 |
| DOB NOW | Foundation | Signed-off | JLS Group Construction | 09/12/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | JLS Group Construction | 08/18/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | JLS Group Construction | 08/18/2025 |
| DOB NOW | Support of Excavation | Signed-off | JLS Group Construction | 08/15/2025 |
| DOB NOW | Construction Fence | Permit Issued | JLS Group Construction | 07/17/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/28/2026 | Permit Issued | JLS Group Construction | Air Conditioning Systems, Ventilation Systems | Cooling Mitsubishi Electric PURY-EP288TSNU-A1 2,888,000 BTU · Vrf Outdoor ×14 PURY-EP336TSNU-A1 336,000 BTU · Vrf Outdoor ×7 MXZ-SM48NAM2-U1 48,000 BTU · Heat Pump Outdoor ×2 MXZ-SM36NAM2-U1 36,000 BTU · Heat Pump Outdoor ×1 PURY-EP264TSNU-A1 264,000 BTU · Vrf Outdoor ×1 PURY-EP288YSNU-A1 288,000 BTU · Vrf Outdoor ×1 PURY-EP336YTSNU-A1 336,000 BTU · Vrf Outdoor ×1 PURY-EP96TNU-A1 96,000 BTU · Vrf Outdoor ×1 Greenheck ×1 Ventilation Greenheck ×219 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Permit Issued | Safepipe Plumbing | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Permit Issued | Safepipe Plumbing | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/18/2026 | Permit Issued | Tuxedo Electrical Contracting | — |
| 01/28/2026 | Permit Issued | Lumos Electric | — |
| 01/14/2026 | Permit Issued | Nash Electric Services | — |
| 01/06/2026 | Permit Issued | Lumos Electric | — |
| 01/06/2026 | Permit Issued | Lumos Electric | — |
| 12/12/2025 | Permit Issued | Lumos Electric | General Wiring |
| 09/25/2025 | Permit Issued | Lumos Electric | 3 meters, 3 new_meters |
| 04/15/2025 | Permit Issued | AL-Lectric Elect'l Contracting | 3 meters, 3 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Permit Issued | JLS Group Construction | Concrete |
| 10/23/2025 | Permit Issued | Parksite Construction | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/25/2026 | Permit Issued | MC Superstructure | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/08/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/15/2026 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 04/15/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 03/19/2026 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 03/19/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 02/04/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/30/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/05/2025 | Standpipe Systems | — | special |
| 11/10/2025 | Concrete - Cast-In-Place | George Lau | special |
| 10/20/2025 | Excavations - Sheeting, Shoring, and Bracing | SAMER ABOU-GHAIDA | special |
| 10/20/2025 | Structural Stability – Alterations of existing buildings | SAMER ABOU-GHAIDA | special |
| 10/20/2025 | Structural Steel - Details | SAMER ABOU-GHAIDA | special |
| 10/20/2025 | Deep Foundation Elements | SAMER ABOU-GHAIDA | special |
| 10/20/2025 | Final | SAMER ABOU-GHAIDA | progress |
| 10/20/2025 | Footing and Foundation | SAMER ABOU-GHAIDA | progress |
| 10/20/2025 | Concrete - Cast-In-Place | SAMER ABOU-GHAIDA | special |
| 10/02/2025 | Post-installed Anchors | George Lau | special |
| 10/02/2025 | Excavations - Sheeting, Shoring, and Bracing | George Lau | special |
| 10/02/2025 | Subsurface Conditions – Fill Placement & In-Place Density | George Lau | special |
| 10/02/2025 | Structural Steel - Welding | George Lau | special |
| 10/02/2025 | Concrete - Cast-In-Place | George Lau | special |
| 10/02/2025 | Subgrade Inspections | George Lau | special |
| 10/02/2025 | Structural Steel - Details | George Lau | special |
| 09/26/2025 | Subsurface Conditions – Fill Placement & In-Place Density | George Lau | special |
| 09/26/2025 | Subgrade Inspections | George Lau | special |
| 09/26/2025 | Structural Steel - Welding | George Lau | special |
| 09/26/2025 | Structural Steel - Details | George Lau | special |
| 09/26/2025 | Post-installed Anchors | George Lau | special |
| 09/26/2025 | Excavations - Sheeting, Shoring, and Bracing | George Lau | special |
| 09/26/2025 | Concrete - Cast-In-Place | George Lau | special |
| 09/15/2025 | Maintenance information | — | energy_progress |
| 09/15/2025 | HVAC-R and service water heating system controls | — | energy_progress |