| Owner | Filings | Most Recent |
|---|---|---|
| 424 West 33rd Street | 69 | 03/21/2026 |
| 424 W 33rd St Associates | 45 | 03/21/2026 |
| Brookfield powered by CBRE | 41 | 06/28/2026 |
| West 31st Street | 8 | 07/08/2026 |
| 9 33rd Associates L P | 2 | 03/21/2026 |
| Vectra Mngmnt Group | 2 | 03/21/2026 |
| S Associates | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Wellworth Consulting | 10 | 10/13/2026 |
| Tohfaz Uddin PE | 9 | 10/13/2026 |
| Gilsanz Murray Steficek | 7 | 02/06/2026 |
| Meyers+ Engineers | 15 | 01/26/2026 |
| S9 Architecture and Engineering | 5 | 10/22/2025 |
| Leon Skvirsky PE | 6 | 10/09/2025 |
| Concept Design Group | 3 | 09/15/2025 |
| Socotec | 4 | 08/28/2025 |
| Kaback Enterprises | 2 | 07/15/2025 |
| Bellsey & Associates | 9 | 03/31/2025 |
| HKC Engineering | 2 | 12/23/2024 |
| Cameron Engineering | 27 | 11/08/2024 |
| Diaz Architects Inc., PA | 5 | 07/23/2024 |
| WB Engineers & Consultants | 3 | 03/06/2024 |
| HLW International | 1 | 03/05/2024 |
| MSP Engineering | 3 | 11/21/2023 |
| Shop Architects | 1 | 07/12/2023 |
| Goldman Copeland Associates | 9 | 04/24/2023 |
| Andrew Formichella | 1 | 09/29/2022 |
| Brand Access Solutions | 4 | 08/16/2022 |
| Carry D. McLain - Architect | 2 | 06/28/2022 |
| Loring Consulting Engineers | 6 | 06/27/2022 |
| FL&M Engineering Design & Inspection | 1 | 01/04/2022 |
| Barak Pliskin | 1 | 04/27/2021 |
| Robert Derector Associates | 5 | 04/13/2021 |
| Safway Atlantic | 5 | 12/26/2019 |
| Jaros Baum & Bolles | 1 | 11/19/2019 |
| KZ Engineering | 1 | 12/11/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| DVA Advisors | 65 | 03/21/2026 |
| William Vitacco Associates | 57 | 03/21/2026 |
| Spring Scaffolding | 16 | 03/21/2026 |
| Building Brothers | 12 | 03/21/2026 |
| Milrose Consultants | 12 | 03/21/2026 |
| Municipal Building Consultants | 1 | 03/21/2026 |
| A1 Expediting Service | 18 | 03/21/2026 |
| Green Studio | 2 | 03/21/2026 |
| Synergy Building Consultants | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Safway Atlantic | Scaffold | 17 | 07/08/2026 |
| Spring Scaffolding | Scaffold | 16 | 10/14/2026 |
| JRM Construction Management | General Contractor | 13 | 08/26/2026 |
| Holt Construction | General Contractor | 7 | 07/08/2026 |
| Par Environmental | General Contractor | 6 | 07/08/2026 |
| Allertonfox Construction | General Contractor | 6 | 07/08/2026 |
| Blade Contracting | General Contractor | 5 | 07/08/2026 |
| Universal Management & Cont | General Contractor | 5 | 07/08/2026 |
| Demar Plumbing | Fire Protection | 4 | 07/08/2026 |
| Tishman Interiors | General Contractor | 4 | 07/08/2026 |
| Timbil Mechanical | specialty_contractor | 4 | 03/21/2026 |
| Benjamin Group Enterprises | General Contractor | 3 | 07/08/2026 |
| Darby Construction Service | General Contractor | 3 | 03/21/2026 |
| Summit Interiors | General Contractor | 3 | 07/08/2026 |
| Tri-Star Construction | General Contractor | 3 | 06/28/2026 |
| Urban Atelier Group | General Contractor | 3 | 07/08/2026 |
| Demar Plumbing | Plumbing | 3 | 07/08/2026 |
| Abco-Peerless Sprinkler | Fire Protection | 2 | 07/08/2026 |
| Ashlar Mechanical | Fire Protection | 2 | 07/08/2026 |
| Best Plumbing & Heating & Cooling | Fire Protection | 2 | 07/08/2026 |
| M & S Buildings Services | Fire Protection | 2 | 07/08/2026 |
| Wolf Construction Corp 20 | General Contractor | 2 | 07/08/2026 |
| NYC Fire Sprinkler | Fire Protection | 2 | 07/08/2026 |
| Sirina Fire Protection | Fire Protection | 2 | 07/08/2026 |
| Active Signs | Sign hanger | 2 | 07/08/2026 |
| Evergreen Mechanical | Plumbing | 2 | 07/08/2026 |
| Evergreen Mechanical | Fire Protection | 2 | 07/08/2026 |
| Service Sign Erectors Co | Sign hanger | 2 | 07/08/2026 |
| M & S Mechanical Services | Plumbing | 1 | 07/08/2026 |
| Par Fire Protection | Fire Protection | 1 | 07/08/2026 |
| Parkview P&H | Plumbing | 1 | 07/08/2026 |
| Five Star Awnings | specialty_contractor | 1 | 04/09/2026 |
| PSI Partners | Fire Protection | 1 | 07/08/2026 |
| Raptor Mechanical | Plumbing | 1 | 07/08/2026 |
| NJS Electrical Services | Electrical | 1 | 03/22/2026 |
| W5 Group | General Contractor | 1 | 04/09/2026 |
| Blade Contracting | Scaffold | 1 | 07/08/2026 |
| Star-Delta Electric | Electrical | 1 | 03/22/2026 |
| Robert B. Samuels | Electrical | 1 | 03/22/2026 |
| R. Gunzer | Electrical | 1 | 03/22/2026 |
| Denko Mechanical | Fire Protection | 1 | 07/08/2026 |
| Full Capacity Fire | Fire Protection | 1 | 07/08/2026 |
| George Breslaw Plumbing | Plumbing | 1 | 07/08/2026 |
| Mac Felder | Plumbing | 1 | 07/08/2026 |
| Mackler Master Fire | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Hudson Peaks Consulting | 8381 | 17 | 02/06/2026 |
| Socotec | 301 | 1 | 10/22/2025 |
| MEP Inspections | 1102 | 6 | 09/15/2025 |
| Socotec Engineering | 4983 | 2 | 08/28/2025 |
| Domani Inspection Service | 843 | 8 | 08/28/2025 |
| Consulting and Testing SE | 6152 | 53 | 03/31/2025 |
| Enthink Engineers | 6247 | 1 | 03/06/2024 |
| Jaros, Baum & Bolles | 1092 | 1 | 07/12/2023 |
| Milrose Consultants | 2003 | 4 | 06/27/2022 |
| G. Blinn Consulting | 2894 | 2 | 01/19/2022 |
| Lilker Associates Consulting | 816 | 5 | 04/13/2021 |
| Atlantic Engineeringlabor | 1381 | 1 | 11/19/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Spring Scaffolding | 10/13/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Spring Scaffolding | 10/13/2026 |
| DOB NOW | General Construction | Permit Issued | JRM Construction Management | 08/03/2026 |
| DOB NOW | Structural | Permit Issued | JRM Construction Management | 05/19/2026 |
| DOB NOW | Sprinklers | Signed-off | Best Plumbing & Heating & Cooling | 05/14/2026 |
| DOB NOW | Sprinklers | Signed-off | Best Plumbing & Heating & Cooling | 05/13/2026 |
| DOB NOW | General Construction | Permit Issued | JRM Construction Management | 05/11/2026 |
| DOB NOW | Plumbing | Permit Issued | Demar Plumbing | 05/04/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JRM Construction Management | 04/28/2026 |
| DOB NOW | Standpipe | Permit Issued | Demar Plumbing | 04/28/2026 |
| DOB NOW | Sprinklers | Permit Issued | Demar Plumbing | 04/28/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Spring Scaffolding | 04/16/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Spring Scaffolding | 04/15/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | Spring Scaffolding | 04/15/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Spring Scaffolding | 04/15/2026 |
| DOB NOW | Construction Fence | Permit Issued | Spring Scaffolding | 04/15/2026 |
| DOB NOW | Sprinklers | Permit Issued | Demar Plumbing | 03/30/2026 |
| DOB NOW | Plumbing | Permit Issued | Demar Plumbing | 03/30/2026 |
| DOB NOW | Sprinklers | Permit Issued | Demar Plumbing | 03/25/2026 |
| DOB NOW | Plumbing | Permit Issued | Demar Plumbing | 03/25/2026 |
| DOB NOW | General Construction | Signed-off | JRM Construction Management | 02/10/2026 |
| DOB NOW | Structural | Permit Issued | JRM Construction Management | 02/05/2026 |
| DOB NOW | Mechanical Systems | Signed-off | JRM Construction Management | 01/30/2026 |
| DOB NOW | Structural | Permit Issued | JRM Construction Management | 01/29/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JRM Construction Management | 01/29/2026 |
| DOB NOW | General Construction | Signed-off | JRM Construction Management | 01/29/2026 |
| DOB NOW | Sign | Signed-off | Active Signs | 09/17/2025 |
| DOB NOW | Sign | Signed-off | Active Signs | 09/17/2025 |
| DOB NOW | General Construction | Signed-off | Five Star Awnings | 09/09/2025 |
| DOB NOW | Sprinklers | Signed-off | M & S Buildings Services | 08/14/2025 |
| DOB NOW | Plumbing | Signed-off | Parkview P&H | 08/06/2025 |
| DOB NOW | Sprinklers | Signed-off | M & S Buildings Services | 08/05/2025 |
| DOB NOW | General Construction | Signed-off | W5 Group | 07/28/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | Spring Scaffolding | 07/17/2025 |
| DOB NOW | General Construction | Permit Issued | Tri-Star Construction | 07/11/2025 |
| DOB NOW | General Construction | Signed-off | Urban Atelier Group | 06/23/2025 |
| DOB NOW | Sign | Signed-off | Service Sign Erectors Co | 05/22/2025 |
| DOB NOW | Sign | Signed-off | Service Sign Erectors Co | 05/22/2025 |
| DOB NOW | Structural | Signed-off | Urban Atelier Group | 05/05/2025 |
| DOB NOW | General Construction | Signed-off | Urban Atelier Group | 05/05/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/26/2026 | Permit Issued | JRM Construction Management | Heating and Air Conditioning Systems, Ventilation Systems | |
| 11/15/2024 | Permit Issued | Par Environmental | Associated Ducts and Piping | Ducts & Piping N/A N/A 1 BTU · Ductwork ×2 |
| 05/12/2022 | Signed-off | Par Environmental | Others | Other N/A N/A 1 BTU ×1 |
| 05/18/2020 | Permit Issued | Holt Construction | Associated Ducts and Piping | Ducts & Piping N/A N/A Ductwork |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/26/2026 | Permit Issued | Demar Plumbing | Sprinkler System |
| 12/04/2025 | Permit Issued | Demar Plumbing | Sprinkler System |
| 09/10/2025 | Permit Issued | Demar Plumbing | Sprinkler System |
| 08/28/2025 | Signed-off | Best Plumbing & Heating & Cooling | 2,548 heads |
| 11/15/2024 | — | — | Sprinkler System |
| 06/24/2022 | Permit Issued | Evergreen Mechanical | 1 heads |
| 05/12/2022 | Permit Issued | Denko Mechanical | 288 heads |
| 05/18/2020 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/26/2026 | Permit Issued | Demar Plumbing | — |
| 12/04/2025 | Permit Issued | Demar Plumbing | Water/Sanitary |
| 09/10/2025 | Permit Issued | Demar Plumbing | Water/Sanitary |
| 08/28/2025 | Signed-off | Parkview P&H | Water/Sanitary |
| 11/15/2024 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2026 | Permit Issued | Top Shelf Electric | — |
| 05/26/2026 | Permit Issued | Inter Connection Eletric | General Wiring |
| 03/27/2026 | Permit Issued | Inter Connection Eletric | — |
| 07/25/2025 | Complete | Precision Electrical Cont | General Wiring |
| 05/22/2025 | Permit Issued | Rainbow Electric Co | — |
| 05/22/2025 | Permit Issued | Rainbow Electric Co | — |
| 05/22/2025 | Permit Issued | Rainbow Electric Co | — |
| 05/22/2025 | Permit Issued | Rainbow Electric Co | — |
| 12/11/2024 | Complete | R. Gunzer | General Wiring |
| 08/20/2024 | Permit Issued | All NU Electrical Contracting | 3 meters, 1 new_meters |
| 09/27/2022 | Complete | Konsker Electric | — |
| 12/29/2021 | Complete | Top Shelf Electric | — |
| 02/17/2021 | Permit Issued | Robert Chimenti | 5 meters, 1 new_meters |
| 01/21/2021 | Complete | Dal Electrical | General Wiring |
| 12/22/2020 | Complete | Robert B. Samuels | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/06/2026 | Permit Issued | JRM Construction Management | Concrete |
| 01/26/2026 | Permit Issued | JRM Construction Management | Steel, Concrete |
| 12/04/2025 | Permit Issued | Demar Plumbing | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2026 | Permit Issued | Spring Scaffolding | Fence, Scaffold, Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/12/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/04/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/30/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/30/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/08/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/08/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/08/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/06/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/26/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/21/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/08/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/27/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/09/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/10/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/19/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/18/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/12/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/25/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/17/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/04/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/26/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/22/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/19/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/26/2026 | Structural Steel - High Strength Bolting | GIORGI KHARDZEISHVILI | special |
| 03/26/2026 | Final | GIORGI KHARDZEISHVILI | progress |
| 03/26/2026 | Structural Steel - Details | GIORGI KHARDZEISHVILI | special |
| 03/26/2026 | Sprayed fire-resistant materials | GIORGI KHARDZEISHVILI | special |
| 03/26/2026 | Structural Steel - Welding | GIORGI KHARDZEISHVILI | special |
| 03/26/2026 | Structural Stability – Alterations of existing buildings | GIORGI KHARDZEISHVILI | special |
| 03/26/2026 | Concrete - Cast-In-Place | GIORGI KHARDZEISHVILI | special |
| 03/26/2026 | Post-installed Anchors | GIORGI KHARDZEISHVILI | special |
| 02/05/2026 | Sprayed fire-resistant materials | GIORGI KHARDZEISHVILI | special |
| 02/05/2026 | Post-installed Anchors | GIORGI KHARDZEISHVILI | special |
| 02/05/2026 | Concrete - Cast-In-Place | GIORGI KHARDZEISHVILI | special |
| 02/05/2026 | Final | GIORGI KHARDZEISHVILI | progress |
| 02/05/2026 | Structural Steel - Welding | GIORGI KHARDZEISHVILI | special |
| 02/05/2026 | Structural Steel - High Strength Bolting | GIORGI KHARDZEISHVILI | special |
| 02/05/2026 | Structural Steel - Details | GIORGI KHARDZEISHVILI | special |
| 02/05/2026 | Structural Stability – Alterations of existing buildings | GIORGI KHARDZEISHVILI | special |
| 01/05/2026 | Post-installed Anchors | GIORGI KHARDZEISHVILI | special |
| 01/05/2026 | Fire-Resistant Penetrations and Joints | GIORGI KHARDZEISHVILI | special |
| 12/05/2025 | Final | GIORGI KHARDZEISHVILI | progress |
| 12/05/2025 | Structural Steel - High Strength Bolting | GIORGI KHARDZEISHVILI | special |
| 12/05/2025 | Structural Steel - Welding | GIORGI KHARDZEISHVILI | special |
| 12/05/2025 | Concrete - Cast-In-Place | GIORGI KHARDZEISHVILI | special |
| 12/05/2025 | Sprayed fire-resistant materials | GIORGI KHARDZEISHVILI | special |
| 12/05/2025 | Post-installed Anchors | GIORGI KHARDZEISHVILI | special |
| 12/05/2025 | Structural Stability – Alterations of existing buildings | GIORGI KHARDZEISHVILI | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| P.J. Clarke's | Restaurant / Food Service | Cellar, Floor 1 | Project M01185627 Project M01185651 Project M01185831 Project M01185565 Project M01185589 Project M01121273 Project M01121276 |
| Xxxxxxxxxxxx | Office | Floor 2 | Project M00879419 |
| Regus | Office | Floors 7, 9, 11 | Project M00750317 Project M00750341 Project M00750353 Project M00624477 Project M00624482 Project M00624503 Project M00266834 Project M00266826 |