← Back
Single or multiple dwelling with stores or offices
43 MERCER STREET
MANHATTAN · BIN 1079898
💬 Discuss this project
1868Year Built
4Stories
S9Building Class
M1-5/R7XZoning
9,755 sfGross Floor Area
5Units
Rent Stabilized11 Open Violations ▸
Single or multiple dwelling with stores or offices · Owner of record: 41 MERCER STREET HOLDINGS LLC · 3,670 sf lot · 2.66 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof4p · 3 filings · 20 docs
Floor 410p · 3 filings · 20 docs
Floor 37p · 4 filings · 20 docs
Floor 25p · 3 filings · 20 docs
Floor 13p · 2 filings · 20 docs
Cellar21p · 5 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FORTY THREE MERCER PROPERTY4607/08/2026
OWNERS REP607/08/2026
41 MERCER STREET HOLDINGS LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/15/2021$9.5M—— → —$974/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CITY WIDE EXPEDITING3003/21/2026
AE DESIGN SOLUTION603/21/2026
A E C CONSULTING EXPEDITING203/21/2026
LOUIS STRIAR203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FOUNDATIONS INTERIOR DESIGNGeneral Contractor807/08/2026
CORE SCAFFOLD SYSTEMS INC.General Contractor207/08/2026
AMOK INCPlumbing207/08/2026
CONTACT PLUS ELEC'L CORPElectrical103/22/2026
DOWNEY, CONORElectrical103/21/2026
AMOK INCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ANCORA ENGINEERING, PLLC6818103/20/2025
KAM W CHIU1429905/24/2023
Building Lifecycle
All (90)Filed (20)Permit Issued (9)Signed Off (7)Violation (27)Inspection (6)Objection (2)Special Inspection (19)
04/29/2026
Violation issued (HPD, open)
A
04/06/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY SYSTEM SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01275377-I1
04/06/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01232779-I1
11/17/2025
Violation issued (HPD, open)
I
09/03/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01232779-P1
08/22/2025
Permit issued — Supported Scaffold
M01275377-I1-SF
08/21/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SYSTEM SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01275377-I1
06/04/2025
Violation issued (HPD, open)
A
05/30/2025
Permit issued — Sidewalk Shed
M01232779-I1-SH
05/29/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01232779-I1
03/20/2025
Filed — Alteration
M01165146-I1
02/03/2025
Signed off — Alteration
relocate sprinkler heads at 1st floor as per plans.
M08018626-I1
11/22/2024
Violation issued (HPD, open)
I
04/01/2024
Violation issued (HPD, open)
A
11/15/2023
Violation issued (HPD, open)
I
06/12/2023
Signed off — Alteration
Apt combination on 3rd and 4th floors, install a new stair in a new opening between the floors, general renovation. Reverse swing of the existing bdg entrancedoor , replacing one window with a door at the rear of the 4th floor and adding 4 glass doors@cel
M00712443-I1
05/31/2023
Signed off — Alteration
Mechanical modifications throughout as per plans.
M00740152-I1
05/24/2023
Filed — Alteration
Mechanical modifications throughout as per plans.
M00740152-P2
05/17/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Kam Chiu
05/17/2023
Special inspection requirement — Mechanical Systems
Kam Chiu
05/17/2023
Special inspection requirement — Final
ALEXANDR NERATOFF
05/16/2023
Filed — Alteration
NON-ILLUMINATED NON-ADVERTISING ACCESSORY AWNING - (FLOWER LOGO). NO CHANGE OF USE, EGRESS OR OCCUPANCY.
M00872126-I1
05/16/2023
Special inspection requirement — Final
MOHAMMAD AHEAD
03/22/2023
Signed off — Alteration
Modification to plumbing fixtures per plans. This application in conjunction with application #'s M00712443 & M00712234. No change in use egress or occupancy.
M00732150-I1
03/22/2023
Signed off — Alteration
Interior renovation to 1st floor and cellar as per plans. No change in use egress or occupancy.
M00712234-I1
03/15/2023
Violation issued (HPD, open)
A
03/01/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/28/2023
Filed — Alteration
Modification to plumbing fixtures per plans. This application in conjunction with application #'s M00712443 & M00712234. No change in use egress or occupancy.
M00732150-P3
02/27/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
02/10/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/09/2023
Filed — Alteration
relocate sprinkler heads at 1st floor as per plans.
M08018626-P3
02/07/2023
Special inspection requirement — Sprinkler Systems
Kam Chiu
02/07/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Kam Chiu
01/05/2023
Filed — Alteration
relocate sprinkler heads at 1st floor as per plans.
M08018626-P2
01/04/2023
Special inspection requirement — Sprinkler Systems
Kam Chiu
01/04/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Kam Chiu
12/29/2022
Filed — Alteration
Interior renovation to 1st floor and cellar as per plans. No change in use egress or occupancy.
M00712234-P1
12/29/2022
Objection raised — Admin
12/29/2022
Objection resolved — Addressed
12/29/2022
Special inspection requirement — Final
ALEXANDR NERATOFF
12/22/2022
Permit issued — Mechanical Systems
M00712443-I1-MS
12/22/2022
Permit issued — Structural
M00712443-I1-ST
12/21/2022
Filed — Alteration
relocate sprinkler heads at 1st floor as per plans.
M08018626-P1
12/21/2022
Special inspection requirement — Final
ALEXANDR NERATOFF
12/20/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Kam Chiu
12/20/2022
Special inspection requirement — Sprinkler Systems
Kam Chiu
12/19/2022
Permit issued — Sprinklers
M08018626-I1-EW-SP
12/16/2022
Filed — Alteration
Modification to plumbing fixtures per plans. This application in conjunction with application #'s M00712443 & M00712234. No change in use egress or occupancy.
M00732150-P2
12/09/2022
Special inspection requirement — Final
ALEXANDR NERATOFF
12/09/2022
Special inspection requirement — Mechanical Systems
Kam Chiu
12/08/2022
Filed — Alteration
Apt combination on 3rd and 4th floors, install a new stair in a new opening between the floors, general renovation. Reverse swing of the existing bdg entrancedoor , replacing one window with a door at the rear of the 4th floor and adding 4 glass doors@cel
M00712443-P1
12/01/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
12/01/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/30/2022
Special inspection requirement — Mechanical Systems
Kam Chiu
11/30/2022
Special inspection requirement — Final
ALEXANDR NERATOFF
11/29/2022
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
11/28/2022
Filed — Alteration
Mechanical modifications throughout as per plans.
M00740152-P1
11/21/2022
Filed — Alteration
Modification to plumbing fixtures per plans. This application in conjunction with application #'s M00712443 & M00712234. No change in use egress or occupancy.
M00732150-P1
11/02/2022
Violation issued (HPD, open)
I
10/24/2022
Filed — Alteration
relocate sprinkler heads at 1st floor as per plans.
M08018626-I1
Latest 60 of 90 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offCORE SCAFFOLD SYSTEMS INC08/22/2025
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC05/30/2025
DOB NOWMechanical SystemsSigned-offFOUNDATIONS INTERIOR DESI12/22/2022
DOB NOWStructuralSigned-offFOUNDATIONS INTERIOR DESI12/22/2022
DOB NOWSprinklersSigned-offAMOK INC12/19/2022
DOB NOWMechanical SystemsSigned-offFOUNDATIONS INTERIOR DESI10/06/2022
DOB NOWPlumbingSigned-offAMOK INC09/30/2022
DOB NOWMechanical SystemsSigned-offFOUNDATIONS INTERIOR DESI08/15/2022
DOB NOWGeneral ConstructionSigned-offFOUNDATIONS INTERIOR DESI07/21/2022
BIS—ISSUEDJOHN FURTH PEACHY08/10/2010
BISOTISSUEDJOHN FURTH PEACHY04/27/2010
BIS—ISSUEDJOHN FURTH PEACHY04/27/2010
BISPLISSUEDLYNES PLBG & HTG CORPO08/06/2008
BIS—ISSUEDJOHN FURTH PEACHY06/04/2008
BIS—ISSUEDJOHN FURTH PEACHY01/23/2007
BIS—ISSUEDJOHN FURTH PEACHY06/28/2004
BISSPISSUEDKB PLUMBING & HEATING INC10/03/2001
BISEQISSUEDROBIN CONSTRUCTION INC04/12/2001
BISMHISSUEDROBIN CONSTRUCTION INC04/12/2001
BISOTISSUEDROBIN CONSTRUCTION INC04/12/2001
BISOTISSUEDROBIN CONSTRUCTION INC04/12/2001
BISOTISSUEDPEACHY CONSTRUCTION11/03/1995
BISPLISSUEDDANICA PLG & HTG CORP11/03/1995
3 projects · most recent 06/25/2025
General Wiring
FiledStatusContractorScope
06/25/2025CompleteSOLAS ELECTRICAL CORP—
10/25/2022CompleteCONTACT PLUS ELEC'L CORPGeneral Wiring
01/09/2020CompleteILLUMINOUS ELECTRIC CORP.—
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
03/01/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/27/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/10/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/01/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/01/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/29/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
05/17/2023Fire-Resistant Penetrations and JointsKam Chiuspecial
05/17/2023Mechanical SystemsKam Chiuspecial
05/17/2023FinalALEXANDR NERATOFFprogress
05/16/2023FinalMOHAMMAD AHEADprogress
02/07/2023Sprinkler SystemsKam Chiuspecial
02/07/2023Fire-Resistant Penetrations and JointsKam Chiuspecial
01/04/2023Sprinkler SystemsKam Chiuspecial
01/04/2023Fire-Resistant Penetrations and JointsKam Chiuspecial
12/29/2022FinalALEXANDR NERATOFFprogress
12/21/2022FinalALEXANDR NERATOFFprogress
12/20/2022Fire-Resistant Penetrations and JointsKam Chiuspecial
12/20/2022Sprinkler SystemsKam Chiuspecial
12/09/2022FinalALEXANDR NERATOFFprogress
12/09/2022Mechanical SystemsKam Chiuspecial
11/30/2022Mechanical SystemsKam Chiuspecial
11/30/2022FinalALEXANDR NERATOFFprogress
09/27/2022FinalALEXANDR NERATOFFprogress
09/27/2022Mechanical SystemsKam Chiuspecial
09/27/2022Fire-Resistant Penetrations and JointsKam Chiuspecial
▾Documents — 101 on file (BIS + DOB NOW)
▸Plans & Drawings20
▸DOB NOWPlans/Sketch20
09/02/2026M00712234-I1Request digital key ↗
09/02/2026M00712234-P1Request digital key ↗
09/02/2026M00732150-I1Request digital key ↗
Showing 3 of 20 on file for this type
▸Applications & Permits12
▸DOB NOWLPC Approval/Permit12
09/02/2026M00712234-I1Open ↗
09/02/2026M00732150-P2Open ↗
09/01/2026M00740152-P1Open ↗
Showing 3 of 12 on file for this type
▸Seals & Professional Certifications39
▸DOB NOWDPL-1: Design Professional Seal & Signature20
09/02/2026M00712234-I1Open ↗
09/02/2026M00732150-I1Open ↗
09/02/2026M00732150-P3Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
09/01/2026M08018626-P3Open ↗
09/01/2026M08018626-P3Open ↗
09/01/2026M00740152-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/28/2026M00872126-I1Open ↗
09/01/2026M00712234-P1Open ↗
09/01/2026M00740152-P1Open ↗
Showing 3 of 7 on file for this type
▸Environmental & Asbestos19
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
09/02/2026M00712234-I1Open ↗
09/02/2026M00732150-I1Open ↗
09/02/2026M00732150-P3Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWOER: Notice to Proceed5
08/13/2026M00732150-I1Open ↗
08/13/2026M00712234-I1Open ↗
08/13/2026M00872126-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWOER: Notice of Satisfaction1
08/13/2026M00740152-I1Open ↗
▸Other Documents11
▸DOB NOWProof of Historic Building11
09/02/2026M00712234-I1Open ↗
09/02/2026M00732150-P2Open ↗
09/01/2026M00740152-P1Open ↗
Showing 3 of 11 on file for this type