RoofUnder Construction19p · 10 filings · 20 docs
ArchitectureCivilMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
inspection using industrial rope access techniques and methods. See attached plans designated primary site supervisor: Brian Barco
On file for this project
2 documents · 1 drawing sheet
Filing structural application for roof dunnage in association with DOB NOW # M01225139 and DOB NOW # M01215618
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Bulkhead1p · 1 filing · 3 docs
Architecture
Repair of exterior walls involving sealant, localized brick removal/replacement, pointing, precast stone repair including silane coating, repair of corroded steel supports as per plans (Local Law 11 - Facade Repair.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Floor 9Under Construction2p · 1 filing · 6 docs
Architecture
Issued Permit Scope
General Construction
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Floor 8Under Construction10p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modifications to existing HVAC System: Remove ductwork, diffusers, AC units and associated equipment on the 1, 2, 5, 8, Roof as per plans (Demo & Whitebox.) No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
MINOR MECHANICAL WORK AS PER PLANS
On file for this project
24 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 7Under Construction53p · 9 filings · 20 docs
ArchitectureCivilDMElectricalFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
Minor interior demolition; Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 7th floor as per plans (Hines - Demo, Whitebox & Stair Infill) No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Modifications to existing HVAC System: Remove ductwork, diffusers, AC units and associated equipment on the 7th Floor and Reinstall ductwork on the 6th Floor in relation to slab infill as per plans (Demo & Whitebox.) No change in use, egress or occupancy.
On file for this project
5 documents
Modifications to the existing Sprinkler System: Remove (3) heads and install (3) new heads on the 6th Floor; Remove (4) heads, relocate (12) heads and Install (4) new sprinkler heads on the 7th Floor and associated piping as per plans (Demo & Whitebox.)
On file for this project
5 documents
Latest 3 of 8 filings on this floor.
Floor 6Under Construction8p · 3 filings · 16 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modifications to existing HVAC System: Remove ductwork, diffusers, AC units and associated equipment on the 7th Floor and Reinstall ductwork on the 6th Floor in relation to slab infill as per plans (Demo & Whitebox.) No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Modifications to the existing Sprinkler System: Remove (3) heads and install (3) new heads on the 6th Floor; Remove (4) heads, relocate (12) heads and Install (4) new sprinkler heads on the 7th Floor and associated piping as per plans (Demo & Whitebox.)
On file for this project
5 documents
Floor 5Under Construction11p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Minor interior demolition, removal of interior non-load bearing partitions and finishes on the 1, 2, 5th and Roof as per plans (Hines Demo & Whitebox.) No change to use, egress or occupancy.
On file for this project
3 documents
Modifications to existing HVAC System: Remove ductwork, diffusers, AC units and associated equipment on the 1, 2, 5, 8, Roof as per plans (Demo & Whitebox.) No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 4Under Construction29p · 8 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modification to existing HVAC system and installation of commercial kitchen, and hood and duct ventilation system as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
17 documents · 1 drawing sheet
Modification to existing Sprinkler system and plumbing fixtures as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
8 documents · 4 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 3Under Construction15p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Install new Fixtures: (3) HWH, (3) Ejector Pumps, (3) sinks, (4) Dishwashers, (2) Water dispensers, (2) Icemakers, (2) Coffeemakers and associated CW/sanitary piping on the 7th Floor as per plans (K. Hovnanian Companies.)
On file for this project
14 documents · 1 drawing sheet
Modifications to the existing HVAC System: Installation of new ductwork, controls and VAVs on the 3rd Floor as per plans (Clarkson Sales Office.) No change to use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 2Under Construction13p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Minor interior demolition, removal of interior non-load bearing partitions and finishes on the 1, 2, 5th and Roof as per plans (Hines Demo & Whitebox.) No change to use, egress or occupancy.
On file for this project
3 documents
Modifications to existing HVAC System: Remove ductwork, diffusers, AC units and associated equipment on the 1, 2, 5, 8, Roof as per plans (Demo & Whitebox.) No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 1Under Construction75p · 19 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Filing for interior renovations in restaurant space on first floor and mezzanines. Work includes installation of interior non-load bearing partitions. No change to use, egress or occupancy. Please see comments for additional information.
On file for this project
11 documents · 2 drawing sheets
Structural modifications taking place on the 1st floor (storefront work) as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
20 documents · 1 drawing sheet
Filing plumbing application for installation of plumbing fixtures and cooking equipment in restaurant space, filed in conjunction with related DOB NOW application # M01213438-I1 (general construction).
On file for this project
9 documents
Latest 3 of 8 filings on this floor.
MezzanineUnder Construction27p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Filing for interior renovations in restaurant space on first floor and mezzanines. Work includes installation of interior non-load bearing partitions. No change to use, egress or occupancy. Please see comments for additional information.
On file for this project
11 documents
Filing for modification to existing sprinkler system for restaurant space on the first floor, in association with general construction application # M01213438-I1.
On file for this project
4 documents
Filing plumbing application for installation of plumbing fixtures and cooking equipment in restaurant space, filed in conjunction with related DOB NOW application # M01213438-I1 (general construction).
On file for this project
9 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
CellarUnder Construction59p · 10 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modifications to the existing Sprinkler System: Relocate Fire Department Connection, add Ball drip Check valve with ABD on the 1st Floor and associated FD Connection piping on the Cellar as per plans (FDC Relocation.) No change to use, egress or occupancy
On file for this project
5 documents · 1 drawing sheet
Filing plumbing application for installation of plumbing fixtures and cooking equipment in restaurant space, filed in conjunction with related DOB NOW application # M01213438-I1 (general construction).
On file for this project
9 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Basement2p · 2 filings · 11 docs
Fire ProtectionPlumbing
No filed description on record for this project.
On file for this project
5 documents · 1 drawing sheet
No filed description on record for this project.
On file for this project
6 documents · 1 drawing sheet