| Owner | Filings | Most Recent |
|---|---|---|
| Solstice Residential Group | 20 | 07/08/2026 |
| Ansonia Clockworks Condominium | 11 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Gary Bennett | 2 | 04/07/2026 |
| CCA | 1 | 12/11/2025 |
| The Vilnits Group | 3 | 03/06/2025 |
| Sarah Jacoby Architect | 3 | 01/09/2025 |
| Urban Associates | 1 | 07/09/2024 |
| Fsi Architecture | 1 | 07/28/2023 |
| Michael T Cetera | 2 | 06/20/2022 |
| Jill Porter Architect | 4 | 03/23/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Aegis Building Consultants | 4 | 03/21/2026 |
| Jenny Flores Expediting | 4 | 03/21/2026 |
| Cypher Design | 1 | 03/21/2026 |
| East Coast Expediting | 1 | 03/21/2026 |
| Joseph Fellner | 3 | 03/21/2026 |
| The Vilnits Group | 2 | 03/21/2026 |
| Metropolis Group | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Dancoby | General Contractor | 11 | 07/08/2026 |
| 458 Construction Co | General Contractor | 4 | 07/08/2026 |
| Pro N.Y. Solutions | General Contractor | 3 | 03/21/2026 |
| Design Tech Construction | General Contractor | 2 | 03/21/2026 |
| Code Mechanical | Plumbing | 2 | 07/08/2026 |
| Elray Construction | General Contractor | 2 | 07/08/2026 |
| Rite Way Heating | Plumbing | 1 | 07/08/2026 |
| Amps & Volts Electrical Conts | Electrical | 1 | 03/22/2026 |
| Starlite Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Trincity Electric | Electrical | 1 | 03/22/2026 |
| Downtown Complete Construction | General Contractor | 1 | 03/26/2026 |
| Galicia Contracting of NJ | General Contractor | 1 | 04/09/2026 |
| Apollo Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Aspect Plumbing & Heating Co | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Gary Bennett Architecture | 6976 | 2 | 04/07/2026 |
| Niza Works of Architects | 6101 | 2 | 04/07/2026 |
| Prudigm Engineering Llcu | 4304 | 1 | 12/11/2025 |
| The Vilnits Group | 1223 | 4 | 03/06/2025 |
| Urban Engineering | 2575 | 1 | 07/09/2024 |
| Sarah Jacoby Architect | 5641 | 1 | 06/03/2024 |
| Fsi Architecture | 354 | 1 | 07/28/2023 |
| O'Rourke Engineering | 5873 | 1 | 05/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | Elray Construction | 05/26/2026 |
| DOB NOW | Plumbing | Permit Issued | Apollo Plumbing & Heating | 05/18/2026 |
| DOB NOW | General Construction | Permit Issued | Elray Construction | 04/17/2026 |
| DOB NOW | General Construction | Signed-off | Galicia Contracting of NJ | 02/20/2026 |
| DOB NOW | General Construction | Signed-off | Dancoby | 11/13/2024 |
| DOB NOW | General Construction | Signed-off | Dancoby | 10/09/2024 |
| DOB NOW | Plumbing | Signed-off | LS Plumbing | 10/09/2024 |
| DOB NOW | Structural | Signed-off | Dancoby | 10/09/2024 |
| DOB NOW | General Construction | Signed-off | Dancoby | 07/30/2024 |
| DOB NOW | Plumbing | Signed-off | Aspect Plumbing & Heating Co | 07/17/2024 |
| DOB NOW | Plumbing | Signed-off | Starlite Plumbing & Heating | 07/09/2024 |
| DOB NOW | General Construction | Signed-off | Dancoby | 07/02/2024 |
| DOB NOW | General Construction | Signed-off | Design Tech Construction | 06/25/2024 |
| DOB NOW | General Construction | Signed-off | Pro N.Y. Solutions | 11/21/2023 |
| DOB NOW | General Construction | Signed-off | 458 Construction Co | 12/12/2022 |
| DOB NOW | General Construction | Signed-off | 458 Construction Co | 11/09/2022 |
| DOB NOW | General Construction | Signed-off | 458 Construction Co | 06/29/2022 |
| DOB NOW | Plumbing | Signed-off | Code Mechanical | 01/06/2022 |
| DOB NOW | Plumbing | Signed-off | Code Mechanical | 07/27/2021 |
| DOB NOW | General Construction | Signed-off | Andamio Scaffolding | 07/19/2021 |
| BIS | PL | ISSUED | Tri State Plumbing & Heating | 01/17/2023 |
| BIS | OT | ISSUED | Exclusive Restoration | 03/17/2022 |
| BIS | OT | ISSUED | Exclusive Restoration | 03/11/2021 |
| BIS | PL | ISSUED | Tri State Plumbing & Heating | 02/03/2021 |
| BIS | OT | ISSUED | Exclusive Restoration | 11/17/2020 |
| BIS | OT | ISSUED | Exclusive Restoration | 10/05/2020 |
| BIS | PL | ISSUED | Colbren Plumbing & Heating | 07/10/2019 |
| BIS | OT | ISSUED | A & J Contractors Co | 06/17/2019 |
| BIS | PL | ISSUED | Marathon Mechanical | 05/15/2019 |
| BIS | OT | ISSUED | Liquid 12 Interiors | 05/08/2019 |
| BIS | PL | ISSUED | C.W.C. Fire Suppression | 08/03/2016 |
| BIS | MH | ISSUED | Bednarz Construction | 07/29/2016 |
| BIS | PL | ISSUED | C.W.C. Fire Suppression | 07/17/2015 |
| BIS | OT | ISSUED | Bednarz Construction | 07/08/2015 |
| BIS | OT | ISSUED | Brend Renovation | 05/07/2015 |
| BIS | PL | ISSUED | C.W.C. Fire Suppression | 02/27/2015 |
| BIS | OT | ISSUED | Bednarz Construction | 02/10/2015 |
| BIS | PL | ISSUED | Authentic Plumbing | 11/14/2014 |
| BIS | EQ | ISSUED | Brend Renovation | 10/21/2014 |
| BIS | PL | ISSUED | Authentic Plumbing | 09/12/2013 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2026 | Complete | Amps & Volts Electrical Contractors | General Wiring |
| 04/21/2026 | Permit Issued | SNB Electrical Contng | General Wiring |
| 01/30/2026 | Permit Issued | Nyco Electric | General Wiring |
| 09/25/2025 | Complete | Cresco Electrical | General Wiring |
| 07/23/2024 | Permit Issued | Trincity Electric | General Wiring |
| 07/17/2024 | Complete | Sunbird Electrical Contracting | General Wiring |
| 01/28/2021 | Complete | A.davino Electrical Cont'g Co | General Wiring |
| 04/24/2019 | Complete | Bass Electrical | General Wiring |
| 03/30/2018 | Complete | Blaze Electric | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/08/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 06/05/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 06/03/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 02/19/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/14/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/04/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/30/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/11/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/29/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/05/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/24/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/11/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 12/30/2021 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/24/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/02/2026 | Tenant Protection Plan Compliance | Nicolas Zapata | special |
| 01/28/2026 | Fire-Resistant Penetrations and Joints | Gary Bennett | special |
| 01/28/2026 | Lighting in dwelling units | Gary Bennett | energy_progress |
| 01/28/2026 | Interior lighting power | Gary Bennett | energy_progress |
| 01/28/2026 | Final | Gary Bennett | progress |
| 01/28/2026 | Lighting controls | Gary Bennett | energy_progress |
| 01/28/2026 | Fire-Resistance Rated Construction | Gary Bennett | progress |
| 12/04/2025 | Insulation placement and R values | Taylor James Pierce | energy_progress |
| 12/04/2025 | Tenant Protection Plan Compliance | Naeem Anwar | special |
| 12/02/2025 | Final | Taylor James Pierce | progress |
| 03/13/2025 | Fire-Resistant Penetrations and Joints | ILYA VILNITS | special |
| 07/07/2024 | Structural Stability – Alterations of existing buildings | Nizar Khoury | special |
| 07/07/2024 | Final | Nizar Khoury | progress |
| 07/07/2024 | Structural Cold-Formed Steel | Nizar Khoury | special |
| 07/07/2024 | Tenant Protection Plan Compliance | ILYA VILNITS | special |
| 06/03/2024 | Fire-Resistant Penetrations and Joints | Sarah Jacoby | special |
| 06/03/2024 | Energy Code Compliance Inspections | Sarah Jacoby | progress |
| 06/03/2024 | Lighting in dwelling units | Sarah Jacoby | energy_progress |
| 03/06/2024 | Final | Sarah Jacoby | progress |
| 07/19/2023 | Tenant Protection Plan Compliance | James Cicalo | special |
| 05/24/2023 | Masonry | James Cicalo | special |
| 05/24/2023 | Structural Stability – Alterations of existing buildings | James Cicalo | special |
| 05/24/2023 | Final | James Cicalo | progress |
| 06/23/2022 | Final | MICHAEL CETERA | progress |
| 06/18/2022 | Final | MICHAEL CETERA | progress |