← Back
One family attached or semi-detached
441 76 STREET
BROOKLYN · BIN 3148803
💬 Discuss this project
1925Year Built
2Stories
A5Building Class
R5BZoning
1,708 sfGross Floor Area
1Units
One family attached or semi-detached · 2,000 sf lot · 0.85 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralOther
Roof3p · 1 filing · 7 docs
Floor 23p · 1 filing · 20 docs
Floor 1
Cellar1p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/11/2021$1.1M—Private party → Private party$644/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC102/19/2026
ANTHONY BONSIGNORE, RA303/02/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BROOKLYN SOLARWORKS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CUBE BUILDERS GROUP NYGeneral Contractor603/21/2026
DECO BUILDING GROUP CORPGeneral Contractor407/08/2026
NEW YORK STANDARD MECH CORPPlumbing307/08/2026
BROOKLYN SOLARWORKS LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244102/19/2026
JAJ ENGINEERING PLLC930403/02/2023
Building Lifecycle
All (51)Filed (4)Permit Issued (8)Signed Off (3)Inspection (6)Special Inspection (30)
06/08/2026
Signed off — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01357993-I1
02/20/2026
Permit issued — Solar
B01357993-I1-SL
02/19/2026
Filed — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01357993-I1
02/19/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
02/19/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
02/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
02/10/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
02/10/2026
Special inspection requirement — Final
NARESH MAHANGU
03/27/2023
Signed off — Alteration
INSTALL NEW, AND RELOCATE PLUMBING AND GAS FIXTURES ON THE CELLAR, 1ST, 2ND & OSP AS PER PLANS FILED
B00474557-I1
03/02/2023
Filed — Alteration
INSTALL NEW, AND RELOCATE PLUMBING AND GAS FIXTURES ON THE CELLAR, 1ST, 2ND & OSP AS PER PLANS FILED
B00474557-P3
01/31/2023
Signed off — Alteration
INTERIOR RENOVATION WORK ON THE CELLAR,1ST & 2ND FLOORS, REMOVE ONE STORY FRAME AND DECK AT REAR, NEW ONE STORY AND CELLAR ADDITION WITH OPEN DECK AT REAR ALL AS PER PLANS FILED
B00474945-I1
01/31/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joseph Jabour
01/31/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Joseph Jabour
01/31/2023
Special inspection requirement — HVAC-R and service water heating equipment
Joseph Jabour
01/31/2023
Special inspection requirement — HVAC-R and service water heating system controls
Joseph Jabour
01/31/2023
Special inspection requirement — Maintenance information
Joseph Jabour
01/17/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/05/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/14/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/27/2022
Permit issued — Plumbing
B00474557-I1-PL
07/11/2022
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
07/07/2022
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
06/28/2022
Permit issued — Structural
B00474945-I1-GC-CX
04/03/2022
Special inspection requirement — Final
Joseph Jabour
04/03/2022
Special inspection requirement — Energy Code Compliance Inspections
Joseph Jabour
04/03/2022
Special inspection requirement — Footing and Foundation
Joseph Jabour
04/03/2022
Special inspection requirement — Lighting controls
Joseph Jabour
04/03/2022
Special inspection requirement — HVAC-R and service water heating equipment
Joseph Jabour
04/03/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
Joseph Jabour
04/03/2022
Special inspection requirement — Protection of exposed foundation insulation
Joseph Jabour
04/03/2022
Special inspection requirement — Maintenance information
Joseph Jabour
04/03/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Joseph Jabour
04/03/2022
Special inspection requirement — Fenestration air leakage
Joseph Jabour
04/03/2022
Special inspection requirement — Fenestration areas
Joseph Jabour
04/03/2022
Special inspection requirement — Interior lighting power
Joseph Jabour
04/03/2022
Special inspection requirement — Air barrier - visual inspection
Joseph Jabour
04/03/2022
Special inspection requirement — Insulation placement and R values
Joseph Jabour
04/03/2022
Special inspection requirement — HVAC-R and service water heating system controls
Joseph Jabour
04/03/2022
Special inspection requirement — Masonry
Joseph Jabour
04/03/2022
Special inspection requirement — Mechanical Systems
Joseph Jabour
04/03/2022
Special inspection requirement — Structural Cold-Formed Steel
Joseph Jabour
04/03/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
Joseph Jabour
04/03/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joseph Jabour
09/14/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/13/2021
Permit issued — Plumbing
B00474557-I1-PL
07/08/2021
Permit issued — Construction Fence
B00474540-I1-FN
06/17/2021
Permit issued — Structural
B00474945-I1-GC-CX
05/07/2021
Permit issued — Plumbing
B00474557-I1-PL
04/30/2021
Permit issued — Construction Fence
B00474540-I1-FN
03/12/2021
Filed — Alteration
INTERIOR RENOVATION WORK ON THE CELLAR,1ST & 2ND FLOORS, REMOVE ONE STORY FRAME AND DECK AT REAR, NEW ONE STORY AND CELLAR ADDITION WITH OPEN DECK AT REAR ALL AS PER PLANS FILED
B00474945-I1
03/11/2021
Filed — Alteration
INSTALL NEW, AND RELOCATE PLUMBING AND GAS FIXTURES ON THE CELLAR, 1ST, 2ND & OSP AS PER PLANS FILED
B00474557-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offBROOKLYN SOLARWORKS LLC02/20/2026
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP07/27/2022
DOB NOWStructuralSigned-offCUBE BUILDERS GROUP NY06/28/2022
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP07/13/2021
DOB NOWConstruction FenceSigned-offDECO BUILDING GROUP CORP07/08/2021
DOB NOWStructuralSigned-offCUBE BUILDERS GROUP NY06/17/2021
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP05/07/2021
DOB NOWConstruction FenceSigned-offDECO BUILDING GROUP CORP04/30/2021
2 projects · most recent 02/10/2026
General Wiring
FiledStatusContractorScope
02/10/2026CompleteBROOKYLN SOLARWORKS, LLC—
05/03/2021Permit IssuedKWONG MING ELECTRIC INCGeneral Wiring
1 project · most recent 02/19/2026
FiledStatusContractorScope
02/19/2026Signed-offBROOKLYN SOLARWORKS LLC42 panels, 18.48 kw, 805 roof_area_sqft
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
01/17/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/05/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/14/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/11/2022Pass-Final General Construction Non-Directive 14PassView ↗
07/07/2022Fail-Final General Construction Non-Directive 14FailView ↗
09/14/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
02/19/2026Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
02/19/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
02/10/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
02/10/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
02/10/2026FinalNARESH MAHANGUprogress
01/31/2023Fire-Resistant Penetrations and JointsJoseph Jabourspecial
01/31/2023HVAC-R and service water piping design and insulationJoseph Jabourenergy_progress
01/31/2023HVAC-R and service water heating equipmentJoseph Jabourenergy_progress
01/31/2023HVAC-R and service water heating system controlsJoseph Jabourenergy_progress
01/31/2023Maintenance informationJoseph Jabourenergy_progress
04/03/2022FinalJoseph Jabourprogress
04/03/2022Energy Code Compliance InspectionsJoseph Jabourprogress
04/03/2022Footing and FoundationJoseph Jabourprogress
04/03/2022Lighting controlsJoseph Jabourenergy_progress
04/03/2022HVAC-R and service water heating equipmentJoseph Jabourenergy_progress
04/03/2022Fenestration and door U-factor and product ratingsJoseph Jabourenergy_progress
04/03/2022Protection of exposed foundation insulationJoseph Jabourenergy_progress
04/03/2022Maintenance informationJoseph Jabourenergy_progress
04/03/2022HVAC-R and service water piping design and insulationJoseph Jabourenergy_progress
04/03/2022Fenestration air leakageJoseph Jabourenergy_progress
04/03/2022Fenestration areasJoseph Jabourenergy_progress
04/03/2022Interior lighting powerJoseph Jabourenergy_progress
04/03/2022Air barrier - visual inspectionJoseph Jabourenergy_progress
04/03/2022Insulation placement and R valuesJoseph Jabourenergy_progress
04/03/2022HVAC-R and service water heating system controlsJoseph Jabourenergy_progress
Latest 25 of 34.
▾Documents — 92 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch - Earthwork3
09/01/2026B00474945-I1Request digital key ↗
09/01/2026B00474945-P9Request digital key ↗
08/14/2026B00474945-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/01/2026B00474945-P9Request digital key ↗
09/01/2026B00474945-I1Request digital key ↗
08/14/2026B00474945-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural3
09/01/2026B00474945-I1Request digital key ↗
09/01/2026B00474945-P9Request digital key ↗
08/14/2026B00474945-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing3
09/01/2026B00474557-P3Request digital key ↗
09/01/2026B00474557-I1Request digital key ↗
08/14/2026B00474557-P1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction3
09/01/2026B00474945-P9Request digital key ↗
09/01/2026B00474945-I1Request digital key ↗
08/14/2026B00474945-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Foundation3
09/01/2026B00474945-I1Request digital key ↗
09/01/2026B00474945-P9Request digital key ↗
08/14/2026B00474945-P1Request digital key ↗
▸DOB NOWPlans/Sketch1
08/18/2026B01357993-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records12
▸DOB NOWRestrictive Declaration/Easement 16
08/13/2026B00474945-P9Open ↗
08/13/2026B00474557-I1Open ↗
08/13/2026B00474557-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZoning Exhibit form (1-5)3
08/13/2026B00474945-P1Open ↗
08/13/2026B00474945-P9Open ↗
08/13/2026B00474945-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026B00474945-I1Open ↗
08/13/2026B00474945-P1Open ↗
08/13/2026B00474945-P9Open ↗
▸Seals & Professional Certifications38
▸DOB NOWSpecial Inspector Seal & Signature18
09/29/2026B00474945-P9Open ↗
09/29/2026B00474945-P9Open ↗
09/29/2026B00474945-P9Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWProgress Inspector Seal & Signature13
09/29/2026B00474945-P9Open ↗
09/29/2026B00474945-P9Open ↗
09/29/2026B00474945-P9Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/18/2026B01357993-I1Open ↗
08/13/2026B00474557-P3Open ↗
08/13/2026B00474557-I1Open ↗
Showing 3 of 7 on file for this type
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/13/2026B00474945-P9Open ↗
08/13/2026B00474945-P1Open ↗
08/13/2026B00474945-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/18/2026B01357993-I1Open ↗
08/13/2026B00474557-P1Open ↗
08/13/2026B00474945-P1Open ↗
Showing 3 of 7 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026B00474945-I1Open ↗
08/13/2026B00474557-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/18/2026B01357993-I1Open ↗
▸Cost, Insurance & Ownership2
▸DOB NOWCertification by Insurance Broker or Agency1
08/13/2026B00474945-I1Open ↗
▸DOB NOWCertificate of Insurance1
08/13/2026B00474945-I1Open ↗
▸Other Documents8
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/13/2026B00474945-P9Open ↗
08/13/2026B00474945-P1Open ↗
08/13/2026B00474945-I1Open ↗
▸DOB NOWPlot Diagram3
08/13/2026B00474945-P1Open ↗
08/13/2026B00474945-P9Open ↗
08/13/2026B00474945-I1Open ↗
▸DOB NOWAdditional Insured Authorizations1
08/13/2026B00474945-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00474945-I1Open ↗