| Owner | Filings | Most Recent |
|---|---|---|
| BOP WEST 31ST STREET | 106 | 07/08/2026 |
| OWNERS REP | 3 | 07/08/2026 |
| BROOKFIELD POWERED BY CBRE | 12 | 07/08/2026 |
| PENDRY MANHATTAN WEST | 5 | 04/09/2026 |
| PAVARIA MC GOVERN LLC | 2 | 03/22/2026 |
| TISHMAN CONSTRUCTION | 4 | 03/22/2026 |
| PAVARINI MCGOVERN | 2 | 03/22/2026 |
| CM&B CONSTRUCTION | 1 | 03/22/2026 |
| BROOKFIELD PROPERTIES | 2 | 03/22/2026 |
| BOP W31 STREET LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KONOSKI ENGINEERING PLLC | 2 | 07/08/2026 |
| STANTEC CONSULTING | 4 | 08/05/2025 |
| IW ARCHITECTURE, PLLC | 1 | 11/05/2024 |
| MARTINKOVIC MILFORD ARCHITECTS | 1 | 09/24/2024 |
| MARVEL ARCHITECTS | 2 | 03/08/2024 |
| JAROS BAUM & BOLLES | 2 | 11/02/2023 |
| ADVANCED PROFESSIONAL ENGINEERING | 8 | 05/05/2023 |
| CROSS ARCHITECTURE | 8 | 09/13/2022 |
| PATUXENT ENGINEERING LLC | 1 | 03/25/2022 |
| ADS ENGINEERS | 4 | 02/24/2022 |
| SHAABAN ENGINEERING, LLC | 1 | 09/28/2021 |
| DAVID BUCOVY ARCHITECT | 4 | 09/09/2021 |
| AMA CONSULTING ENGINEERS, PC | 14 | 08/11/2021 |
| SAFWAY ATLANTIC LLC | 5 | 06/14/2021 |
| ROBERT GERMAIN JR. PE | 2 | 12/02/2020 |
| SKIDMORE OWINGS & MERRILL LLP | 2 | 09/02/2020 |
| SEVERUD ASSOCIATES CONSULTING ENGIN | 1 | — |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 57 | 03/21/2026 |
| DVA Advisors | 13 | 03/21/2026 |
| SMEP DESIGN & CONSULTATION LLC | 2 | 03/21/2026 |
| WILLIAM VITTACO ASSOCIATES | 5 | 03/21/2026 |
| KAZAM CONSULTANTS | 2 | 03/21/2026 |
| NEW YORK SIGN CONSULTANTS | 2 | 03/21/2026 |
| PATUXENT ENGINEERING | 2 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SAFWAY ATLANTIC, LLC | General Contractor | 20 | 07/08/2026 |
| JAMES M. BARB CONSTR. INC | General Contractor | 6 | 03/21/2026 |
| CONSTRUCTION MANAGEMENT & | General Contractor | 5 | 07/08/2026 |
| EPIC MECHANICAL CONTRACTO | General Contractor | 4 | 03/21/2026 |
| SHAWMUT WOODWORKING & SUPPLY | General Contractor | 2 | 07/08/2026 |
| BLUEWATER PLBG& HTG INC | Plumbing | 2 | 07/08/2026 |
| PARKVIEW P&H INC | Plumbing | 2 | 07/08/2026 |
| ADVANCED PLUMBING LLC | Fire Protection | 2 | 07/08/2026 |
| W.J. REGAN & COMPANY LLC | General Contractor | 2 | 07/08/2026 |
| NYC FIRE SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| RAEL AUTOMATIC SPR.CO INC | Fire Protection | 1 | 07/08/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 1 | 07/08/2026 |
| CAPITOL AWNING CO INC | General Contractor | 1 | 04/09/2026 |
| C C CONTROLLED COMBUSTION | General Contractor | 1 | 04/09/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 1 | 07/08/2026 |
| SAMIRO SERVICES INC | General Contractor | 1 | 07/22/2026 |
| ADVANCED PLBG LLC | Plumbing | 1 | 07/08/2026 |
| FULTON PLBG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| LAB PLBG & HTG CO INC | Plumbing | 1 | 07/08/2026 |
| RRP PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| DOME INDUSTRIES LLC | Electrical | 1 | 03/22/2026 |
| GOING SIGN SVCNG | Scaffold | 1 | 07/08/2026 |
| E-J ELEC. INSTALLATION CO | Electrical | 1 | 03/22/2026 |
| FRED GELLER ELEC'L INC. | Electrical | 1 | 03/22/2026 |
| PATRIOT ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KONOSKI ENGINEERING PLLC | 9111 | 2 | 07/08/2026 |
| CONSULTING AND TESTING SE | 6152 | 6 | 08/05/2025 |
| ENTHINK ENGINEERS LLC | 6247 | 1 | 09/25/2024 |
| SOCOTEC ENGINEERING | 4983 | 4 | 03/08/2024 |
| CATALPA SPECIAL INSPECTIO | 2004 | 2 | 10/17/2022 |
| MEP INSPECTIONS, INC | 1102 | 2 | 08/20/2021 |
| ATLANTIC ENGINEERINGLABOR | 1381 | 10 | 08/11/2021 |
| ROBERT F. GERMAIN JR. PE | 5100 | 2 | 12/02/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | SAMIRO SERVICES INC | 07/20/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | STRUCTURAL PRESERVATION S | 01/30/2026 |
| DOB NOW | Plumbing | Signed-off | RRP PLUMBING CORP | 11/13/2024 |
| DOB NOW | Sign | Signed-off | POLSINELLI, HENRY | 11/13/2024 |
| DOB NOW | Sprinklers | Signed-off | ABCO-PEERLESS SPRKLR CORP | 10/25/2024 |
| DOB NOW | Sprinklers | Signed-off | ASCO SPRINKLER CO.,INC | 10/11/2024 |
| DOB NOW | Plumbing | Signed-off | FULTON PLBG & HTG CORP | 10/04/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JAMES M. BARB CONSTR. INC | 10/02/2024 |
| DOB NOW | General Construction | Signed-off | JAMES M. BARB CONSTR. INC | 10/02/2024 |
| DOB NOW | Sprinklers | Signed-off | NYC FIRE SPRINKLER CORP | 01/24/2024 |
| DOB NOW | Mechanical Systems | Signed-off | CONSTRUCTION MANAGEMENT & | 06/14/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 05/24/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 03/28/2022 |
| DOB NOW | Plumbing | Signed-off | ADVANCED PLBG LLC | 03/14/2022 |
| DOB NOW | Standpipe | Signed-off | ADVANCED PLUMBING LLC | 02/04/2022 |
| DOB NOW | Standpipe | Signed-off | ADVANCED PLUMBING LLC | 02/04/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SHAWMUT WOODWORKING & SUPPLY | 01/21/2022 |
| DOB NOW | General Construction | Signed-off | SHAWMUT WOODWORKING & SUPPLY | 01/21/2022 |
| DOB NOW | Plumbing | Signed-off | BLUEWATER PLBG& HTG INC | 01/20/2022 |
| DOB NOW | General Construction | Signed-off | CAPITOL AWNING CO INC | 12/03/2021 |
| DOB NOW | Construction Fence | Signed-off | SAFWAY ATLANTIC, LLC | 09/23/2021 |
| DOB NOW | Mechanical Systems | Signed-off | EPIC MECHANICAL CONTRACTO | 08/03/2021 |
| DOB NOW | Mechanical Systems | Signed-off | CONSTRUCTION MANAGEMENT & | 07/22/2021 |
| DOB NOW | Plumbing | Signed-off | PARKVIEW P&H INC | 07/07/2021 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 06/23/2021 |
| DOB NOW | Sprinklers | Signed-off | RAEL AUTOMATIC SPR.CO INC | 05/12/2021 |
| DOB NOW | Sprinklers | Signed-off | SIRINA FIRE PROT CORP | 04/15/2021 |
| DOB NOW | Plumbing | Signed-off | LAB PLBG & HTG CO INC | 04/13/2021 |
| DOB NOW | Mechanical Systems | Signed-off | W.J. REGAN & COMPANY LLC | 03/15/2021 |
| DOB NOW | General Construction | Signed-off | W.J. REGAN & COMPANY LLC | 03/15/2021 |
| DOB NOW | Mechanical Systems | Signed-off | CONSTRUCTION MANAGEMENT & | 03/05/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFWAY ATLANTIC, LLC | 12/18/2020 |
| DOB NOW | Construction Fence | Signed-off | SAFWAY ATLANTIC, LLC | 12/18/2020 |
| DOB NOW | Boiler Equipment | Signed-off | C C CONTROLLED COMBUSTION | 12/15/2020 |
| DOB NOW | Mechanical Systems | Signed-off | C C CONTROLLED COMBUSTION | 12/08/2020 |
| DOB NOW | Boiler Equipment | Signed-off | C C CONTROLLED COMBUSTION | 12/02/2020 |
| DOB NOW | Sprinklers | Signed-off | ARIANA CONTRACTING INC | 11/18/2020 |
| DOB NOW | Plumbing | Signed-off | BLUEWATER PLBG& HTG INC | 10/21/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFWAY ATLANTIC, LLC | 09/22/2020 |
| DOB NOW | Construction Fence | Signed-off | SAFWAY ATLANTIC, LLC | 09/21/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/24/2026 | Permit Issued | 4 GEN ELECTRICAL CONT | General Wiring |
| 03/18/2025 | Complete | FRED GELLER ELEC'L INC. | General Wiring |
| 10/02/2024 | Complete | EFCO ELECTRICAL SERVI INC | General Wiring |
| 11/22/2022 | Complete | PATRIOT ELECTRIC CORP | General Wiring |
| 09/29/2022 | Complete | KNIGHT ELEC'L SERV. CORP. | General Wiring |
| 02/14/2022 | Permit Issued | C.FALCO ELETL CONT CORP | General Wiring |
| 01/27/2022 | Complete | SPIELER & RICCA ELEC'L CO | General Wiring |
| 11/24/2021 | Complete | QUANTUM ELECTRIC CORP. | General Wiring |
| 09/28/2021 | Complete | DOME ELECT & COMM CONT IN | General Wiring |
| 07/23/2021 | Complete | SPIELER & RICCA ELEC'L CO | — |
| 07/23/2021 | Complete | SPIELER & RICCA ELEC'L CO | — |
| 06/14/2021 | Complete | PATRIOT ELECTRIC CORP | — |
| 05/04/2021 | Complete | PATRIOT ELECTRIC CORP | General Wiring |
| 04/05/2021 | Complete | JAM ELECTRICAL CORP | — |
| 02/24/2021 | Cancelled | PATRIOT ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2026 | Permit Issued | STRUCTURAL PRESERVATION S | Suspended Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2026 | Permit Issued | STRUCTURAL PRESERVATION S | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/14/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 12/31/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/05/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/18/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/14/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/07/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/06/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/28/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/15/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/15/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/30/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/30/2022 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 06/28/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/28/2022 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 06/27/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/16/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/01/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/28/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/22/2021 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/14/2021 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/10/2021 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/09/2026 | Fire-Resistant Penetrations and Joints | christopher konoski | special |
| 07/09/2026 | Ventilation and air distribution system | christopher konoski | energy_progress |
| 07/09/2026 | Maintenance information | christopher konoski | energy_progress |
| 07/09/2026 | Duct leakage testing, insulation and design | christopher konoski | energy_progress |
| 07/09/2026 | Final | christopher konoski | progress |
| 07/09/2026 | Fire-Resistance Rated Construction | christopher konoski | progress |
| 07/09/2026 | Energy Code Compliance Inspections | christopher konoski | progress |
| 07/09/2026 | Mechanical Systems | christopher konoski | special |
| 07/09/2026 | Tenant Protection Plan Compliance | christopher konoski | special |
| 07/07/2026 | Tenant Protection Plan Compliance | — | special |
| 06/21/2026 | Duct leakage testing, insulation and design | christopher konoski | energy_progress |
| 06/21/2026 | Energy Code Compliance Inspections | christopher konoski | progress |
| 06/21/2026 | Fire-Resistant Penetrations and Joints | christopher konoski | special |
| 06/21/2026 | Maintenance information | christopher konoski | energy_progress |
| 06/21/2026 | Ventilation and air distribution system | christopher konoski | energy_progress |
| 06/21/2026 | Mechanical Systems | christopher konoski | special |
| 06/21/2026 | Fire-Resistance Rated Construction | christopher konoski | progress |
| 06/21/2026 | Final | christopher konoski | progress |
| 08/06/2025 | Tenant Protection Plan Compliance | DANIEL CREIGHTON | special |
| 08/06/2025 | Sprinkler Systems | DANIEL CREIGHTON | special |
| 09/17/2024 | Fire-Resistant Penetrations and Joints | DANIEL CREIGHTON | special |
| 09/17/2024 | Post-installed Anchors | DANIEL CREIGHTON | special |
| 09/17/2024 | Exhaust and Vent Systems in Plenums and Ducts | Sunil Saigal | special |
| 09/17/2024 | Energy Code Compliance Inspections | DANIEL CREIGHTON | progress |
| 09/17/2024 | Fire-Resistance Rated Construction | DANIEL CREIGHTON | progress |