| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01467934 | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Permit Issued | 10/29/2026 | 11/02/2026 | Design GILSANZ MURRAY STEFICEK LLP Owner ROCKEFELLER GROUP, INC. | Structural Modifications: Installation of structural steel supports and framing related escalator removal between the SC1 (CO)/ C2 and Cella… |
| M01453416 ↗ | 205 FRONT STREET MANHATTAN | Alteration | Permit Issued | 09/24/2026 | 10/27/2026 | Design ALTA INDELMAN ARCHITECT Filer RIZZO GROUP | GENERAL CONSTRUCTION WORK TAKING PLACE ON FLOORS 001 AND 002 AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| M01453437 ↗ | 205 FRONT STREET MANHATTAN | Alteration | Permit Issued | 09/25/2026 | 10/27/2026 | Design ABS ENGINEERING, PLLC Filer RIZZO GROUP | MECHANICAL WORK TAKING PLACE ON FLOORS 001 AND 002 AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| M01467902 | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Permit Issued | 10/20/2026 | 10/23/2026 | Design TPG ARCHITECTURE, LLP Owner ROCKEFELLER GROUP, INC. | Minor interior demolition - removal of escalator between C2 & C1. Install interior partitions, finishes and patch ceilings for retail additi… |
| M01444040 | 45 ROCKEFELLER PLAZA MANHATTAN | Alteration | Permit Issued | 10/12/2026 | 10/20/2026 | Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | Structural work on 2nd floor as per plans. No change to use, egress or occupancy. |
| M01259447 | 7 EAST 7TH STREET MANHATTAN | Alteration | Permit Issued | 08/01/2025 | 09/10/2026 | Design DERIVE ENGINEERS | Structural work to support several mechanical units from the underside of the 3rd fl and roof, in conjunction with (-I1 ) application for re… |
| Name | Projects together | Most recent |
|---|---|---|
| AMA Consulting Engineers | 7 | 05/01/2026 |
| John F. Giuseffi, Architect | 7 | 07/10/2026 |
| Syska Hennessy Group | 6 | 05/29/2026 |
| Fogarty Finger Architecture | 5 | 12/30/2025 |
| Gensler | 4 | 05/07/2024 |
| Patti & Anthes Consulting Engineers | 4 | 05/26/2026 |
| EP Engineering | 3 | 06/03/2026 |
| Gilsanz Murray Steficek | 3 | 10/29/2026 |
| Robert Derector Associates | 3 | 02/27/2024 |
| Verderame-Cale Architecture | 3 | 07/12/2023 |
| Active Design Group Engineering | 2 | 10/12/2026 |
| Clifford Dias, PE | 2 | 01/12/2023 |
| GC Engineering & Associates | 2 | 04/12/2024 |
| Janko Rasic Architects | 2 | 01/12/2023 |
| Kahn Architecture & Design | 2 | 05/01/2026 |
| Montroy Demarco Architecture | 2 | 06/01/2023 |
| Omer Fenik, RA | 2 | 12/14/2021 |
| Ove Arup & Partners | 2 | 06/11/2024 |
| TPG Architecture | 2 | 10/20/2026 |
| ABS Engineering | 1 | 09/25/2026 |
| Alta Indelman Architect | 1 | 09/24/2026 |
| Architectura | 1 | 08/06/2021 |
| Aza Engineering | 1 | 05/16/2025 |
| B+W Architecture | 1 | 04/17/2025 |
| B2 Engineering | 1 | 07/02/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| A&A Plumbing | 6 | 09/19/2025 |
| Standard Fire Protection | 5 | 08/11/2025 |
| Artcon | 1 | 11/21/2023 |
| Hydronic Concepts NY P&H | 1 | 03/13/2024 |
| Hydronic Concepts NY Plumbing | 1 | 03/13/2024 |
| NY Building Associates | 1 | 11/21/2023 |
| Plaza Construction | 1 | 12/19/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| Tishman Speyer Properties | 17 | 10/12/2026 |
| Rockefeller Group | 10 | 10/29/2026 |
| BXP | 5 | 05/23/2024 |
| New York Institute of Technology | 4 | 06/11/2024 |
| Milltex Distributors | 3 | 01/03/2023 |
| Nyit | 3 | 10/07/2022 |
| BXP | 2 | 08/11/2025 |
| BXP | 2 | 08/07/2019 |
| CBRE | 2 | 07/02/2024 |
| Highline Developers | 2 | 01/03/2023 |
| Mfa 527 Madison | 2 | 07/10/2026 |
| NYC Economic Development | 2 | 09/25/2026 |
| The Cooper Union for the Advancemen | 2 | 08/05/2025 |
| Uncommon Schools | 2 | 06/03/2026 |
| 111 East 48th St Holdings | 1 | 11/21/2023 |
| BOP West 31st Street | 1 | 03/02/2021 |
| CUNY | 1 | 05/06/2026 |
| Interchurch Center | 1 | 03/13/2024 |
| Piedmont Office Management | 1 | 07/21/2026 |
| Rcpi Landmark Properties | 1 | 02/27/2024 |
| SL Green Realty | 1 | 05/04/2022 |
| Waldorf Realty | 1 | 12/22/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| Brookbridge Consulting Services | 12 | 10/29/2026 |
| Gillman Consulting | 12 | 08/11/2025 |
| Walter T. Gorman, PE | 11 | 10/12/2026 |
| Mbe Code & Zoning | 8 | 07/21/2026 |
| KM Associates of New York | 4 | 06/03/2026 |
| Municipal Building Consultants | 3 | 08/05/2025 |
| Barnwell Consultants | 2 | 07/10/2026 |
| Brookbridge Consultant Servies | 2 | 05/01/2026 |
| Oef Consultants | 2 | 12/14/2021 |
| PWF | 2 | 09/19/2025 |
| Rizzo Group | 2 | 09/25/2026 |
| CPS | 1 | 03/13/2024 |
| GC Engineering & Associates | 1 | 04/12/2024 |
| Jam Consultants | 1 | 05/04/2022 |
| JM Zoning | 1 | 05/16/2025 |
| Paul D. Hofherr | 1 | 01/03/2023 |
| William Vitacco Associates | 1 | 03/02/2021 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01467934 | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Permit Issued | 10/29/2026 | 11/02/2026 | Design GILSANZ MURRAY STEFICEK LLP Owner ROCKEFELLER GROUP, INC. | Structural Modifications: Installation of structural steel supports and framing related escalator removal between the SC1 (CO)/ C2 and Cella… |
| M01453416 ↗ | 205 FRONT STREET MANHATTAN | Alteration | Permit Issued | 09/24/2026 | 10/27/2026 | Design ALTA INDELMAN ARCHITECT Filer RIZZO GROUP | GENERAL CONSTRUCTION WORK TAKING PLACE ON FLOORS 001 AND 002 AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| M01453437 ↗ | 205 FRONT STREET MANHATTAN | Alteration | Permit Issued | 09/25/2026 | 10/27/2026 | Design ABS ENGINEERING, PLLC Filer RIZZO GROUP | MECHANICAL WORK TAKING PLACE ON FLOORS 001 AND 002 AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| M01467902 | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Permit Issued | 10/20/2026 | 10/23/2026 | Design TPG ARCHITECTURE, LLP Owner ROCKEFELLER GROUP, INC. | Minor interior demolition - removal of escalator between C2 & C1. Install interior partitions, finishes and patch ceilings for retail additi… |
| M01444040 | 45 ROCKEFELLER PLAZA MANHATTAN | Alteration | Permit Issued | 10/12/2026 | 10/20/2026 | Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | Structural work on 2nd floor as per plans. No change to use, egress or occupancy. |
| M01259447 | 7 EAST 7TH STREET MANHATTAN | Alteration | Permit Issued | 08/01/2025 | 09/10/2026 | Design DERIVE ENGINEERS | Structural work to support several mechanical units from the underside of the 3rd fl and roof, in conjunction with (-I1 ) application for re… |
| M01388016 | 55 LEXINGTON AVENUE MANHATTAN | Alteration | Permit Issued | 05/01/2026 | 08/31/2026 | Design IMEG Consulting Corp. Owner CUNY | Install one (1) new exhaust fan with associated ductwork and exhaust grille with fire damper for new fire alarm closet. Install one (1) new … |
| M01414283 ↗ | 527 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 07/10/2026 | 07/16/2026 | Owner MFA 527 MADISON LLC Filer BARNWELL CONSULTANTS | GENERAL CONSTRUCTION FOR INTERIOR PARTITIONS AND RELATED FINISHES FOR FLOOR, WALL & CEILING, AS PER PLANS FILED HEREWITH. NO CHANGE TO USE,… |
| M01414318 ↗ | 527 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 07/09/2026 | 07/16/2026 | Owner MFA 527 MADISON LLC Filer BARNWELL CONSULTANTS | MECHANICAL SYSTEMS MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, BULK, EGRESS, OR OCCUPANCY IS PROPOSED. |
| M01400910 ↗ | 1271 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 05/28/2026 | 06/05/2026 | Design TPG ARCHITECTURE, LLP Owner Rockefeller Group | Minor interior demolition. Removal and disposal of interior partitions, fixtures, suspended ceilings, floor and wall finishes, selective pip… |
| B01396196 | 507 MAC DONOUGH STREET BROOKLYN | Alteration | Signed-off | 06/01/2026 | 06/03/2026 | Design THE SWITZER GROUP Owner Uncommon Schools | Interior alterations to existing stair wall area at cellar and 1st floor, including stair wall upgrade and related general construction work… |
| B01398310 | 507 MAC DONOUGH STREET BROOKLYN | Alteration | Signed-off | 06/03/2026 | 06/03/2026 | Design EP ENGINEERING LLC Owner Uncommon Schools | Mechanical modifications to include HVAC replacement and replacement of associated ductwork. No change in use, occupancy, or egress. |
| M01388272 ↗ | 30 ROCKEFELLER PLAZA MANHATTAN | Alteration | Permit Issued | 05/26/2026 | 06/03/2026 | Filer WALTER T. GORMAN, PE, PC | Alterations to mechanical system on 43rd floor as per plans. No change to use. egress or occupancy. |
| M01400980 ↗ | 1271 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 05/29/2026 | 06/02/2026 | Design SYSKA HENNESSY GROUP Owner Rockefeller Group | Modifications to the existing HVAC System: Install (1) new FSD and tie into existing ductwork. Existing mechanical system throughout space t… |
| M01388260 ↗ | 30 ROCKEFELLER PLAZA MANHATTAN | Alteration | Permit Issued | 05/19/2026 | 05/22/2026 | Design BONSIGNORE ARCHITECTS Filer WALTER T. GORMAN, PE, PC | DEMOLITION IN 43RD FLOOR TO INCLUDE THE REMOVAL OF INTERIOR NON-LOAD BEARING PARTITIONS, DOORS, AND FINISHES AS PER PLANS FILED HEREWITH. NO… |
| M01380758 ↗ | 1500 BROADWAY MANHATTAN | Alteration | Permit Issued | 05/01/2026 | 05/20/2026 | Minor demolition with installation of new interior partitions, doors, suspended ceilings and finishes on the 20th floor (SNA Displays) as pe… | |
| M01380762 ↗ | 1500 BROADWAY MANHATTAN | Alteration | Permit Issued | 05/01/2026 | 05/06/2026 | Design AMA CONSULTING ENGINEERS, PC | Modification to the existing mechanical system on the 20th floor (SNA Displays) as per plans. No change to use, egress or occupancy |
| M01281593 ↗ | 891 AMSTERDAM AVENUE MANHATTAN | Alteration | Permit Issued | 01/23/2026 | 02/06/2026 | Design BAZINI ENGINEERING, P.C. | REPLACE ROOFTOP KITCHEN EXHAUST FAN AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01339495 ↗ | 60 BROAD STREET MANHATTAN | Alteration | Signed-off | 01/14/2026 | 01/26/2026 | Design MORRIS ADJMI ARCHITECTS Filer MBE CODE & ZONING LLC | INTERIOR OFFICE RENOVATION 38 STORY BUILDING B (OFFICE). REMOVING A CONVIENCE STAIR CONNECTING THE 2 FLOORS 31 & 32 FLRS. COVERING THE OPENI… |
| M01333177 ↗ | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 12/30/2025 | 01/06/2026 | Owner ROCKEFELLER GROUP, INC. | Minor interior demo. Removal of interior partitions, doors, suspended ceilings, flooring and finishes on the 15th Floor as per plans (Rock G… |
| B01256595 | 213 OSBORNE STREET BROOKLYN | Alteration | Signed-off | 07/21/2025 | 11/19/2025 | Design EP ENGINEERING LLC Filer PWF | RENOVATION OF BATHROOM INCLUDING NEW FIXTURES AND PIPING. NO CHANGE TO USE, OCCUPANCY OR EGRESS |
| B01255192 | 905 WINTHROP STREET BROOKLYN | Alteration | Signed-off | 07/15/2025 | 11/17/2025 | Design EP ENGINEERING LLC Filer PWF | RENOVATION OF BATHROOM INCLUDING NEW FIXTURES AND PIPING. NO CHANGE TO USE, OCCUPANCY OR EGRESS |
| M01292021 ↗ | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 10/09/2025 | 10/16/2025 | Design SYSKA HENNESSY GROUP Owner ROCKEFELLER GROUP, INC. | Modifications to the existing HVAC System: Demolition of existing ductwork back to riser on the 20-21st Floors as per plans (Rock Group - Of… |
| M01291964 ↗ | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 10/03/2025 | 10/10/2025 | Owner ROCKEFELLER GROUP, INC. | Minor interior demo. Removal of interior partitions, doors, suspended ceilings, flooring and finishes on the 20-22nd Floors as per plans (Ro… |
| M01292004 ↗ | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 10/03/2025 | 10/10/2025 | Design GILSANZ MURRAY STEFICEK LLP Owner ROCKEFELLER GROUP, INC. | Structural Modifications: floor infills on the 21st & 22nd floors as per plans (Rock Group - Office Demo.) No change to use, egress or occup… |
| M01256792 ↗ | 510 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 07/31/2025 | 08/27/2025 | Owner BOSTON PROPERTIES Filer GILLMAN CONSULTING INC | Remove and construct interior partitions, doors and ceiling as shown on drawings. No change in use, egress or occupancy. |
| M01216037 | 7 EAST 7TH STREET MANHATTAN | Alteration | Signed-off | 05/15/2025 | 06/06/2025 | Design AZA ENGINEERING LLC Filer JM ZONING, LLC. | Sprinkler scope related to proposed interior renovation of offices at the 2nd floor. No change to use, egress or occupancy. |
| M01196170 ↗ | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 05/14/2025 | 05/19/2025 | Minor interior demo. Removal of interior partitions, doors, suspended ceilings, flooring and finishes on the Sub-Cellar #1 (CO)/ C2 (Mktg), … | |
| M01196193 ↗ | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 05/13/2025 | 05/19/2025 | Design GILSANZ MURRAY STEFICEK LLP Owner ROCKEFELLER GROUP, INC. | Structural Modifications: Slab infill at existing stair openings to be demolished on the 3-5th Floors as per plans (Office Demo.) No change … |
| M01196236 ↗ | 1221 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 05/14/2025 | 05/16/2025 | Design SYSKA HENNESSY GROUP Owner ROCKEFELLER GROUP, INC. | Modifications to the existing HVAC System: Demolition of existing ductwork back to riser on the Sub-Cellar #1 (CO)/ C2 (Mktg), 3-5th and 23-… |
| M01150758 ↗ | 666 3RD AVENUE MANHATTAN | Alteration | Signed-off | 01/14/2025 | 04/21/2025 | Owner TISHMAN SPEYER Filer GILLMAN CONSULTING INC | Removal and installation of non-load bearing partitions, doors, frames, flooring, ceiling and related finishes. Refer to comments section fo… |
| M00917651 ↗ | 520 LEXINGTON AVENUE MANHATTAN | Alteration | Signed-off | 11/21/2023 | 03/24/2025 | Design CL ENGINEERING P.C. | TO PROPOSE INTERIOR RENOVATION WITH GENERAL CONSTRUCTION WORK ON FIRST FLOOR AS PER PLAN FILED HEREWITH, NO CHANGE OF USE, EGRESS OR OCCUPAN… |
| M00914375 ↗ | 60 BROAD STREET MANHATTAN | Alteration | Signed-off | 12/19/2023 | 01/23/2025 | Design TULLER/MCNEALUS/FELD | Interior renovations consisting of partitions and finishes as per plans filed herewith. No change to use, egress or occupancy. |
| M01141357 ↗ | 850 3RD AVENUE MANHATTAN | Alteration | Signed-off | 01/02/2025 | 01/06/2025 | Design MDEAS ARCHITECTS | GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 3RD FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01035786 | 666 3RD AVENUE MANHATTAN | Alteration | Signed-off | 05/06/2024 | 08/12/2024 | Design CFS ENGINEERING, DPC Owner TISHMAN SPEYER Filer GILLMAN CONSULTING INC | Structural modifications to include new structural steel for modernfold espero manual movable partition as per plans filed herewith. No chan… |
| M01046429 ↗ | 1271 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 07/01/2024 | 08/08/2024 | Installation of new guardrail at the inside perimeter or the main roof, inboard of the parapet. Removal of aluminum/steel decorative spires … | |
| M00781303 | 1855 BROADWAY MANHATTAN | Alteration | Signed-off | 03/28/2024 | 07/11/2024 | Design GENSLER | Propose to renovate the lobby on 1st level as shown on plans. |
| M01067893 ↗ | 575 5TH AVENUE MANHATTAN | Alteration | Signed-off | 07/02/2024 | 07/09/2024 | Design B2 ENGINEERING PC Owner CBRE, INC. | Modifications to the existing HVAC System: Install new ductwork and ceiling registers and associated controls and piping on the 22nd Floor (… |
| M01067862 ↗ | 575 5TH AVENUE MANHATTAN | Alteration | Signed-off | 07/02/2024 | 07/05/2024 | Owner CBRE, INC. | Minor Interior Demolition. Installation of new partitions, millwork, doors, suspended ceilings, flooring and finishes on the 22nd Flr (CO)/ … |
| M00779939 | 1849 BROADWAY MANHATTAN | Alteration | Signed-off | 09/15/2022 | 06/17/2024 | Design GENSLER Owner NYIT Filer MBE CODE & ZONING LLC | Propose to create wall entrance opening in lobby |
| M01063494 | 1855 BROADWAY MANHATTAN | Alteration | Signed-off | 06/11/2024 | 06/14/2024 | Design OVE ARUP & PARTNERS PC Filer MBE CODE & ZONING LLC | Install new structural framing wall between buildings as shown on drawings filed herewith. |
| M01038829 | 1849 BROADWAY MANHATTAN | Alteration | Signed-off | 04/24/2024 | 06/13/2024 | Design BUROHAPPOLD Filer MBE CODE & ZONING LLC | Removal of existing restroom exhaust fans, ductwork, and new air terminals of existing air terminals. |
| M00785607 | 1849 BROADWAY MANHATTAN | Alteration | Signed-off | 10/07/2022 | 05/30/2024 | Design OVE ARUP & PARTNERS PC Owner NYIT Filer MBE CODE & ZONING LLC | Modify structural beam framing |
| M00784741 | 1855 BROADWAY MANHATTAN | Alteration | Signed-off | 09/15/2022 | 05/29/2024 | Design GENSLER Owner NYIT Filer MBE CODE & ZONING LLC | Propose to construct wall opening between structures as shown on drawings filed herewith. |
| M01050107 ↗ | 510 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 05/23/2024 | 05/28/2024 | Owner BXP Filer GILLMAN CONSULTING INC | Modification of existing office space as shown on drawings filed. No change in use, egress or occupancy. |
| M00779979 | 1849 BROADWAY MANHATTAN | Alteration | Signed-off | 09/15/2022 | 05/24/2024 | Design GENSLER Filer MBE CODE & ZONING LLC | Propose to renovate cafeteria area as shown |
| M01018462 | 1855 BROADWAY MANHATTAN | Alteration | Signed-off | 03/20/2024 | 05/24/2024 | Design THE MCGUIRE GROUP ARCHITECTS | Renovation and construct interior partitions, ceilings, and doors on 10th floor lab |
| M01045749 ↗ | 40 10TH AVENUE MANHATTAN | Alteration | Signed-off | 05/06/2024 | 05/15/2024 | Modifications to the existing mechanical system. No change in use, egress or occupancy. | |
| M01026175 ↗ | 87 LEONARD STREET MANHATTAN | Alteration | Signed-off | 04/12/2024 | 04/16/2024 | Design GC ENG & ASSOCIATES, PC Filer GC ENG & ASSOCIATES | HEREWITH FILING FOR INTERIOR PARTITIONS MODIFICATION AS PER PLANS. NO CHANGE TOUSE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION. |
| M00999281 | 475 RIVERSIDE DRIVE MANHATTAN | Alteration | Signed-off | 03/07/2024 | 04/04/2024 | Design EMTG CONSULTANTS INC Owner INTERCHURCH CENTER CORP. Filer CPS | Herewith filing for modification of existing sprinkler system on the 18th floor and minor plumbing work as per the drawings. No change in us… |
| M01004742 ↗ | 1 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 02/27/2024 | 03/01/2024 | General construction buildout on 18th floor as per plans. No change to use, egress or occupancy. | |
| M01004744 ↗ | 1 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 02/27/2024 | 03/01/2024 | Design ROBERT DERECTOR ASSOCIATES Filer WALTER T. GORMAN, PE, PC | Mechanical work on 18th floor buildout as per plan. No change to use, egress or occupancy. |
| M00984390 ↗ | 1 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 01/11/2024 | 01/17/2024 | General construction buildout on 19th floor as per plans. No change to use, egress or occupancy. | |
| M00984400 ↗ | 1 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 01/11/2024 | 01/16/2024 | Design ROBERT DERECTOR ASSOCIATES | Mechanical work on 19th floor as per plan. No change to use, egress or occupancy. |
| M00971781 ↗ | 666 3RD AVENUE MANHATTAN | Alteration | Signed-off | 12/12/2023 | 12/18/2023 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Filer GILLMAN CONSULTING INC | Modification/additions to existing sprinkler/standpipe systems and related branch piping. No change in use, egress or occupancy under this a… |
| M00802800 ↗ | 450 WEST 14TH STREET MANHATTAN | Alteration | Signed-off | 01/03/2023 | 08/17/2023 | Design JACK GREEN ASSOCIATES Filer PAUL D. HOFHERR | Relocate and refabricate existing and additional ductwork. No change in use, occupancy or egress under this application. |
| M00883540 ↗ | 30 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 07/12/2023 | 07/19/2023 | Design VERDERAME-CALE ARCHITECTURE Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | Demolition work in mechanical rooms on 22nd floor as per plans. No change to use, egress or occupancy. |
| M08042758 ↗ | 610 5TH AVENUE MANHATTAN | Alteration | Signed-off | 03/21/2023 | 07/18/2023 | Alterations on 7th floor terrace as per plans. No change to use, egress or occupancy. | |
| M00883565 ↗ | 30 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 07/10/2023 | 07/14/2023 | Demolition work and the installation of chilled water DOAS units as per plans. No change to use, egress or occupancy. | |
| M00883560 ↗ | 30 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 06/30/2023 | 07/08/2023 | Design GACE DPC | Structural work as per plans. No change to use, egress or occupancy. |
| M00876004 ↗ | 156 WEST 56TH STREET MANHATTAN | Alteration | Signed-off | 06/01/2023 | 07/07/2023 | Owner TISHMAN SPEYER Filer GILLMAN CONSULTING INC | Hereby filing to demolish and construct interior partitions, ceilings and doors on 7th floor for Commercial office interior, and replacing l… |
| M00876042 ↗ | 156 WEST 56TH STREET MANHATTAN | Alteration | Signed-off | 06/08/2023 | 07/05/2023 | Owner TISHMAN SPEYER Filer GILLMAN CONSULTING INC | Hereby filing to modify the ductwork and piping for the 7th and 20th floor commercial suites as shown on plans filed herewith. No change to … |
| M00865015 | 1855 BROADWAY MANHATTAN | Alteration | Signed-off | 05/09/2023 | 06/22/2023 | Design H2M ARCHITECTS AND ENGINEERS Filer MBE CODE & ZONING LLC | Propose to renovate interior partitions, ceilings and doors on 9th floor lab as shown. |
| M08051907 ↗ | 1230 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 06/01/2023 | 06/09/2023 | Terrace alterations as per plans. No change to use, egress or occupancy. | |
| 120369635BIS | 2 SUTTON PLACE SOUTH MANHATTAN | — | ISSUED | 09/20/2010 | 05/09/2023 | — | OT, PL |
| M08036471 ↗ | 2 EAST 67TH STREET MANHATTAN | Alteration | Signed-off | 03/01/2023 | 05/01/2023 | Design NEW YORK ENGINEERS LLC | Demolition of existing Roof Top Unit and replaced with new |
| M00826435 ↗ | 1 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 02/21/2023 | 02/22/2023 | Design ROBERT DERECTOR ASSOCIATES Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | Mechanical work on suite 1280 as per plans. No change to use, egress or occupancy. |
| M00822845 ↗ | 1 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 02/08/2023 | 02/09/2023 | Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | Buildout in suite 1280 as per plans. No change to use, egress or occupancy. |
| M08015840 ↗ | 610 5TH AVENUE MANHATTAN | Alteration | Signed-off | 01/18/2023 | 01/25/2023 | Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | Demolition and construction work in Corridor/Lobby & Bathrooms on 3rd floor as per plans. No change to use, egress or occupancy. |
| M08033573 ↗ | 610 5TH AVENUE MANHATTAN | Alteration | Signed-off | 01/16/2023 | 01/20/2023 | Design VERDERAME-CALE ARCHITECTURE Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | General construction including installation of partitions, ceilings, flooring as per plans filed herewith in east end suites. No change to u… |
| M08055086 ↗ | 610 5TH AVENUE MANHATTAN | Alteration | Signed-off | 01/12/2023 | 01/19/2023 | Design CLIFFORD DIAS, PE, PC Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | Mechanical work on 3rd floor east end as per plans. No change to use, egress or occupancy. |
| M08008779 ↗ | 610 5TH AVENUE MANHATTAN | Alteration | Signed-off | 01/12/2023 | 01/18/2023 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Filer WALTER T. GORMAN, PE, PC | Alterations to ductwork as per plans. No change to use, egress or occupancy. |
| M07998811 ↗ | 850 7TH AVENUE MANHATTAN | Alteration | Signed-off | 10/07/2022 | 01/16/2023 | Design GC ENG & ASSOCIATES, PC | GENERAL CONSTRUCTION TO REMOVE INTERIOR PARTITION, DOORS AND CEILING AS SHONW ON DRAWINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| B08034603 ↗ | 1421 SHEEPSHEAD BAY ROAD BROOKLYN | Alteration | Signed-off | 12/22/2022 | 01/05/2023 | Design JRS ARCHITECT, PC Owner WALDORF REALTY CO INC | COMMERCIAL SPACE RENOVATION AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00786170 ↗ | 450 WEST 14TH STREET MANHATTAN | Alteration | Signed-off | 09/15/2022 | 12/20/2022 | General Construction to include new partitions, doors and painting. No change in use, occupancy or egress under this application. | |
| M00782436 ↗ | 510 MADISON AVENUE MANHATTAN | Alteration | Permit Issued | 07/29/2022 | 08/18/2022 | Design AMA CONSULTING ENGINEERS, PC Owner BXP Filer GILLMAN CONSULTING INC | Modification to HVAC system and related piping as shown on drawings filed herewith. No change in use, egress or occupancy. |
| M00782198 ↗ | 510 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 07/28/2022 | 08/01/2022 | Owner BXP Filer GILLMAN CONSULTING INC | Remove and construction interior partitions, doors and ceilings as shown on drawings filed herewith. No change in use, egress or occupancy. |
| M00679305 ↗ | 1 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 07/20/2022 | 07/25/2022 | Design VERDERAME-CALE ARCHITECTURE Owner TISHMAN SPEYER | FILING FOR RENOVATION OF SUITE 2801 & 2804 CORRIDORS & BATHROOMS ON THE 28TH FLOOR AS SHOWN ON DRAWINGS FILED HEREWITH.NO CHANGE IN USE, OC… |
| M00679314 ↗ | 1 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 07/20/2022 | 07/21/2022 | Design CLIFFORD DIAS, PE, PC Owner TISHMAN SPEYER | Filing for associated duct and piping as shown on drawings submitted herewith. No change in use, egress or occupancy. |
| M00690520 ↗ | 134 WEST 26TH STREET MANHATTAN | Alteration | Signed-off | 03/10/2022 | 06/13/2022 | INTERIOR ALTERATIONS TO NORTH (FRONT) SPACE. PARTITIONS. CEILINGS, LIGHTING AND FINISHES. NO CHANGE TO USE, EGRESS OR OCCUPANCY. | |
| 123865451BIS | 520 LEXINGTON AVENUE MANHATTAN | — | ISSUED | 01/28/2020 | 05/18/2022 | — | OT |
| M00730313 ↗ | 701 7TH AVENUE MANHATTAN | Alteration | Signed-off | 05/04/2022 | 05/10/2022 | Owner SL GREEN REALTY Filer JAM CONSULTANTS, INC. | minor architectural work to include the removal and installation of a counter top and related finishes . no change in use egress or occupanc… |
| 123700744BIS | 761 7TH AVENUE MANHATTAN | — | ISSUED | 03/25/2022 | 03/25/2022 | — | OT |
| M00674735 ↗ | 510 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 02/28/2022 | 03/14/2022 | Owner BXP Filer GILLMAN CONSULTING INC | Remove and construct interior partitions, doors and ceiling as shown on drawings filed herewith. No change in use, egress or occupancy. |
| M00674867 ↗ | 510 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 02/24/2022 | 03/11/2022 | Design SYSKA HENNESSY GROUP Owner BXP Filer GILLMAN CONSULTING INC | Modification to HVAC ductwork and related piping as shown on drawings filed herewith. No change in use, egress or occupancy. |
| M00592943 ↗ | 70 WEST 40TH STREET MANHATTAN | Alteration | Signed-off | 09/15/2021 | 01/07/2022 | Design OMER FENIK, RA Filer OEF CONSULTANTS, LLC | RENOVATION OF TOILETS; NEW ADA TOILET. ALL PL WORK IS TO BE FILED SEPARATELY. NO CHANGE IN EGRESS OCCUPANCY OR USE. |
| M00640578 ↗ | 70 WEST 40TH STREET MANHATTAN | Alteration | Signed-off | 12/14/2021 | 12/29/2021 | Design OMER FENIK, RA Filer OEF CONSULTANTS, LLC | RENOVATION TO 1ST FL. MEZZ TOILET RMs. REMOVE MINOR PARTITIONS, INSTALL NEW FINISHES, REPLACE DOORS, NEW HUNG CLNG, REPLACE FIXTURES (PLUMBI… |
| M00563551 ↗ | 510 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 08/06/2021 | 09/01/2021 | Design ARCHITECTURA Owner BOSTON PROPERTIES Filer GILLMAN CONSULTING INC | Minor tenant alteration of existing 10th Floor (south-east) office space. Removal of interior non-load bearing office partitions. New interi… |
| 140982024BIS | 1140 5TH AVENUE MANHATTAN | — | ISSUED | 08/04/2021 | 08/04/2021 | — | OT |
| M00523925 ↗ | 58 WEST 40TH STREET MANHATTAN | Alteration | Signed-off | 06/01/2021 | 07/06/2021 | Design JANKO RASIC ARCHITECTS, PLLC | HEREWITH FILING PAA TO UPDATE SIA AND PROGRESS INSPECTOR. THE PROJECT INVOLVES CLOSURE OF WALL OPENING AS PER PLANS FILED HEREWITH. NO CHAN… |
| M00236488 ↗ | 45 ROCKEFELLER PLAZA MANHATTAN | Alteration | Signed-off | 10/17/2019 | 07/02/2021 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER | MECHANICAL MODIFICATIONS |
| M00462311 ↗ | 70 WEST 40TH STREET MANHATTAN | Alteration | Signed-off | 02/10/2021 | 04/01/2021 | Design JANKO RASIC ARCHITECTS, PLLC | OFFICE RENOVATION AS PER PLANS FILED HEREWITH. |
| 140943004BIS | 45 ROCKEFELLER PLAZA MANHATTAN | — | ISSUED | 10/28/2020 | 03/26/2021 | — | OT |
| M00464945 ↗ | 442 WEST 33RD STREET MANHATTAN | Alteration | Signed-off | 03/01/2021 | 03/15/2021 | Design DAVID BUCOVY ARCHITECT | General construction in coffeeshop space. Filed in conjunction with NB # 121187713. |
| M00464954 ↗ | 442 WEST 33RD STREET MANHATTAN | Alteration | Signed-off | 03/02/2021 | 03/15/2021 | Design AMA CONSULTING ENGINEERS, PC Owner BOP WEST 31ST STREET LLC | Modification of existing ductwork and installation of new diffusers. |
| 123200455BIS | 424 WEST 33RD STREET MANHATTAN | — | ISSUED | 02/07/2018 | 02/10/2021 | — | MH, OT |
| 123881086BIS | 1270 AVENUE OF THE AMERICAS MANHATTAN | — | ISSUED | 10/23/2019 | 02/09/2021 | — | OT |
| 140967700BIS | 510 MADISON AVENUE MANHATTAN | — | ISSUED | 11/04/2020 | 11/04/2020 | — | OT |
| M00236393 ↗ | 1270 AVENUE OF THE AMERICAS MANHATTAN | Alteration | Signed-off | 10/23/2019 | 10/14/2020 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER | HEREWITH FILING FOR MECHANICAL MODIFICATIONS AS PER PLANS. |
| 140954304BIS | 435 WEST 31ST STREET MANHATTAN | — | ISSUED | 10/07/2020 | 10/07/2020 | — | OT |