| Owner | Filings | Most Recent |
|---|---|---|
| 444 OWNERS | 65 | 03/22/2026 |
| DOUGLAS ELLIMAN PROPERTY MANAGEMENT | 10 | 07/08/2026 |
| CEPRINE CONSTRUCTION | 7 | 07/08/2026 |
| BROWN HARRIS STEVENS | 4 | 03/21/2026 |
| C O 444 OWNERS | 2 | 03/21/2026 |
| 444 OWNER | 2 | 03/21/2026 |
| 333 EAST 52ND ST COR | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MICHAEL G. FAHEY ARCHITECT P.C. | 1 | 08/11/2026 |
| STARK CONSULTING, LLC | 1 | 08/11/2026 |
| TRUONG MONTGOMERY ARCHITECT | 4 | 08/03/2026 |
| KN3 ENGINEERING LLC | 2 | 10/10/2025 |
| SPAR UNLIMITED LLC | 1 | 09/16/2025 |
| TAN ENGINEERING PC | 5 | 10/30/2023 |
| LANA L LICCIARDI | 3 | 08/21/2023 |
| LUAY BAHOORA ARCHITECTS | 2 | 07/12/2023 |
| SUPERSTRUCTURES ENG. + ARCH. | 2 | 03/11/2022 |
| URBAN INTEGRATIONS | 1 | 08/12/2020 |
| KZ ENGINEERING, P.C | 1 | 05/10/2019 |
| JOEL PHAGOO P.E. PLLC | 1 | 11/09/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| DVA Advisors | 7 | 03/21/2026 |
| S M EXPEDITING | 6 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| SUPERSTRUCTURES ENG + ARCH | 2 | 03/21/2026 |
| UNITED SAFETY CONSULTANTS | 1 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 2 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CEPRINE CONSTRUCTION INC | General Contractor | 5 | 07/08/2026 |
| ASPEN INTERIOR LLC | General Contractor | 4 | 07/08/2026 |
| DYNAMIC INSTALLATION CORP. | General Contractor | 3 | 03/21/2026 |
| SERAFIM TSIOUGRIS | Electrical | 2 | 03/21/2026 |
| STANLEY RUTH CO LLC | General Contractor | 2 | 03/21/2026 |
| G.P. MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| TOUGH STALLION LLC | Electrical | 1 | 03/21/2026 |
| A F INTERIOR CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| C.S. SCOTT ENTERPRISES | General Contractor | 1 | 07/04/2026 |
| NPF CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| SKYLINE RESTORATION INC | General Contractor | 1 | 04/09/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 1 | 07/08/2026 |
| AUTHENTIC PLBG CORP | Plumbing | 1 | 07/08/2026 |
| ATTRACTIVE LIGHTING ELECL | Electrical | 1 | 03/22/2026 |
| VILLAGE P & H NY INC | Plumbing | 1 | 08/07/2026 |
| BIRNBAUM, ALAN | Electrical | 1 | 03/21/2026 |
| DARIO KNESICH | Electrical | 1 | 03/21/2026 |
| ERNEST JOCHEN | Electrical | 1 | 03/21/2026 |
| FRANK LA GREGA | Electrical | 1 | 03/21/2026 |
| SPICE ELECTRIC COMPANY | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PROJECT TACTICAL SOLUTION | 5859 | 4 | 08/03/2026 |
| MOHAMMAD AHEAD - PROFESSI | 9286 | 2 | 10/10/2025 |
| SPAR UNLIMITED LLC | 5967 | 1 | 09/16/2025 |
| SALAMON ENGINEERING PLLC | 1264 | 4 | 08/21/2023 |
| TAN ENGINEERING, P.C. | 1291 | 2 | 08/09/2023 |
| CROSSCHECK INSPECTION SER | 544 | 2 | 07/12/2023 |
| ALAN MARGOLIN & ASSOC | 423 | 2 | 03/11/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | VILLAGE P & H NY INC | 08/06/2026 |
| DOB NOW | General Construction | Permit Issued | C.S. SCOTT ENTERPRISES | 07/02/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 02/27/2026 |
| DOB NOW | General Construction | Signed-off | SKYLINE RESTORATION INC | 10/03/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 07/15/2025 |
| DOB NOW | Mechanical Systems | Signed-off | STANLEY RUTH CO LLC | 02/20/2024 |
| DOB NOW | Plumbing | Signed-off | AUTHENTIC PLBG CORP | 08/01/2023 |
| DOB NOW | General Construction | Signed-off | A F INTERIOR CONSTRUCTION | 08/01/2023 |
| DOB NOW | Plumbing | Signed-off | G.P. MECHANICAL CORP | 07/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ASPEN INTERIOR LLC | 07/01/2023 |
| DOB NOW | Plumbing | Signed-off | G.P. MECHANICAL CORP | 03/31/2023 |
| DOB NOW | General Construction | Signed-off | ASPEN INTERIOR LLC | 03/30/2023 |
| DOB NOW | Structural | Permit Issued | NPF CONSTRUCTION CORP | 03/15/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CEPRINE CONSTRUCTION INC | 11/16/2020 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 08/13/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | CEPRINE CONSTRUCTION INC | 05/05/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | CEPRINE CONSTRUCTION INC | 05/13/2019 |
| DOB NOW | Sidewalk Shed | Permit Issued | DYNAMIC INSTALLATION CORP | 11/10/2017 |
| BIS | PL | ISSUED | GANIC PLUMBING & HTG INC | 03/09/2026 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 03/01/2021 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 03/06/2020 |
| BIS | OT | ISSUED | AM&G WATERPROOFING LLC | 11/08/2017 |
| BIS | PL | ISSUED | R&A HEATING & CONTRG CO.I | 06/06/2017 |
| BIS | OT | ISSUED | REMONT INC | 05/30/2017 |
| BIS | OT | ISSUED | QUALITY BUILDING CONSTRUTION | 05/18/2015 |
| BIS | PL | ISSUED | J. CAIAZZO PLBG & HTG COR | 02/25/2015 |
| BIS | OT | ISSUED | CASTLE ENTERPRISE CONSTRU | 01/09/2015 |
| BIS | OT | ISSUED | QUALITY BUILDING CONSTRUTION | 05/20/2014 |
| BIS | PL | ISSUED | PREMIER FLOW PLBG AND HTG | 03/21/2014 |
| BIS | OT | ISSUED | HAMILTON AIR COMPANY, INC. | 03/10/2014 |
| BIS | OT | ISSUED | ARTAN IBRAHIMI | 02/26/2014 |
| BIS | OT | ISSUED | STRUCTURE NYC INC | 02/10/2014 |
| BIS | PL | ISSUED | DPH PLUMBING & HTG CORP | 01/22/2014 |
| BIS | OT | ISSUED | STRUCTURE NYC INC | 01/09/2014 |
| BIS | OT | ISSUED | QUALITY BUILDING CONSTRUTION | 06/12/2013 |
| BIS | EQ | ISSUED | STEEL SYSTEMS LLC | 05/09/2013 |
| BIS | EQ | ISSUED | STEEL SYSTEMS LLC | 05/07/2013 |
| BIS | EQ | ISSUED | STEEL SYSTEMS LLC | 04/01/2013 |
| BIS | OT | ISSUED | HITE CONSTRUCTION INC | 03/15/2013 |
| BIS | PL | ISSUED | SKINNER PLUMBING & HEATING | 10/08/2012 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/11/2026 | — | — | Heating and Air Conditioning Systems | Heat / Cool Daikin RXTQ48TBVJUB 48,300 BTU · Vrf Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2026 | Permit Issued | PARAMOUNT SERVICES, LLC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/11/2026 | Complete | JASON SALOME ELEC'L CONTG | — |
| 08/06/2026 | Complete | RIGHT VOLTAGE ELECTRIC CO | — |
| 08/06/2026 | Complete | RIGHT VOLTAGE ELECTRIC CO | — |
| 12/09/2023 | Complete | ATTRACTIVE LIGHTING ELECL | General Wiring |
| 08/01/2023 | Complete | ARMA ELECTRIC INC | General Wiring |
| 08/12/2022 | Complete | CENTENNIAL ELEVATOR INDUS | General Wiring |
| 09/16/2021 | Complete | SPICE ELECTRIC COMPANY | General Wiring |
| 01/15/2020 | Permit Issued | UPDATE SYSTEMS ELECTRICAL | General Wiring |
| 05/07/2019 | Complete | V. VASS ELECTRIC CORP | — |
| 05/06/2019 | Complete | TOWER ELECTRIC INC. | General Wiring |
| 10/09/2018 | Complete | GOTHAM WIRING LICENSED | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/09/2017 | Permit Issued | DYNAMIC INSTALLATION CORP | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2025 | Permit Issued | SKYLINE RESTORATION INC | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/18/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/03/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/13/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/11/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/26/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/10/2026 | Tenant Protection Plan Compliance | — | special |
| 08/10/2026 | Heating Systems | — | special |
| 08/10/2026 | Maintenance information | — | energy_progress |
| 08/10/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/10/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 08/10/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 08/10/2026 | Post-installed Anchors | — | special |
| 08/10/2026 | Energy Code Compliance Inspections | — | progress |
| 08/10/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 08/03/2026 | Fire-Resistant Penetrations and Joints | Max Lee | special |
| 07/27/2026 | Mechanical Systems | — | special |
| 07/27/2026 | Final | — | progress |
| 07/27/2026 | Tenant Protection Plan Compliance | — | special |
| 06/25/2026 | Lighting in dwelling units | — | energy_progress |
| 06/25/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/25/2026 | Final | — | progress |
| 06/25/2026 | Energy Code Compliance Inspections | — | progress |
| 06/25/2026 | Fire-Resistance Rated Construction | — | progress |
| 06/25/2026 | Lighting controls | — | energy_progress |
| 10/24/2025 | Post-installed Anchors | MOHAMMAD AHEAD | special |
| 10/24/2025 | Alternative Materials - OTCR Buildings Bulletin Number | MOHAMMAD AHEAD | special |
| 10/10/2025 | Alternative Materials - OTCR Buildings Bulletin Number | MOHAMMAD AHEAD | special |
| 10/10/2025 | Post-installed Anchors | MOHAMMAD AHEAD | special |
| 09/15/2025 | Tenant Protection Plan Compliance | SCOTT PROFETA | special |
| 09/15/2025 | Post-installed Anchors | SCOTT PROFETA | special |