← Back
Elevator cooperative
444 EAST 52 STREET
MANHATTAN · East Midtown-Turtle Bay · BIN 1040141
💬 Discuss this project
1929Year Built
11Stories
D4Building Class
R10Zoning
72,865 sfGross Floor Area
51Units
LL97 CoveredRent Stabilized17 Open Violations ▸FISP: SAFE
Elevator cooperative · Owner of record: 444 OWNERS CORP · 9,062 sf lot · 8.04 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Permit Issued — active, not yet Signed-off
Roof4p · 2 filings · 15 docs
Floor 8Under Construction13p · 4 filings · 20 docs
Floor 713p · 5 filings · 20 docs
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Cellar5p · 1 filing · 8 docs
Site & exterior8p · 3 filings · 9 docs
Filed — no permit issued18p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
444 OWNERS6503/22/2026
DOUGLAS ELLIMAN PROPERTY MANAGEMENT1007/08/2026
CEPRINE CONSTRUCTION707/08/2026
BROWN HARRIS STEVENS403/21/2026
C O 444 OWNERS203/21/2026
444 OWNER203/21/2026
333 EAST 52ND ST COR203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DVA Advisors703/21/2026
S M EXPEDITING603/21/2026
AE DESIGN SOLUTION403/21/2026
SUPERSTRUCTURES ENG + ARCH203/21/2026
UNITED SAFETY CONSULTANTS103/21/2026
A1 EXPEDITING SERVICE203/21/2026
SYNERGY BUILDING CONSULTANTS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CEPRINE CONSTRUCTION INCGeneral Contractor507/08/2026
ASPEN INTERIOR LLCGeneral Contractor407/08/2026
DYNAMIC INSTALLATION CORP.General Contractor303/21/2026
SERAFIM TSIOUGRISElectrical203/21/2026
STANLEY RUTH CO LLCGeneral Contractor203/21/2026
G.P. MECHANICAL CORPPlumbing207/08/2026
TOUGH STALLION LLCElectrical103/21/2026
A F INTERIOR CONSTRUCTIONGeneral Contractor107/08/2026
C.S. SCOTT ENTERPRISESGeneral Contractor107/04/2026
NPF CONSTRUCTION CORPGeneral Contractor107/08/2026
SKYLINE RESTORATION INCGeneral Contractor104/09/2026
SPRING SCAFFOLDING LLCGeneral Contractor107/08/2026
AUTHENTIC PLBG CORPPlumbing107/08/2026
ATTRACTIVE LIGHTING ELECLElectrical103/22/2026
VILLAGE P & H NY INCPlumbing108/07/2026
BIRNBAUM, ALANElectrical103/21/2026
DARIO KNESICHElectrical103/21/2026
ERNEST JOCHENElectrical103/21/2026
FRANK LA GREGAElectrical103/21/2026
SPICE ELECTRIC COMPANYElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PROJECT TACTICAL SOLUTION5859408/03/2026
MOHAMMAD AHEAD - PROFESSI9286210/10/2025
SPAR UNLIMITED LLC5967109/16/2025
SALAMON ENGINEERING PLLC1264408/21/2023
TAN ENGINEERING, P.C.1291208/09/2023
CROSSCHECK INSPECTION SER544207/12/2023
ALAN MARGOLIN & ASSOC423203/11/2022
Building Lifecycle
All (165)Filed (24)Permit Issued (18)Signed Off (8)Facade (FISP) (15)Violation (54)Inspection (6)Objection (10)Special Inspection (30)
08/12/2026
Objection resolved — Addressed
08/11/2026
Filed — Alteration
PROPOSED INTERIOR RENOVATION TO EXISTING MAISONETTE A INCLUDING NON-BEARING PARTITIONS. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
M01422665-S1
08/11/2026
Filed — Alteration
PROPOSED INTERIOR RENOVATION TO EXISTING MAISONETTE A INCLUDING NON-BEARING PARTITIONS. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
M01422665-I1
08/11/2026
Objection raised — Scope
08/10/2026
Special inspection requirement — Tenant Protection Plan Compliance
08/10/2026
Special inspection requirement — Heating Systems
08/10/2026
Special inspection requirement — Maintenance information
08/10/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
08/10/2026
Special inspection requirement — HVAC-R and service water heating system controls
08/10/2026
Special inspection requirement — HVAC-R and service water heating equipment
08/10/2026
Special inspection requirement — Post-installed Anchors
08/10/2026
Special inspection requirement — Energy Code Compliance Inspections
08/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/08/2026
Objection resolved — Addressed
08/08/2026
Objection resolved — Addressed
08/07/2026
Objection raised — Other
08/07/2026
Objection raised — Other
08/06/2026
Permit issued — Plumbing
M01378007-S1-PL
08/03/2026
Filed — Alteration
RECONFIGURATION AND RENOVATION OF 2 BATHROOMS. NO CHANGE TO OCCUPANCY USE OR EGRESS.
M01378007-P1
08/03/2026
Filed — Alteration
RECONFIGURATION AND RENOVATION OF 2 BATHROOMS. NO CHANGE TO OCCUPANCY USE OR EGRESS.
M01378007-P2
08/03/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Max Lee
07/27/2026
Special inspection requirement — Mechanical Systems
07/27/2026
Special inspection requirement — Final
07/27/2026
Special inspection requirement — Tenant Protection Plan Compliance
07/02/2026
Permit issued — General Construction
M01378007-I1-GC
06/25/2026
Special inspection requirement — Lighting in dwelling units
06/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/25/2026
Special inspection requirement — Final
06/25/2026
Special inspection requirement — Energy Code Compliance Inspections
06/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
06/25/2026
Special inspection requirement — Lighting controls
05/06/2026
Filed — Alteration
RECONFIGURATION AND RENOVATION OF 2 BATHROOMS. NO CHANGE TO OCCUPANCY USE OR EGRESS.
M01378007-I1
05/06/2026
Filed — Alteration
RECONFIGURATION AND RENOVATION OF 2 BATHROOMS. NO CHANGE TO OCCUPANCY USE OR EGRESS.
M01378007-S1
02/27/2026
Permit issued — Suspended Scaffold
M01246897-I1-SC
10/24/2025
Special inspection requirement — Post-installed Anchors
MOHAMMAD AHEAD
10/24/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
MOHAMMAD AHEAD
10/10/2025
Filed — Alteration
Installation of suspended scaffold for facade work or inspection
M01246897-P1
10/10/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
MOHAMMAD AHEAD
10/10/2025
Special inspection requirement — Post-installed Anchors
MOHAMMAD AHEAD
10/03/2025
Permit issued — General Construction
M01286514-I1-GC
09/16/2025
Filed — Alteration
Roof replacement and installation of new guard rails. No change in use egress or occupancy.
M01286514-I1
09/15/2025
Special inspection requirement — Tenant Protection Plan Compliance
SCOTT PROFETA
09/15/2025
Special inspection requirement — Post-installed Anchors
SCOTT PROFETA
09/15/2025
Special inspection requirement — Insulation placement and R values
SCOTT PROFETA
09/15/2025
Special inspection requirement — Air barrier - visual inspection
SCOTT PROFETA
09/12/2025
Special inspection requirement — Final
SCOTT PROFETA
07/15/2025
Permit issued — Suspended Scaffold
M01246897-I1-SC
07/01/2025
Filed — Alteration
Installation of suspended scaffold for facade work or inspection
M01246897-I1
06/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/08/2024
Signed off — Alteration
INTERIOR RENOVATION & MECHANICAL WORK IN APT #7BC AS SHOWN ON PLANS. THERE IS NO CHANGE IN USE, OCCUPANCY OR MEANS OF EGRESS.
M00865559-I1
05/02/2024
Signed off — Alteration
PLUMBING WORK IN APT # 7BC AS SHOWN ON PLANS. THERE IS NO CHANGE IN USE, OCCUPANCY OR MEANS OF EGRESS.
M00865562-I1
02/20/2024
Permit issued — Mechanical Systems
M00865559-I1-MS
01/29/2024
Cycle 9 facade report signed — SAFE
01/09/2024
Cycle 9 facade report submitted
01/04/2024
Cycle 9 facade inspection completed
12/18/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/15/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/15/2023
Signed off — Alteration
Additions/Modifications to existing plumbing system. No change to use, egress, or occupancy.
M08038969-I1
11/15/2023
Signed off — Alteration
Additions/Modifications to existing mechanical system. No change to use, egress, or occupancy.
M08038952-I1
11/14/2023
Signed off — Alteration
Non-Structural Demolition Removal and disposal of interior partitions, fixtures, and finishes. Installation of new partitions doors, floor and wall finishes
M08038928-I1
Latest 60 of 165 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedVILLAGE P & H NY INC08/06/2026
DOB NOWGeneral ConstructionPermit IssuedC.S. SCOTT ENTERPRISES07/02/2026
DOB NOWSuspended ScaffoldPermit IssuedSKYLINE RESTORATION INC02/27/2026
DOB NOWGeneral ConstructionSigned-offSKYLINE RESTORATION INC10/03/2025
DOB NOWSuspended ScaffoldPermit IssuedSKYLINE RESTORATION INC07/15/2025
DOB NOWMechanical SystemsSigned-offSTANLEY RUTH CO LLC02/20/2024
DOB NOWPlumbingSigned-offAUTHENTIC PLBG CORP08/01/2023
DOB NOWGeneral ConstructionSigned-offA F INTERIOR CONSTRUCTION08/01/2023
DOB NOWPlumbingSigned-offG.P. MECHANICAL CORP07/27/2023
DOB NOWMechanical SystemsSigned-offASPEN INTERIOR LLC07/01/2023
DOB NOWPlumbingSigned-offG.P. MECHANICAL CORP03/31/2023
DOB NOWGeneral ConstructionSigned-offASPEN INTERIOR LLC03/30/2023
DOB NOWStructuralPermit IssuedNPF CONSTRUCTION CORP03/15/2022
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC11/16/2020
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC08/13/2020
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC05/05/2020
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC05/13/2019
DOB NOWSidewalk ShedPermit IssuedDYNAMIC INSTALLATION CORP11/10/2017
BISPLISSUEDGANIC PLUMBING & HTG INC03/09/2026
BISOTISSUEDSKYLINE RESTORATION INC03/01/2021
BISOTISSUEDSKYLINE RESTORATION INC03/06/2020
BISOTISSUEDAM&G WATERPROOFING LLC11/08/2017
BISPLISSUEDR&A HEATING & CONTRG CO.I06/06/2017
BISOTISSUEDREMONT INC05/30/2017
BISOTISSUEDQUALITY BUILDING CONSTRUTION05/18/2015
BISPLISSUEDJ. CAIAZZO PLBG & HTG COR02/25/2015
BISOTISSUEDCASTLE ENTERPRISE CONSTRU01/09/2015
BISOTISSUEDQUALITY BUILDING CONSTRUTION05/20/2014
BISPLISSUEDPREMIER FLOW PLBG AND HTG03/21/2014
BISOTISSUEDHAMILTON AIR COMPANY, INC.03/10/2014
BISOTISSUEDARTAN IBRAHIMI02/26/2014
BISOTISSUEDSTRUCTURE NYC INC02/10/2014
BISPLISSUEDDPH PLUMBING & HTG CORP01/22/2014
BISOTISSUEDSTRUCTURE NYC INC01/09/2014
BISOTISSUEDQUALITY BUILDING CONSTRUTION06/12/2013
BISEQISSUEDSTEEL SYSTEMS LLC05/09/2013
BISEQISSUEDSTEEL SYSTEMS LLC05/07/2013
BISEQISSUEDSTEEL SYSTEMS LLC04/01/2013
BISOTISSUEDHITE CONSTRUCTION INC03/15/2013
BISPLISSUEDSKINNER PLUMBING & HEATING10/08/2012
+ 28 more permits on file
1 project · most recent 08/11/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/11/2026——Heating and Air Conditioning Systems
Heat / Cool
Daikin RXTQ48TBVJUB 48,300 BTU · Vrf Outdoor ×2
1 project · most recent 08/03/2026
Water/Sanitary
FiledStatusContractorScope
08/03/2026Permit IssuedPARAMOUNT SERVICES, LLCWater/Sanitary
11 projects · most recent 08/11/2026
General Wiring
FiledStatusContractorScope
08/11/2026CompleteJASON SALOME ELEC'L CONTG—
08/06/2026CompleteRIGHT VOLTAGE ELECTRIC CO—
08/06/2026CompleteRIGHT VOLTAGE ELECTRIC CO—
12/09/2023CompleteATTRACTIVE LIGHTING ELECLGeneral Wiring
08/01/2023CompleteARMA ELECTRIC INCGeneral Wiring
08/12/2022CompleteCENTENNIAL ELEVATOR INDUSGeneral Wiring
09/16/2021CompleteSPICE ELECTRIC COMPANYGeneral Wiring
01/15/2020Permit IssuedUPDATE SYSTEMS ELECTRICALGeneral Wiring
05/07/2019CompleteV. VASS ELECTRIC CORP—
05/06/2019CompleteTOWER ELECTRIC INC.General Wiring
10/09/2018CompleteGOTHAM WIRING LICENSEDGeneral Wiring
1 project · most recent 11/09/2017
Sidewalk Shed
FiledStatusContractorScope
11/09/2017Permit IssuedDYNAMIC INSTALLATION CORPSidewalk Shed
1 project · most recent 10/10/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
10/10/2025Permit IssuedSKYLINE RESTORATION INCSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
12/18/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/15/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/03/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/13/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/11/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/26/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 52
DateRequirementInspectorRole
08/10/2026Tenant Protection Plan Compliance—special
08/10/2026Heating Systems—special
08/10/2026Maintenance information—energy_progress
08/10/2026HVAC-R and service water piping design and insulation—energy_progress
08/10/2026HVAC-R and service water heating system controls—energy_progress
08/10/2026HVAC-R and service water heating equipment—energy_progress
08/10/2026Post-installed Anchors—special
08/10/2026Energy Code Compliance Inspections—progress
08/10/2026Fire-Resistant Penetrations and Joints—special
08/03/2026Fire-Resistant Penetrations and JointsMax Leespecial
07/27/2026Mechanical Systems—special
07/27/2026Final—progress
07/27/2026Tenant Protection Plan Compliance—special
06/25/2026Lighting in dwelling units—energy_progress
06/25/2026Fire-Resistant Penetrations and Joints—special
06/25/2026Final—progress
06/25/2026Energy Code Compliance Inspections—progress
06/25/2026Fire-Resistance Rated Construction—progress
06/25/2026Lighting controls—energy_progress
10/24/2025Post-installed AnchorsMOHAMMAD AHEADspecial
10/24/2025Alternative Materials - OTCR Buildings Bulletin NumberMOHAMMAD AHEADspecial
10/10/2025Alternative Materials - OTCR Buildings Bulletin NumberMOHAMMAD AHEADspecial
10/10/2025Post-installed AnchorsMOHAMMAD AHEADspecial
09/15/2025Tenant Protection Plan ComplianceSCOTT PROFETAspecial
09/15/2025Post-installed AnchorsSCOTT PROFETAspecial
Latest 25 of 52.
▾Documents — 392 on file (BIS + DOB NOW)
▸Plans & Drawings24
▸DOB NOWPlans/Sketch22
09/06/2026M00001965-I1Request digital key ↗
09/02/2026M00645375-P1Request digital key ↗
09/02/2026M00645375-I1Request digital key ↗
Showing 3 of 22 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/04/2026M00382179-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00165184-I1Request digital key ↗
▸Applications & Permits66
▸BISWORK PERMIT APPLICATION36
03/06/2020140872116Open ↗
11/09/2017121462586Open ↗
06/09/2017123094855Open ↗
Showing 3 of 36 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION29
03/01/2022104806694Open ↗
12/17/2021102909088Open ↗
10/15/2019140872116Open ↗
Showing 3 of 29 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Zoning, Tax Lot & Property Records1
▸BISFLOOD ZONE DESIGN CERTIFICATION1
10/15/2019140872116Open ↗
▸Seals & Professional Certifications100
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION35
04/06/2018123094855Open ↗
05/22/2017123094855Open ↗
05/22/2017123094855Open ↗
Showing 3 of 35 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature24
09/02/2026M00645375-P1Open ↗
09/02/2026M00645375-I1Open ↗
09/01/2026M08038969-P1Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
09/20/2026M01378007-P2Open ↗
09/01/2026M00645375-P1Open ↗
08/31/2026M00865562-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
09/01/2026M00645375-P1Open ↗
08/26/2026M00165184-I1Open ↗
08/25/2026M00382179-I1Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
10/17/2014121833604Open ↗
Showing 1 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
10/15/2019140872116Open ↗
10/17/2014121833604Open ↗
05/09/2013140077510Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
10/15/2019140872116Open ↗
05/09/2013140077510Open ↗
04/01/2013140066407Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
10/15/2019140872116Open ↗
05/09/2013140077510Open ↗
04/01/2013140066407Open ↗
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment37
▸BISSELF-CERT PLUMBING NOTICE25
06/09/2015121833604Open ↗
07/31/2014121902913Open ↗
06/18/2014121568017Open ↗
Showing 3 of 25 on file for this type
▸BISSCHEDULE B - PLUMBING8
04/15/2013121568017Open ↗
09/27/2012121351688Open ↗
Showing 2 of 8 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
05/22/2017123094855Open ↗
10/17/2014121833604Open ↗
01/29/2014121902913Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
03/14/2014121904314Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes3
06/06/2017123094855Open ↗
05/25/2017123094855Open ↗
10/15/2019140872116Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00382179-I1Open ↗
▸Environmental & Asbestos30
▸DOB NOWDEP ACP-5: Asbestos Assessment Report12
09/02/2026M00645375-P1Open ↗
09/02/2026M00645375-I1Open ↗
08/30/2026M00865559-P1Open ↗
Showing 3 of 12 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'8
01/13/2012120943364Open ↗
01/13/2012120943364Open ↗
Showing 2 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
10/17/2014121833604Open ↗
01/29/2014121902913Open ↗
05/09/2013140077510Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/15/2026M08038969-I1Open ↗
08/15/2026M08038928-I1Open ↗
08/13/2026M08038952-I1Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
03/04/2014121904314Open ↗
09/27/2012121351688Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
03/06/2020140872116Open ↗
▸Energy Compliance31
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS12
05/22/2017123094855Open ↗
04/25/2017121833604Open ↗
10/31/2014121904314Open ↗
Showing 3 of 12 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
04/06/2018123094855Open ↗
04/25/2017121833604Open ↗
10/31/2014121904314Open ↗
Showing 3 of 8 on file for this type
▸BISTR8: Energy Code Progress Inspections5
03/04/2014121904314Open ↗
04/15/2013121568017Open ↗
09/27/2012121351688Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
10/15/2019140872116Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
10/15/2019140872116Open ↗
▸BISNYCECC ANALYSIS1
10/15/2019140872116Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY6
12/22/2021102909088Open ↗
12/17/2021102909088Open ↗
03/06/2020140872116Open ↗
Showing 3 of 6 on file for this type
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
12/22/2021102909088Open ↗
▸Approvals, Objections & Sign-offs26
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST11
12/30/2021102909088Open ↗
04/06/2018123094855Open ↗
04/25/2017121833604Open ↗
Showing 3 of 11 on file for this type
▸BISADMINISTRATIVE OBJECTIONS9
04/15/2013121568017Open ↗
09/27/2012121351688Open ↗
Showing 2 of 9 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
10/31/2014121904314Open ↗
07/15/2013120943364Open ↗
05/13/2013140066407Open ↗
Showing 3 of 5 on file for this type
▸BISSUPERSEDING LETTER1
11/09/2017121462586Open ↗
▸Cost, Insurance & Ownership34
▸BISCOST AFFIDAVIT33
12/27/2021102909088Open ↗
12/22/2021102909088Open ↗
10/15/2019140872116Open ↗
Showing 3 of 33 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT1
01/23/2015121833604Open ↗
▸Filing & Intake Forms25
▸BISEFILING COVER SHEET14
05/22/2017123094855Open ↗
10/17/2014121833604Open ↗
03/04/2014121904314Open ↗
Showing 3 of 14 on file for this type
▸BISADDITIONAL INFORMATION6
02/26/2018123094855Open ↗
05/16/2014121568017Open ↗
01/08/2013110426726Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
10/15/2019140872116Open ↗
05/09/2013140077510Open ↗
04/01/2013140066407Open ↗
▸BISBOROUGH INTAKE FORM2
04/06/2018123094855Open ↗
02/09/2018123094855Open ↗
▸Other Documents7
▸DOB NOWManufacturer's Specifications2
08/13/2026M01246897-I1Open ↗
08/13/2026M01246897-P1Open ↗
▸DOB NOWCalculations2
08/13/2026M01246897-P1Open ↗
08/13/2026M01246897-I1Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
03/06/2020140872116Open ↗
▸BISDepartment of Consumer Affairs (DCA) Form1
02/27/2014121902913Open ↗
▸BISSUBSTANTIAL IMPROVEMENT CALCULATIONS1
10/15/2019140872116Open ↗