| Owner | Filings | Most Recent |
|---|---|---|
| SHR GROUP | 18 | 09/10/2026 |
| JAMESTOWN | 31 | 07/08/2026 |
| TRI BOROUGH SCAFFOLDING | 6 | 07/08/2026 |
| T-MOBILE | 6 | 07/08/2026 |
| JLL | 10 | 07/08/2026 |
| 24 | 07/08/2026 | |
| AT&T | 11 | 03/22/2026 |
| BLACK LARK ENTERPRISES | 8 | 03/22/2026 |
| RP STELLAR MILK OWNER LLC | 3 | 03/22/2026 |
| LAWRENCE EXTERIOR REST CO | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LEO Y LEE, PE | 1 | 04/21/2026 |
| RIGID STRUCTURAL DESIGN, LLC | 1 | 10/23/2025 |
| ROCK ARCH ENG CORP | 1 | 04/23/2025 |
| OSPINO ENGINEERING PLLC | 3 | 03/14/2025 |
| DESIMONE CONSULTING ENGINEERS | 5 | 09/18/2024 |
| JAROS BAUM & BOLLES | 9 | 09/05/2024 |
| M MOSER ASSOCIATES | 3 | 09/05/2024 |
| A SAXON DESIGN GROUP | 2 | 11/27/2023 |
| PETER MUNOZ | 1 | 04/08/2022 |
| ANASTASIO ARCHITECTS | 1 | 09/07/2021 |
| ROBERT DERECTOR ASSOCIATES | 5 | 12/21/2020 |
| PATUXENT ENGINEERING LLC | 1 | 11/25/2020 |
| KZ ENGINEERING, P.C | 1 | 08/20/2020 |
| SCALAR ARCHITECTURE PC | 1 | 07/13/2020 |
| NORTHEAST TOWER SURVEYING, INC. | 1 | 04/29/2020 |
| ANDREW FORMICHELLA | 7 | 01/24/2020 |
| ADG ARCHITECTURE AND DESIGN PC | 1 | 11/14/2019 |
| 5TH FLOOR DESIGN | 1 | 07/23/2019 |
| KM CONSULTING ENGINEERS, INC. | 1 | 04/11/2019 |
| SYNC ARCHITECTURE P.C | 1 | 01/22/2019 |
| COM-EX ENGINEERING OF NY, PLLC | 1 | 01/22/2019 |
| BURTNER ENGINEERING SERVICES, LLC | 1 | 01/14/2019 |
| WCG SOLUTIONS | 1 | 12/27/2018 |
| NB&C | 1 | 02/08/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| RIZZO GROUP | 19 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 8 | 03/21/2026 |
| HIERARCH-E | 6 | 03/21/2026 |
| A K EXPEDITING | 2 | 03/21/2026 |
| BILTMORE GROUP | 4 | 03/21/2026 |
| CCM CONSULTING GROUP, INC. | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| EA DESIGN GROUP | 2 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 3 | 03/21/2026 |
| GC1 EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TRI BOROUGH SCAFFOLDING | General Contractor | 10 | 07/08/2026 |
| SHR GROUP INC | General Contractor | 8 | 07/08/2026 |
| SAC WIRELESS,LLC | General Contractor | 6 | 03/21/2026 |
| LAWRENCE J. LEVINE | Fire Protection | 5 | 03/21/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 4 | 07/08/2026 |
| L&K PARTNERS, INC | General Contractor | 4 | 07/08/2026 |
| STONEHENGE BUILDING SERV | General Contractor | 4 | 09/10/2026 |
| EASTERN ALLIANCE LLC | General Contractor | 4 | 03/21/2026 |
| OVERLAND CONTRACTING INC | General Contractor | 3 | 03/21/2026 |
| BENCHMARK BUILDERS LLC | General Contractor | 3 | 07/08/2026 |
| PAR FIRE PROTECTION | Plumbing | 3 | 03/22/2026 |
| KC EXPEDITING INC | General Contractor | 2 | 06/28/2026 |
| ERNEST JOCHEN | Electrical | 2 | 03/21/2026 |
| SCIAME CONSTRUCTION LLC | General Contractor | 2 | 03/21/2026 |
| TRISTATE PLBG SVCS CORP | Plumbing | 1 | 07/08/2026 |
| CHRISTOPHER HAND | Electrical | 1 | 03/21/2026 |
| COLIN MCELWEE | Electrical | 1 | 03/21/2026 |
| JAVIER VALERA ACERO | Electrical | 1 | 03/21/2026 |
| PATRIOT ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 1 | 07/08/2026 |
| TRISTATE PLBG SVCS CORP | Fire Protection | 1 | 07/08/2026 |
| EAGLE SCAFFOLDING SVCS INC | General Contractor | 1 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 1 | 07/08/2026 |
| GOTHAM COMMUNICATIONS LLC | General Contractor | 1 | 07/08/2026 |
| KMM TELECOMMUNICATIONS | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ROCK ARCH ENG CORP | 7831 | 1 | 04/23/2025 |
| SOCOTEC ENGINEERING | 4983 | 4 | 09/18/2024 |
| SAG ENGINEERING & CONSULT | 608 | 1 | 03/15/2023 |
| DELTA TESTING LABS | 687 | 11 | 04/26/2022 |
| CODEGREEN | 510 | 1 | 12/21/2020 |
| DNA CONTROLLED INSPECTION | 554 | 3 | 03/23/2020 |
| R MARSAC CONSULTING LLC | 329 | 1 | 01/22/2019 |
| BURTNER ENGINEERING SERVI | 5910 | 2 | 01/14/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Permit Issued | STONEHENGE BUILDING SERV | 09/09/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | STONEHENGE BUILDING SERV | 07/17/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | STONEHENGE BUILDING SERV | 07/06/2026 |
| DOB NOW | General Construction | Permit Issued | STONEHENGE BUILDING SERV | 05/18/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | KC EXPEDITING INC | 04/21/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | KC EXPEDITING INC | 04/07/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | SHR GROUP INC | 10/24/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | PEDROL CONTRACTING INC | 07/03/2025 |
| DOB NOW | General Construction | Permit Issued | SHR GROUP INC | 05/14/2025 |
| DOB NOW | General Construction | Permit Issued | SHR GROUP INC | 05/01/2025 |
| DOB NOW | General Construction | Signed-off | L&K PARTNERS, INC | 04/22/2025 |
| DOB NOW | Structural | Signed-off | L&K PARTNERS, INC | 04/16/2025 |
| DOB NOW | Mechanical Systems | Signed-off | L&K PARTNERS, INC | 04/16/2025 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 03/18/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | PEDROL CONTRACTING INC | 02/11/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | SHR GROUP INC | 01/21/2025 |
| DOB NOW | Antenna | Signed-off | GOTHAM COMMUNICATIONS LLC | 09/21/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | TRI BOROUGH SCAFFOLDING | 05/15/2023 |
| DOB NOW | Structural | Signed-off | RALLY RESTORATION CORP | 05/10/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/23/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | TRI BOROUGH SCAFFOLDING | 04/19/2022 |
| DOB NOW | General Construction | Signed-off | SCIAME CONSTRUCTION LLC | 09/15/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 09/14/2021 |
| DOB NOW | Antenna | Permit Issued | KMM TELECOMMUNICATIONS | 07/15/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | TRI BOROUGH SCAFFOLDING | 03/31/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 11/25/2020 |
| DOB NOW | Antenna | Permit Issued | KMM TELECOMMUNICATIONS | 09/28/2020 |
| DOB NOW | Sidewalk Shed | Permit Issued | TRI BOROUGH SCAFFOLDING | 08/21/2020 |
| DOB NOW | Mechanical Systems | Signed-off | BENCHMARK BUILDERS LLC | 08/06/2020 |
| DOB NOW | Construction Fence | Signed-off | EAGLE SCAFFOLDING SVCS IN | 07/14/2020 |
| DOB NOW | Mechanical Systems | Signed-off | BENCHMARK BUILDERS LLC | 06/18/2020 |
| DOB NOW | Plumbing | Signed-off | TRISTATE PLBG SVCS CORP | 03/25/2020 |
| DOB NOW | Sprinklers | Signed-off | TRISTATE PLBG SVCS CORP | 03/25/2020 |
| DOB NOW | Antenna | Permit Issued | SAC WIRELESS,LLC | 05/30/2019 |
| DOB NOW | Antenna | Permit Issued | OVERLAND CONTRACTING INC | 02/13/2019 |
| DOB NOW | Antenna | Permit Issued | SAC WIRELESS,LLC | 02/08/2019 |
| DOB NOW | Antenna | Signed-off | EASTERN ALLIANCE LLC | 04/10/2018 |
| DOB NOW | Antenna | Signed-off | EASTERN ALLIANCE LLC | 02/08/2018 |
| BIS | OT | ISSUED | RALLY RESTORATION CORP | 03/16/2022 |
| BIS | OT | ISSUED | RALLY RESTORATION CORP | 11/05/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/11/2022 | — | — | 1,076 heads, 37 outlets |
| 12/21/2021 | — | — | 10 outlets |
| 12/21/2020 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/26/2022 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/18/2026 | Permit Issued | TRITECH ELECTRICAL & DATA INC | General Wiring |
| 02/01/2025 | Permit Issued | V ELECTRIC NY INC | — |
| 01/19/2021 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 01/15/2021 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 12/11/2020 | Complete | PATRIOT ELECTRIC CORP | General Wiring |
| 11/24/2020 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 08/25/2020 | Complete | V. VASS ELECTRIC CORP | — |
| 02/14/2020 | Complete | NEAD ELECTRIC INC. | — |
| 09/30/2019 | Complete | PATRIOT ELECTRIC CORP | General Wiring |
| 01/25/2019 | Complete | PATRIOT ELECTRIC CORP | General Wiring |
| 01/17/2019 | Complete | PATRIOT ELECTRIC CORP | — |
| 10/03/2018 | Complete | BIG SHOT ELECTRIC CORP. | General Wiring |
| 01/11/2018 | Complete | ASK ELECTL CONTRTNG CORP | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/04/2022 | — | — | Steel, Concrete |
| 12/22/2021 | — | — | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/21/2026 | Permit Issued | KC EXPEDITING INC | Sidewalk Shed |
| 03/14/2025 | Permit Issued | STONEHENGE BUILDING SERV | Sidewalk Shed |
| 08/20/2020 | Permit Issued | TRI BOROUGH SCAFFOLDING | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/14/2025 | Permit Issued | STONEHENGE BUILDING SERV | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/06/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/24/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/17/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/06/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/30/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/01/2024 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 08/01/2024 | Post-installed Anchors | ALEXIS SCHLESSINGERMAN | special |
| 07/22/2024 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 07/22/2024 | Duct leakage testing, insulation and design | ALEXIS SCHLESSINGERMAN | energy_progress |
| 07/22/2024 | Fire-Resistance Rated Construction | ALEXIS SCHLESSINGERMAN | progress |
| 07/22/2024 | HVAC-R and service water heating system controls | ALEXIS SCHLESSINGERMAN | energy_progress |
| 07/22/2024 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 07/22/2024 | HVAC-R and service water heating equipment | ALEXIS SCHLESSINGERMAN | energy_progress |
| 07/22/2024 | Interior lighting power | ALEXIS SCHLESSINGERMAN | energy_progress |
| 07/22/2024 | HVAC-R and service water piping design and insulation | ALEXIS SCHLESSINGERMAN | energy_progress |
| 07/22/2024 | Lighting controls | ALEXIS SCHLESSINGERMAN | energy_progress |
| 07/22/2024 | Post-installed Anchors | ALEXIS SCHLESSINGERMAN | special |
| 07/15/2024 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 07/15/2024 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 07/15/2024 | Mechanical Systems | ALEXIS SCHLESSINGERMAN | special |
| 07/15/2024 | Sprinkler Systems | ALEXIS SCHLESSINGERMAN | special |
| 02/22/2023 | Concrete - Cast-In-Place | Chester Kowalski | special |
| 02/22/2023 | Structural Steel - Details | Chester Kowalski | special |
| 01/09/2023 | Final | Chester Kowalski | progress |
| 04/04/2022 | Metering | RICHARD GREENWALD | energy_progress |
| 04/04/2022 | Electrical motors and elevators | RICHARD GREENWALD | energy_progress |
| 04/04/2022 | Exterior lighting power | RICHARD GREENWALD | energy_progress |
| 03/28/2022 | Structural Stability – Alterations of existing buildings | RICHARD GREENWALD | special |
| 03/28/2022 | Concrete - Cast-In-Place | RICHARD GREENWALD | special |
| 01/21/2022 | Air barrier - visual inspection | RICHARD GREENWALD | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Office | Cellar, Floors 1–8, Penthouse | Project M01080958 Project M01080848 Project M01080949 Project M01080858 Project M00645061 Project M00645076 Project M00645051 Project M00645034 Project M00666096 Project M00639204 Project M00639200 Project M00649181 |