| Owner | Filings | Most Recent |
|---|---|---|
| Lloyd 54th Condominium | 15 | 07/08/2026 |
| MLP | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Robert John Hills Architect | 2 | 06/02/2026 |
| Mje Professional Services | 3 | 10/23/2025 |
| SW Engineering Company | 2 | 08/19/2025 |
| Aaron McDonald Architect | 2 | 07/09/2025 |
| Urban Design Engineering | 1 | 09/18/2023 |
| Ashraf | 1 | 04/10/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| PS Engineers | 4 | 03/21/2026 |
| Agouti Construction Consulting | 2 | 03/21/2026 |
| Municipal Building Consultants | 2 | 03/21/2026 |
| Construction Lab | 2 | 03/21/2026 |
| SNR Expediting Design | 6 | 03/21/2026 |
| Rigid Structural Design | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| New American Construction | Scaffold | 5 | 07/08/2026 |
| Ice Age Mechanical | specialty_contractor | 4 | 07/08/2026 |
| Intersystem Installation | Scaffold | 3 | 03/21/2026 |
| Maspeth Contracting | General Contractor | 2 | 04/09/2026 |
| John Fitzgerald Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Roma Electric | Electrical | 1 | 03/21/2026 |
| Orchester Management Com* | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SWL Engineering Inspectio | 6912 | 2 | 08/19/2025 |
| AK Consulting Services, I | 6198 | 1 | 07/09/2025 |
| R M & E Engineerinc | 3030 | 1 | 09/18/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Protection and Mechanical Methods | Signed-off | New American Construction | 10/24/2025 |
| DOB NOW | Supported Scaffold | Signed-off | New American Construction | 10/23/2025 |
| DOB NOW | General Construction | Permit Issued | Maspeth Contracting | 10/09/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | Maspeth Contracting | 10/09/2025 |
| DOB NOW | General Construction | Permit Issued | Maspeth Contracting | 10/09/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | New American Construction | 10/07/2025 |
| DOB NOW | Plumbing | Signed-off | John Fitzgerald Plumbing & Heating | 09/05/2025 |
| DOB NOW | General Construction | Signed-off | Orchester Management Com* | 07/21/2025 |
| DOB NOW | General Construction | Permit Issued | Ice Age Mechanical | 07/02/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | Ice Age Mechanical | 07/02/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Intersystem Installation | 04/13/2021 |
| BIS | MH | ISSUED | Maxco Contracting | 02/26/2016 |
| BIS | OT | ISSUED | Jepol Construction | 09/03/2015 |
| BIS | EQ | ISSUED | Jepol Construction | 06/23/2015 |
| BIS | PL | ISSUED | Top Dog Plumbing & Heating | 06/23/2015 |
| BIS | OT | ISSUED | Jepol Construction | 06/23/2015 |
| BIS | OT | ISSUED | Age Contracting | 06/23/2015 |
| BIS | EQ | RE-ISSUED | Steel Systems | 05/04/2015 |
| BIS | EQ | ISSUED | Steel Systems | 05/04/2015 |
| BIS | EQ | ISSUED | Everest Scaffolding | 11/10/2011 |
| BIS | EQ | ISSUED | Everest Scaffolding | 02/04/2008 |
| BIS | EQ | ISSUED | Everest Scaffolding | 08/27/2007 |
| BIS | EQ | ISSUED | Twin & Swing Scaffolding | 06/16/2006 |
| BIS | EQ | ISSUED | Spring Scaffolding | 11/13/2001 |
| BIS | MH | ISSUED | Ampersano Maintenance | 12/03/1999 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/18/2023 | Permit Issued | Ice Age Mechanical | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM36NAMHZ2 3,600 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/02/2026 | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2026 | Permit Issued | Empire Lic Electrical Contractors | General Wiring |
| 07/13/2026 | Permit Issued | Empire Lic Electrical Contractors | General Wiring |
| 10/03/2025 | Complete | Richard Neu | — |
| 03/22/2021 | Complete | Steven Farkas | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/06/2025 | Signed-off | New American Construction | Sidewalk Shed |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2026 | Lighting in dwelling units | — | energy_progress |
| 08/19/2026 | Lighting controls | — | energy_progress |
| 08/19/2026 | Interior lighting power | — | energy_progress |
| 06/25/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/08/2025 | Lighting in dwelling units | Aaron McDonald | energy_progress |
| 07/08/2025 | Fire-Resistant Penetrations and Joints | MAHFUZAR RAHMAN | special |
| 06/30/2025 | Final | Aaron McDonald | progress |
| 06/10/2025 | Final | — | progress |
| 10/01/2024 | Final | Joshua Luckritz | progress |
| 10/01/2024 | Tenant Protection Plan Compliance | JOSHUA LUCKRITZ | special |
| 08/16/2023 | Mechanical Systems | REMON YUSSIF | special |
| 08/16/2023 | Final | SHERIF ABDEL-MESEH | progress |