| Owner | Filings | Most Recent |
|---|---|---|
| STREAM REALTY PARTNERS | 1 | 09/13/2026 |
| CARSAB | 10 | 08/26/2026 |
| ORANGETHEORY FITNESS | 5 | 07/08/2026 |
| STREAM REALTY | 39 | 07/08/2026 |
| AFIAA | 3 | 07/08/2026 |
| AFIAA 45 WEST 45TH STREET, LLC | 13 | 07/08/2026 |
| CBRE | 21 | 07/08/2026 |
| J G CONSTRUCTION SRVCS | 8 | 07/08/2026 |
| AVARGA CONSTRUCTION | 15 | 04/09/2026 |
| 45 W 45 STRATEGIC VENTURES | 189 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/26/2019 | $126.0M | — | 45W45 STRATEGIC VENTURE LLC → AFIAA 45 WEST 45TH STREET, LLC | $1,157/sf building |
| 01/12/2015 | $81.0M | — | NEW 45 WEST 45TH STREET LLC → 45W45 STRATEGIC VENTURE LLC | $744/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| REAVES ARCHITECTURE LLC | 1 | 07/13/2026 |
| JACK GREEN ASSOCIATES | 3 | 07/10/2026 |
| CHANDA ENGINEERING CONSULTANT PC | 7 | 06/12/2026 |
| MG ENGINEERING D.P.C. | 8 | 06/05/2026 |
| OSPINO ENGINEERING PLLC | 4 | 05/20/2025 |
| ZACHARY SAPINSLEY LEWIS, R.A. | 3 | 02/13/2025 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 02/04/2025 |
| LOFFREDO BROOKS ARCHITECTS P.C. | 2 | 11/07/2024 |
| SUPERSTRUCTURES ENG. + ARCH. | 1 | 09/11/2024 |
| CORNERSTONE ENGINEERING, INC. | 1 | 05/24/2024 |
| MIRELLA BOSELLI ARCHITECT | 7 | 05/30/2023 |
| TSF ENGINEERING, PC | 6 | 03/30/2023 |
| HUNTSMAN ARCHITECTURAL GROUP | 2 | 11/30/2022 |
| EP ENGINEERING LLC | 3 | 11/04/2021 |
| SPIVAK ARCHITECTS P.C. | 1 | 05/06/2021 |
| SYED ENGINEERING, P.C. | 1 | 04/10/2019 |
| HAIDER ENGINEERING, P.E. | 1 | 08/14/2018 |
| CHRISTIAN KOTZAMANIS | 1 | 08/03/2018 |
| LEON SKVIRSKY PE | 2 | 01/31/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| RICHARD LEWIS ARCHITECT | 16 | 03/21/2026 |
| RIZZO GROUP | 11 | 03/21/2026 |
| OUTSOURCE CONSULTANTS, INC. | 7 | 03/21/2026 |
| SIGNS CAD | 2 | 03/21/2026 |
| JME BUILDING CONSULTING | 8 | 03/21/2026 |
| SOMMA DESIGN CONSULTING | 2 | 03/21/2026 |
| BUILDING BROTHERS | 4 | 03/21/2026 |
| SUPERSTRUCTURES ENG + ARCH | 1 | 03/21/2026 |
| HAIDER ENGINEERING, P.E. | 1 | 03/21/2026 |
| HAIDER ENGINEERING P E | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MCK CONTRACTING INC | General Contractor | 9 | 07/08/2026 |
| WESBUILT CONSTRUCTION MAN | General Contractor | 5 | 07/08/2026 |
| PAUL OLSEN | Electrical | 5 | 03/21/2026 |
| JOHN GALLIN & SON, INC | General Contractor | 5 | 07/08/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 4 | 07/08/2026 |
| AVARGA CONSTRUCTION CORP | General Contractor | 4 | 06/27/2026 |
| OZ AIR CONDITIONING, INC | General Contractor | 4 | 07/08/2026 |
| MILLENIUM CENT CONTR CORP | General Contractor | 3 | 03/21/2026 |
| CARSAB LLC | General Contractor | 3 | 06/28/2026 |
| RAPTOR MECHANICAL,INC | Plumbing | 3 | 07/08/2026 |
| BARRY SAXE | Electrical | 2 | 03/21/2026 |
| VLADIMIR VATA | Electrical | 2 | 03/21/2026 |
| BEDROCK MECHANICAL INC | Fire Protection | 2 | 07/08/2026 |
| MGI DESIGNED INTERIORS | General Contractor | 2 | 09/15/2026 |
| TREDENT CONTRACTING SERVI | General Contractor | 2 | 07/08/2026 |
| PAUL SIGNS | Scaffold | 2 | 07/08/2026 |
| P & D MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| EXTERIOR WALL & BUILDING | General Contractor | 1 | 04/09/2026 |
| AQUEDUCT MECHANICAL CORP | Fire Protection | 1 | 08/25/2026 |
| ACCURATE MECHANICAL INC | Fire Protection | 1 | 07/08/2026 |
| STEFAN KLINTCHOV | Electrical | 1 | 03/21/2026 |
| SAFEPIPE PLUMBING INC | Plumbing | 1 | 08/26/2026 |
| MARTINEZ ELECTRICAL CONT | Electrical | 1 | 03/22/2026 |
| JOSEPH KASHINSKY | Electrical | 1 | 03/21/2026 |
| SIGNS CAD | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ASDA ARCHITECTURE + DESIG | 2015 | 3 | 07/13/2026 |
| JACK GREEN ASSOCIATES | 422 | 2 | 07/10/2026 |
| CHANDA ENG. CONSULTANT PC | 6842 | 7 | 06/12/2026 |
| BROADWAY INSPECTIONS | 8735 | 1 | 06/05/2026 |
| AK ENGINEERING PC | 678 | 8 | 10/30/2024 |
| SUPERSTRUCTURES ENGINEERI | 374 | 1 | 09/11/2024 |
| TSF ENGINEERING, PC | 1274 | 4 | 03/30/2023 |
| MIRELLA BOSELLI R.A. | 6330 | 4 | 10/28/2022 |
| OUTSOURCE SPECIAL INSPECT | 2827 | 2 | 11/04/2021 |
| STANDARD FIRE SUPPRESSION | 5896 | 1 | 03/19/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | MGI DESIGNED INTERIORS | 09/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | MGI DESIGNED INTERIORS | 09/14/2026 |
| DOB NOW | Plumbing | Permit Issued | SAFEPIPE PLUMBING INC | 08/25/2026 |
| DOB NOW | Plumbing | Permit Issued | AQUEDUCT MECHANICAL CORP | 08/24/2026 |
| DOB NOW | Sprinklers | Permit Issued | AQUEDUCT MECHANICAL CORP | 08/24/2026 |
| DOB NOW | General Construction | Permit Issued | AVARGA CONSTRUCTION CORP | 06/25/2026 |
| DOB NOW | General Construction | Permit Issued | CARSAB LLC | 06/18/2026 |
| DOB NOW | Sprinklers | Permit Issued | SAFEPIPE PLUMBING INC | 05/20/2026 |
| DOB NOW | General Construction | Permit Issued | CARSAB LLC | 05/13/2026 |
| DOB NOW | General Construction | Permit Issued | CARSAB | 03/17/2026 |
| DOB NOW | General Construction | Permit Issued | AVARGA CONSTRUCTION CORP | 03/31/2025 |
| DOB NOW | Supported Scaffold | Signed-off | AVARGA CONSTRUCTION CORP | 02/21/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | AVARGA CONSTRUCTION CORP | 02/04/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | EXTERIOR WALL & BUILDING | 02/04/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | AVARGA CONSTRUCTION CORP | 01/28/2025 |
| DOB NOW | General Construction | Signed-off | JOHN GALLIN SON | 11/20/2024 |
| DOB NOW | Sprinklers | Signed-off | BEDROCK MECHANICAL INC | 11/18/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JOHN GALLIN SON | 11/12/2024 |
| DOB NOW | Plumbing | Signed-off | BEDROCK PLBG. & HTG., INC | 11/12/2024 |
| DOB NOW | General Construction | Signed-off | JOHN GALLIN SON | 09/25/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JOHN GALLIN SON | 09/24/2024 |
| DOB NOW | Sprinklers | Signed-off | BEDROCK MECHANICAL INC | 09/17/2024 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 05/29/2024 |
| DOB NOW | General Construction | Permit Issued | MCK CONTRACTING INC | 10/05/2023 |
| DOB NOW | Construction Fence | Signed-off | MCK CONTRACTING INC | 10/05/2023 |
| DOB NOW | Sprinklers | Permit Issued | P & D MECHANICAL CORP | 09/15/2023 |
| DOB NOW | Construction Fence | Signed-off | MCK CONTRACTING INC | 09/08/2023 |
| DOB NOW | Plumbing | Signed-off | RAPTOR MECHANICAL, INC | 01/31/2023 |
| DOB NOW | General Construction | Signed-off | WESBUILT CONSTRUCTION MAN | 12/05/2022 |
| DOB NOW | General Construction | Permit Issued | MCK CONTRACTING INC | 11/04/2022 |
| DOB NOW | Sprinklers | Permit Issued | REEM PLBG & HTG CORP | 09/26/2022 |
| DOB NOW | General Construction | Permit Issued | WESBUILT CONSTRUCTION MAN | 09/07/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | WESBUILT CONSTRUCTION MAN | 09/07/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | OZ AIR CONDITIONING, INC | 11/10/2021 |
| DOB NOW | Sprinklers | Permit Issued | ACCURATE MECHANICAL INC | 08/23/2021 |
| DOB NOW | Mechanical Systems | Signed-off | OZ AIR CONDITIONING, INC | 08/03/2021 |
| DOB NOW | General Construction | Signed-off | TREDENT CONTRACTING SERVI | 07/30/2021 |
| DOB NOW | General Construction | Permit Issued | MCK CONTRACTING INC | 07/09/2021 |
| DOB NOW | Plumbing | Signed-off | RAPTOR MECHANICAL, INC | 07/08/2021 |
| DOB NOW | General Construction | Signed-off | TREDENT CONTRACTING SERVI | 05/11/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/10/2026 | Permit Issued | MGI DESIGNED INTERIORS | Ventilation Systems | — |
| 06/05/2026 | — | — | Air Conditioning Systems, Heating Systems | Cooling Mitsubishi Electric TUHYE120AN41AN 120,000 BTU · Vrf Outdoor ×2 Heating Mitsubishi Electric TUHYE120AN41AN 135,000 BTU · Vrf Outdoor ×2 |
| 11/04/2021 | Permit Issued | OZ AIR CONDITIONING, INC | Air Conditioning Systems | Cooling Johnson Controls SDSV240C2 8,000 CFM · Packaged Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2026 | Permit Issued | AQUEDUCT MECHANICAL CORP | — |
| 06/12/2026 | Permit Issued | SAFEPIPE PLUMBING INC | Sprinkler System |
| 03/30/2023 | Permit Issued | CMP PIPING INC | 3 heads |
| 08/31/2022 | Permit Issued | REEM PLBG & HTG CORP | — |
| 05/27/2021 | Permit Issued | ACCURATE MECHANICAL INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2026 | Permit Issued | AQUEDUCT MECHANICAL CORP | Water/Sanitary |
| 06/12/2026 | Permit Issued | SAFEPIPE PLUMBING INC | Water/Sanitary |
| 05/21/2021 | Signed-off | RAPTOR MECHANICAL,INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/16/2026 | Complete | RAIDEN ELECTRIC LLC | General Wiring |
| 11/13/2025 | Complete | POWER UP NYC ELECTRIC COR | General Wiring |
| 02/05/2025 | Complete | 5 J'S ELECTL CONTS CORP | — |
| 10/25/2024 | Permit Issued | MRD ELEC'L SERVICES, INC | General Wiring |
| 07/18/2024 | Complete | SIGNS CAD CORP | — |
| 02/19/2024 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 07/14/2021 | Complete | NASH ELECTRIC SERVICES IN | General Wiring, Lighting |
| 07/02/2019 | Complete | ALLIANCE ELEVATOR COMPANY | — |
| 04/08/2019 | Permit Issued | BRANDL ELECTRIC INC. | General Wiring |
| 04/03/2019 | Permit Issued | RICHARD NEU | — |
| 02/10/2019 | Complete | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 12/19/2018 | Complete | CEDAR ELEC'L CONT'RS INC. | HVAC Wiring |
| 12/19/2018 | Complete | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 11/27/2018 | Permit Issued | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 08/04/2018 | Permit Issued | ALEF ELEC'L CONTR'G INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2025 | Permit Issued | AVARGA CONSTRUCTION CORP | Scaffold |
| 09/21/2023 | Signed-off | MCK CONTRACTING INC | Fence |
| 08/14/2018 | Permit Issued | J & G CONSTRUCTION SRVCS | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2025 | Permit Issued | AVARGA CONSTRUCTION CORP | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/28/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/25/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/03/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/23/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/25/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/06/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 10/20/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/20/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/08/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/08/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/20/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/20/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/30/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/24/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/18/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/11/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/05/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/23/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/12/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/28/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/23/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/18/2026 | Tenant Protection Plan Compliance | KARTIK CHANDA | special |
| 07/02/2026 | Fire-Resistant Penetrations and Joints | Alfonso DElia | special |
| 07/02/2026 | Final | LAWRENCE GREEN | progress |
| 07/02/2026 | Final | Alfonso DElia | progress |
| 07/02/2026 | Fire-Resistant Penetrations and Joints | Alfonso DElia | special |
| 07/02/2026 | Mechanical Systems | LAWRENCE GREEN | special |
| 07/02/2026 | Fire-Resistant Penetrations and Joints | Alfonso DElia | special |
| 06/12/2026 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 06/12/2026 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 06/12/2026 | Final | Sanjib Das | progress |
| 06/12/2026 | Lighting controls | KARTIK CHANDA | energy_progress |
| 06/12/2026 | Interior lighting power | KARTIK CHANDA | energy_progress |
| 06/11/2026 | Final | — | progress |
| 06/11/2026 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 06/11/2026 | Interior lighting power | KARTIK CHANDA | energy_progress |
| 06/11/2026 | Lighting controls | KARTIK CHANDA | energy_progress |
| 06/08/2026 | Interior lighting power | KARTIK CHANDA | energy_progress |
| 06/08/2026 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 06/08/2026 | Lighting controls | KARTIK CHANDA | energy_progress |
| 05/20/2026 | Interior lighting power | KARTIK CHANDA | energy_progress |
| 05/20/2026 | Lighting controls | KARTIK CHANDA | energy_progress |
| 05/20/2026 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 05/11/2026 | Sprinkler Systems | LAWRENCE GREEN | special |
| 05/07/2026 | HVAC-R and service water piping design and insulation | Salvatore Chiarelli | energy_progress |
| 05/07/2026 | HVAC-R and service water heating equipment | Salvatore Chiarelli | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Madame George | Restaurant / Food Service | Cellar, Floor 1 | Project M00605963 Project M00526394 Project M00495176 |
| Valerie Kitchen | Restaurant / Food Service | Cellar | Project M00495250 |