← Back
BuildNYC
Elevator cooperative
454 WEST 46TH STREET
MANHATTAN · BIN 1083773
💬 Discuss this project
1900Year Built
6Stories
D4Building Class
R8Zoning
60,000 sfGross Floor Area
48Units
LL97 CoveredRent Stabilized12 Active Violations ▸FISP: SAFE
Elevator cooperative · Owner of record: The Piano Factory · 17,715 sf lot · 3.39 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofSuspended scaffold outrigger system for facade inspectionUnder Construction64p · 7 filings · 20 docs
PenthouseUnit PH51p · 5 filings · 20 docs
Floor 7Seventh floor and roof framing1p · 2 filings · 11 docs
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1Installation of Temporary Pipe Scaffold8p · 3 filings · 9 docs
Site & exteriorPiano Factory CORP37p · 6 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Piano Factory8207/08/2026
Phoenix403/21/2026
454 West 46th Street103/21/2026
Piano Factory Cooperative103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Edwards and Zuck407/13/2024
William Green Architecture405/07/2024
Ashraf308/25/2023
Enthink Engineers110/01/2022
Severud Associates106/17/2022
Stone106/02/2022
Syed Engineering310/20/2021
Hamann Engineering303/27/2019
Lombardo Professional Engineering108/07/2018
Baileys Engineering206/28/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
William Vitacco Associates1803/21/2026
PS Engineers203/21/2026
Aca Associates303/21/2026
Stone203/21/2026
Expediting203/21/2026
AE Design Solution403/21/2026
Lombardo Building Consultants203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Express RenovationsGeneral Contractor2407/08/2026
Phoenix Sutton STRScaffold1203/21/2026
Core Scaffold SystemsScaffold707/08/2026
ZKW EnterprisesScaffold407/08/2026
Tribute RestorationScaffold307/08/2026
Everest ScaffoldingScaffold307/08/2026
J & G Construction ServicesScaffold303/21/2026
Elpo Electrical ContgElectrical203/21/2026
Tribute Restorationspecialty_contractor203/21/2026
York RestorationScaffold107/08/2026
I. M. ElectricElectrical103/21/2026
Scarponi & Son Plumbing & HeatingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Domani Inspection Service843807/13/2024
Stone Engineering & Architects1362106/02/2022
Building Lifecycle
All (200)Filed (24)Permit Issued (32)Signed Off (10)Facade (FISP) (15)Violation (60)Inspection (5)Objection (24)Special Inspection (30)
03/22/2026
Permit issued — Suspended Scaffold
M01364442-I1-SC
03/18/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
FRANCISCO PEREZ
03/06/2026
Objection raised — Other
03/06/2026
Objection resolved — Addressed
03/05/2026
Filed — Alteration
FILE SUSPENDED SCAFFOLD OUTRIGGER SYSTEMS FOR FACADE INSPECTION.
M01364442-I1
09/11/2024
Signed off — Alteration
Mechancial work assoicated with interior renovation of existing residential penthouse apartment. No change to egress,use, or occupancy.
M00713369-I1
09/10/2024
Signed off — Alteration
Replacement of roof enclosure and interior renovation of existing residential penthouse. No change to egress, use, or occupancy.
M00713356-I1
09/09/2024
Signed off — Alteration
Filing for the removal of the wood deck and convenience stair at the roof, to be replaced with pavers. No change to use, egress, or occupancy.
M00717868-I1
09/09/2024
Signed off — Alteration
Filing for plumbing work at the penthouse and roof. No change to use, egress, or occupancy.
M00713374-I1
09/09/2024
Signed off — Alteration
Structural work associated with replacement of roof enclosure, new skylights, misc support for condenser units. No change to use, egress, or occupancy.
M00713379-I1
07/25/2024
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
07/25/2024
Objection resolved — Addressed
07/24/2024
Objection raised — Scope
07/19/2024
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
07/13/2024
Filed — Alteration
Mechancial work assoicated with interior renovation of existing residential penthouse apartment. No change to egress,use, or occupancy.
M00713369-P1
07/11/2024
Permit issued — Structural
M00713379-I1-ST
07/11/2024
Permit issued — General Construction
M00713356-I1-GC
07/09/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/09/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/05/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
M00909824-I1
05/14/2024
Special inspection requirement — Metering
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Lighting in dwelling units
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Lighting controls
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Insulation placement and R values
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Fenestration air leakage
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Exterior lighting power
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Fenestration areas
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Energy Code Compliance Inspections
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Final
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Fire-Resistance Rated Construction
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Permanent certificate
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Interior lighting power
JOHN MCMONAGLE
05/14/2024
Special inspection requirement — Air barrier - visual inspection
JOHN MCMONAGLE
05/07/2024
Filed — Alteration
Replacement of roof enclosure and interior renovation of existing residential penthouse. No change to egress, use, or occupancy.
M00713356-P1
03/25/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/06/2024
Objection raised — Scope
02/06/2024
Objection resolved — Addressed
02/01/2024
Filed — Alteration
Filing for plumbing work at the penthouse and roof. No change to use, egress, or occupancy.
M00713374-P1
01/02/2024
Special inspection requirement — Insulation placement and R values
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Energy Code Compliance Inspections
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Final
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Fire-Resistance Rated Construction
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Interior lighting power
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Lighting controls
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Lighting in dwelling units
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Fenestration air leakage
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Metering
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Permanent certificate
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Air barrier - visual inspection
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
JOHN MCMONAGLE
01/02/2024
Special inspection requirement — Exterior lighting power
JOHN MCMONAGLE
11/13/2023
Permit issued — Structural
M00713379-I1-ST
11/09/2023
Permit issued — Mechanical Systems
M00713369-I1-MS
11/09/2023
Permit issued — General Construction
M00717868-I1-GC
11/09/2023
Permit issued — General Construction
M00713356-I1-GC
10/13/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
M08010190-I1
10/02/2023
Permit issued — Sidewalk Shed
M08010190-I1-SF
Latest 60 of 200 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedTribute Restoration03/22/2026
DOB NOWStructuralSigned-offExpress Renovations07/11/2024
DOB NOWGeneral ConstructionSigned-offExpress Renovations07/11/2024
DOB NOWStructuralSigned-offExpress Renovations11/13/2023
DOB NOWMechanical SystemsSigned-offExpress Renovations11/09/2023
DOB NOWGeneral ConstructionSigned-offExpress Renovations11/09/2023
DOB NOWGeneral ConstructionSigned-offExpress Renovations11/09/2023
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR10/02/2023
DOB NOWSupported ScaffoldSigned-offPhoenix Sutton STR10/02/2023
DOB NOWGeneral ConstructionSigned-offExpress Renovations08/24/2023
DOB NOWStructuralSigned-offExpress Renovations08/24/2023
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR07/28/2023
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR07/28/2023
DOB NOWPlumbingSigned-offScarponi & Son Plumbing & Heating06/29/2023
DOB NOWGeneral ConstructionSigned-offExpress Renovations06/08/2023
DOB NOWMechanical SystemsSigned-offExpress Renovations06/06/2023
DOB NOWGeneral ConstructionPermit IssuedTribute Restoration11/17/2022
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR10/03/2022
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR10/03/2022
DOB NOWStructuralSigned-offExpress Renovations09/27/2022
DOB NOWGeneral ConstructionSigned-offExpress Renovations08/02/2022
DOB NOWSupported ScaffoldPermit IssuedZKW Enterprises10/21/2021
DOB NOWSidewalk ShedPermit IssuedZKW Enterprises10/20/2021
DOB NOWSidewalk ShedPermit IssuedJ & G Construction Services05/06/2021
DOB NOWSidewalk ShedPermit IssuedYork Restoration08/08/2018
DOB NOWSidewalk ShedSigned-offEverest Scaffolding07/26/2018
DOB NOWSupported ScaffoldSigned-offTribute Restoration07/25/2018
DOB NOWSidewalk ShedSigned-offEverest Scaffolding06/29/2018
DOB NOWSupported ScaffoldSigned-offTribute Restoration05/11/2018
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems04/10/2018
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems12/05/2017
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems11/09/2017
BISOTISSUEDTribute Restoration02/18/2021
BISOTISSUEDTribute Restoration02/18/2021
BISOTISSUEDExpress Renovations09/24/2020
BISOTISSUEDExpress Renovations09/17/2020
BISOTISSUEDSai Contracting04/02/2019
BISOTISSUEDSai Contracting03/29/2019
BISPLISSUEDTMS Plumbing & Heating02/20/2019
BISMHISSUEDRenovation by MY Home02/15/2019
+ 42 more permits on file
13 projects · most recent 07/13/2024
General Wiring
FiledStatusContractorScope
07/13/2024CompleteAttractive Lighting Electrical—
01/19/2024CompleteElpo Electrical ContgGeneral Wiring
01/10/2024CompleteElpo Electrical ContgGeneral Wiring
07/21/2023CompleteElpo Electrical Contg—
06/14/2023CompleteAttractive Lighting Electrical—
09/26/2022CompleteElpo Electrical Contg—
05/06/2021CompleteRichard Neu—
10/21/2019CompleteAcp Electrical Contracting—
02/18/2019CompleteGsa ElectricGeneral Wiring
08/03/2018CompleteL J Electrical Service—
06/27/2018CompleteBorowide Elect'l Contractors—
03/27/2018CompleteAcp Electrical Contracting—
12/18/2017CompleteAcp Electrical Contracting—
3 projects · most recent 10/20/2021
Sidewalk Shed
FiledStatusContractorScope
10/20/2021Permit IssuedZKW EnterprisesSidewalk Shed
05/06/2021Permit IssuedJ & G Construction ServicesSidewalk Shed
08/07/2018Permit IssuedYork RestorationSidewalk Shed
1 project · most recent 03/05/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
03/05/2026Permit IssuedTribute RestorationSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
07/25/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
07/19/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
07/09/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/09/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/25/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 41
DateRequirementInspectorRole
03/18/2026Alternative Materials - OTCR Buildings Bulletin NumberFRANCISCO PEREZspecial
05/14/2024MeteringJOHN MCMONAGLEenergy_progress
05/14/2024Fenestration and door U-factor and product ratingsJOHN MCMONAGLEenergy_progress
05/14/2024Lighting in dwelling unitsJOHN MCMONAGLEenergy_progress
05/14/2024Lighting controlsJOHN MCMONAGLEenergy_progress
05/14/2024Insulation placement and R valuesJOHN MCMONAGLEenergy_progress
05/14/2024Fenestration air leakageJOHN MCMONAGLEenergy_progress
05/14/2024Exterior lighting powerJOHN MCMONAGLEenergy_progress
05/14/2024Fenestration areasJOHN MCMONAGLEenergy_progress
05/14/2024Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
05/14/2024Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
05/14/2024FinalJOHN MCMONAGLEprogress
05/14/2024Fire-Resistance Rated ConstructionJOHN MCMONAGLEprogress
05/14/2024Permanent certificateJOHN MCMONAGLEenergy_progress
05/14/2024Interior lighting powerJOHN MCMONAGLEenergy_progress
05/14/2024Air barrier - visual inspectionJOHN MCMONAGLEenergy_progress
01/02/2024Insulation placement and R valuesJOHN MCMONAGLEenergy_progress
01/02/2024Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
01/02/2024Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
01/02/2024FinalJOHN MCMONAGLEprogress
01/02/2024Fire-Resistance Rated ConstructionJOHN MCMONAGLEprogress
01/02/2024Interior lighting powerJOHN MCMONAGLEenergy_progress
01/02/2024Lighting controlsJOHN MCMONAGLEenergy_progress
01/02/2024Lighting in dwelling unitsJOHN MCMONAGLEenergy_progress
01/02/2024Fenestration air leakageJOHN MCMONAGLEenergy_progress
Latest 25 of 41.
▾Documents — 529 on file (BIS + DOB NOW)
▸Plans & Drawings23
▸DOB NOWPlans/Sketch20
09/06/2026M00001956-I1Request digital key ↗
09/06/2026M00041024-I1Request digital key ↗
09/06/2026M00041024-P1Request digital key ↗
Showing 3 of 20 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/06/2026M00041024-I1Request digital key ↗
08/15/2026M00041024-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00389896-I1Request digital key ↗
▸Applications & Permits88
▸BISWORK PERMIT APPLICATION46
02/18/2021140977726Open ↗
02/18/2021140977735Open ↗
09/17/2020140952636Open ↗
Showing 3 of 46 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION42
08/11/2021101033365Open ↗
12/17/2020140977735Open ↗
12/17/2020140977726Open ↗
Showing 3 of 42 on file for this type
▸Seals & Professional Certifications118
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION50
01/27/2020123134330Open ↗
01/24/2020123134330Open ↗
01/24/2020123134330Open ↗
Showing 3 of 50 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature20
09/06/2026M00001956-I1Open ↗
09/04/2026M00389896-I1Open ↗
09/03/2026M00612593-I1Open ↗
Showing 3 of 20 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/02/2026M00713356-I1Open ↗
09/02/2026M00713356-I1Open ↗
09/01/2026M00041024-I1Open ↗
Showing 3 of 7 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
09/15/2020140952636Open ↗
04/27/2017140633893Open ↗
02/01/2017140599715Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
09/15/2020140952636Open ↗
04/27/2017140633893Open ↗
02/01/2017140599715Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026M00713356-I1Open ↗
08/28/2026M00713379-I1Open ↗
08/27/2026M00713356-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
04/27/2017140633893Open ↗
02/01/2017140599715Open ↗
01/24/2017140596816Open ↗
▸BISAPPLICANT OWNER SIGNATURE2
11/20/2020140977726Open ↗
11/20/2020140977735Open ↗
▸Trade Schedules & Equipment21
▸BISSCHEDULE B - PLUMBING8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISSELF-CERT PLUMBING NOTICE8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
02/12/2019123664739Open ↗
09/06/2017123134330Open ↗
Showing 2 of 3 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection52
▸DOB NOWHPD-2: Clinton Special District Anti-Harassment Checklist23
09/06/2026M00001956-I1Open ↗
09/06/2026M00041024-I1Open ↗
08/15/2026M00713374-I1Open ↗
Showing 3 of 23 on file for this type
▸BISTenant Protection Plan and Notes8
02/12/2019123664739Open ↗
01/10/2018123195229Open ↗
09/05/2017123134330Open ↗
Showing 3 of 8 on file for this type
▸BISHPD-2 - Clinton Special district Anti-Harassment Checklist7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISANTI-HARASSMENT CHECKLIST: CLINTON6
02/12/2019123664739Open ↗
01/10/2018123195229Open ↗
10/23/2017123134330Open ↗
Showing 3 of 6 on file for this type
▸BISCLINTON DISTRICT: ANTI-HARASSMENT CHECKLIST3
12/29/2020140977735Open ↗
12/29/2020140977726Open ↗
09/15/2020140952636Open ↗
▸BISTPP1: TENANT PROTECTION PLAN2
02/18/2021140977726Open ↗
02/18/2021140977735Open ↗
▸BISHPD-1 - Anti-Harassment Area Checklist1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISHPD: SRO MD CERTIFICATE OF NO HARASSMENT1
01/12/2017122875479Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00389896-I1Open ↗
▸Environmental & Asbestos35
▸BISASBESTOS: CERTIFICATION (DEP ACP5)15
12/29/2020140977735Open ↗
12/29/2020140977726Open ↗
11/20/2020140977726Open ↗
Showing 3 of 15 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
09/06/2026M00041024-I1Open ↗
09/04/2026M00389896-I1Open ↗
08/13/2026M00041024-P2Open ↗
Showing 3 of 5 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
08/15/2026M00713356-I1Open ↗
08/13/2026M00713374-I1Open ↗
08/13/2026M00730932-I1Open ↗
Showing 3 of 4 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISASBESTOS INSPECTION REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance35
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS12
01/13/2020123134330Open ↗
09/30/2019123664739Open ↗
02/27/2019123195229Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY8
12/07/2020140952636Open ↗
12/04/2020140952636Open ↗
12/04/2020140952636Open ↗
Showing 3 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
02/01/2021140952636Open ↗
01/24/2020123134330Open ↗
01/13/2020123134330Open ↗
Showing 3 of 8 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING2
04/27/2017140633893Open ↗
01/24/2017140596816Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
08/13/2026M00713356-I1Open ↗
08/13/2026M00713369-I1Open ↗
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
09/15/2020140952636Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports13
▸BISTECHNICAL REPORT: RESPONSIBILITY12
08/13/2021101033365Open ↗
08/13/2021101033365Open ↗
02/18/2021140977726Open ↗
Showing 3 of 12 on file for this type
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
02/01/2017140599715Open ↗
▸Approvals, Objections & Sign-offs37
▸BISADMINISTRATIVE OBJECTIONS17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST15
08/16/2021101033365Open ↗
02/01/2021140952636Open ↗
01/28/2020123134330Open ↗
Showing 3 of 15 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
09/15/2020140952636Open ↗
04/23/2018140633893Open ↗
Showing 2 of 4 on file for this type
▸BISSHED LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership42
▸BISCOST AFFIDAVIT38
02/01/2021140952636Open ↗
11/20/2020140977726Open ↗
11/20/2020140977735Open ↗
Showing 3 of 38 on file for this type
▸BISCIVIL PENALTY AFFADAVIT/REQUEST3
05/02/2017140633893Open ↗
02/08/2017140599715Open ↗
01/26/2017140596816Open ↗
▸BISLL58-88 CIVIL PENALTY AFFIDAVIT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Filing & Intake Forms51
▸BISEFILING COVER SHEET20
02/12/2019123664739Open ↗
01/10/2018123195229Open ↗
09/06/2017123134330Open ↗
Showing 3 of 20 on file for this type
▸BISADDITIONAL INFORMATION16
12/29/2020140977735Open ↗
12/29/2020140977726Open ↗
12/07/2020140952636Open ↗
Showing 3 of 16 on file for this type
▸BISBOROUGH INTAKE FORM9
01/28/2020123134330Open ↗
01/24/2020123134330Open ↗
01/13/2020123134330Open ↗
Showing 3 of 9 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET6
11/20/2020140977726Open ↗
11/20/2020140977735Open ↗
09/15/2020140952636Open ↗
Showing 3 of 6 on file for this type
▸Other Documents14
▸DOB NOWMultiple Dwelling Special District Notice to Community Board6
09/06/2026M00001956-I1Open ↗
09/06/2026M00041024-I1Open ↗
08/13/2026M00041024-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWMultiple Dwelling Special District Feasibility of Government Funded Rehabilitation6
09/06/2026M00001956-I1Open ↗
09/06/2026M00041024-I1Open ↗
08/13/2026M00068029-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWManufacturer's Specifications1
08/13/2026M01364442-I1Open ↗
▸DOB NOWCalculations1
08/13/2026M01364442-I1Open ↗