💬 Discuss this project
1920Year Built
2Stories
K2Building Class
C4-3AZoning
5,600 sfGross Floor Area
2Units
0 Active ViolationsFDNY Report ↗
Multi-story retail building (2+) · Owner of record: HWM Met/Marcy · 2,800 sf lot · 2 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire Protection
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofAbrams Holdings LLC10p · 3 filings · 20 docs
Floor 2Abrams Holdings LLC26p · 4 filings · 20 docs
Floor 1Webster Bank63p · 7 filings · 20 docs
CellarAbrams Holdings LLC26p · 4 filings · 20 docs
Site & exteriorWebster Bank2p · 2 filings · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Abrams Holding303/21/2026
Sterling National Bank103/22/2026
Store103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Tahir Demircioglu Architect310/05/2026
Concessi Engineering410/22/2024
BXP110/22/2024
Karacoban Engineering509/30/2024
Wexler Associates205/31/2024
HC Engineering211/01/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JP Expedite403/21/2026
Whidden Silver403/21/2026
K M DOB Consulting1803/21/2026
MPDC Design & Construction603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Whalen ConstructionGeneral Contractor707/08/2026
Signs CadSign hanger207/08/2026
Best Plumbing & HVACPlumbing207/08/2026
Best Plumbing HVACGeneral Contractor203/22/2026
Hydronic Concepts NY P&HPlumbing207/08/2026
Ashlar MechanicalFire Protection107/08/2026
Best Plumbing & HVACFire Protection107/08/2026
Best Plumbing HVACPlumbing103/22/2026
LND ElectricElectrical103/22/2026
LND ElectricElectrical103/21/2026
KSK Construction GroupGeneral Contractor107/08/2026
Corp Electrical TechnologiesElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Vibranalysis Inc., Dba VT68641010/05/2026
Concessi Engineering540310/22/2024
Building Lifecycle
All (92)Filed (17)Permit Issued (12)Signed Off (6)Violation (2)Inspection (9)Objection (16)Special Inspection (30)
10/05/2026
Filed — Alteration CO
DEMOLITION OF INTERIOR PARTITIONS, CREATION OF NEW MEANS OF EGRESS WITHIN AN EXISTING COMMERCIAL BUILDING WITH A CHANGE OF USE AND OCCUPANCY ON THE 2ND FLOOR. THIS APPLICATION IS TO OBTAIN A NEW CERTIFICATE OF OCCUPANCY.
B08007992-P2
10/05/2026
Special inspection requirement — Fire-Resistance Rated Construction
JUAN GOMEZ
10/05/2026
Special inspection requirement — Fenestration air leakage
JUAN GOMEZ
10/05/2026
Special inspection requirement — Fenestration areas
JUAN GOMEZ
10/05/2026
Special inspection requirement — Lighting controls
JUAN GOMEZ
10/05/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
JUAN GOMEZ
10/05/2026
Special inspection requirement — Exterior lighting power
JUAN GOMEZ
10/05/2026
Special inspection requirement — Maintenance information
JUAN GOMEZ
10/05/2026
Special inspection requirement — Energy Code Compliance Inspections
JUAN GOMEZ
10/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JUAN GOMEZ
10/05/2026
Special inspection requirement — Interior lighting power
JUAN GOMEZ
08/13/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/28/2025
Filed — Alteration CO
DEMOLITION OF INTERIOR PARTITIONS, CREATION OF NEW MEANS OF EGRESS WITHIN AN EXISTING COMMERCIAL BUILDING WITH A CHANGE OF USE AND OCCUPANCY ON THE 2ND FLOOR. THIS APPLICATION IS TO OBTAIN A NEW CERTIFICATE OF OCCUPANCY.
B08007992-P1
03/27/2025
Special inspection requirement — Exterior lighting power
JUAN GOMEZ
03/27/2025
Special inspection requirement — Fenestration air leakage
JUAN GOMEZ
03/27/2025
Special inspection requirement — Fenestration areas
JUAN GOMEZ
03/27/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
JUAN GOMEZ
03/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JUAN GOMEZ
03/27/2025
Special inspection requirement — Fire-Resistance Rated Construction
JUAN GOMEZ
03/27/2025
Special inspection requirement — Energy Code Compliance Inspections
JUAN GOMEZ
03/27/2025
Special inspection requirement — Maintenance information
JUAN GOMEZ
03/27/2025
Special inspection requirement — Lighting controls
JUAN GOMEZ
03/27/2025
Special inspection requirement — Interior lighting power
JUAN GOMEZ
02/12/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/30/2025
Signed off — Alteration
REMOVING FURNITURE PARTITIONS AND REPLACING THEM WITH FULL HEIGHT PARTITIONS AND GLASS WALL
B01099928-S1
01/13/2025
Signed off — Alteration
REMOVING FURNITURE PARTITIONS AND REPLACING THEM WITH FULL HEIGHT PARTITIONS AND GLASS WALL
B01099928-I1
01/13/2025
Permit issued — Sprinklers
B08015265-I1-EW-SP
11/21/2024
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
10/29/2024
Permit issued — General Construction
B01099928-I1-GC
10/29/2024
Permit issued — Mechanical Systems
B01099928-S1-MS
10/22/2024
Filed — Alteration
REMOVING FURNITURE PARTITIONS AND REPLACING THEM WITH FULL HEIGHT PARTITIONS AND GLASS WALL
B01099928-S1
10/22/2024
Filed — Alteration
REMOVING FURNITURE PARTITIONS AND REPLACING THEM WITH FULL HEIGHT PARTITIONS AND GLASS WALL
B01099928-I1
10/17/2024
Special inspection requirement — Maintenance information
JUAN GOMEZ
10/17/2024
Special inspection requirement — HVAC-R and service water heating equipment
JUAN GOMEZ
10/17/2024
Special inspection requirement — Shutoff dampers
JUAN GOMEZ
10/17/2024
Special inspection requirement — Energy Code Compliance Inspections
JUAN GOMEZ
10/17/2024
Special inspection requirement — Final
JUAN GOMEZ
10/17/2024
Special inspection requirement — Mechanical Systems
JUAN GOMEZ
10/17/2024
Special inspection requirement — HVAC-R and service water heating system controls
JUAN GOMEZ
10/17/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
JUAN GOMEZ
10/09/2024
Objection resolved — Addressed
10/01/2024
Special inspection requirement — Sprinkler Systems
JUAN GOMEZ
10/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JUAN GOMEZ
09/30/2024
Filed — Alteration
MODIFICATION AND INSTALLATION OF PLUMBING FIXTURES AND REMOVAL OF SPRINKLER HEADS WITH PIPES.
B08015265-P2
09/30/2024
Objection resolved — Addressed
08/23/2024
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
08/15/2024
Objection raised — Fire_Protection
08/15/2024
Objection raised — Mechanical
08/09/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/08/2024
Objection resolved — Addressed
08/07/2024
Objection raised — Scope
07/30/2024
Filed — Alteration
MODIFICATION AND INSTALLATION OF PLUMBING FIXTURES AND REMOVAL OF SPRINKLER HEADS WITH PIPES.
B08015265-P1
07/30/2024
Filed — Alteration
MODIFICATION OF EXISTING SUPPLY/ RETURN/ EXHAUST DUCTWORK, AND INSTALLATION OF HVAC ROOFTOP UNIT AND FANS.
B08015173-P1
07/25/2024
Permit issued — Plumbing
B08015265-I1-PL
07/09/2024
Permit issued — General Construction
B08007992-I1-GC
05/31/2024
Filed — Alteration
INSTALLATION OF NEW FOUNDATION FOR NEW STAIRS WITH POST, NEW FRAMING FOR STAIR OPENING, SKYLIGHTS, AND NEW LINTEL FOR EXTERIOR DOOR OPENING. AND INFILL AT EXISTING EXTERIOR WALL AND FLOOR OPENINGS.
B08054856-P1
03/04/2024
Filed — Alteration
INSTALLATION OF NEW FOUNDATION FOR NEW STAIRS WITH POST, NEW FRAMING FOR STAIR OPENING, SKYLIGHTS, AND NEW LINTEL FOR EXTERIOR DOOR OPENING. AND INFILL AT EXISTING EXTERIOR WALL AND FLOOR OPENINGS.
B08054856-I1
10/30/2023
Inspection — Pass-Final SP Permit Withdrawal
Pass
View inspection ↗
10/25/2023
Inspection — Fail-Final SP Permit Withdrawal
Fail
View inspection ↗
06/14/2023
Signed off — Alteration
B00777532-I1
Latest 60 of 92 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedBest Plumbing & HVAC01/13/2025
DOB NOWGeneral ConstructionSigned-offWhalen Construction10/29/2024
DOB NOWMechanical SystemsSigned-offWhalen Construction10/29/2024
DOB NOWPlumbingPermit IssuedBest Plumbing & HVAC07/25/2024
DOB NOWGeneral ConstructionPermit IssuedKSK Construction Group07/09/2024
DOB NOWPlumbingSigned-offHydronic Concepts NY P&H01/10/2023
DOB NOWSprinklersPermit IssuedAshlar Mechanical11/09/2022
DOB NOWPlumbingSigned-offHydronic Concepts NY P&H10/28/2022
DOB NOWGeneral ConstructionSigned-offWhalen Construction09/29/2022
DOB NOWMechanical SystemsSigned-offWhalen Construction09/29/2022
DOB NOWSignSigned-offSigns Cad11/03/2021
DOB NOWSignSigned-offSigns Cad11/01/2021
BISMHISSUEDLMV Consulting Engineering02/23/2006
BISMHISSUEDSuburban Builders of Westchester03/25/2004
BISOTISSUEDSuburban Builders of Westchester03/25/2004
BISPLISSUEDWilliam C. Gerakaris P&H07/29/2003
BISMHISSUEDTown Sports International07/08/2003
BISOTISSUEDTown Sports International07/08/2003
BISSPISSUEDAdvanced Plumbing, Mechanical & Sprinkler06/11/2003
BISPLISSUEDAdvanced Plumbing Mechanical03/19/2003
BISMHISSUEDTown Sports International01/10/2003
BISOTISSUEDTown Sports International01/10/2003
BISEQISSUEDSeasons Contracting10/21/2002
BIS—ISSUEDC Ramimomdo & Sons08/05/2002
BISSPISSUEDNyco Plumbing & Heating06/13/2002
BISEQISSUEDJGN Construction02/14/2002
BISOTISSUEDJGN Construction01/29/2002
BISOTISSUEDJGN Construction01/29/2002
BISMHISSUEDJGN Construction01/29/2002
BIS—ISSUEDC Ramimomdo & Sons08/17/2001
BIS—ISSUEDC Ramimomdo & Sons Construction04/23/2001
1 project · most recent 07/30/2024
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/30/2024——Heating and Air Conditioning Systems
Heat / Cool
Allied ZGC120S4M 180,000 BTU · Rooftop Unit ×1
2 projects · most recent 09/30/2024
FiledStatusContractorScope
09/30/2024Permit IssuedBest Plumbing & HVAC6 heads
09/22/2022Permit IssuedAshlar Mechanical8 heads
1 project · most recent 09/30/2024
Gas Water/Sanitary
FiledStatusContractorScope
09/30/2024Permit IssuedBest Plumbing & HVACGas, Water/Sanitary
6 projects · most recent 04/01/2025
General Wiring
FiledStatusContractorScope
04/01/2025Permit IssuedLND ElectricGeneral Wiring
12/08/2023Permit IssuedSRM Electrical Service—
01/19/2023CompleteH. & L. ElectricGeneral Wiring
12/13/2021CompleteSigns Cad—
12/13/2021CompleteSigns Cad—
07/26/2020CompleteCorp Electrical TechnologiesGeneral Wiring
1 project · most recent 05/31/2024
Steel Concrete Masonry
FiledStatusContractorScope
05/31/2024——Steel, Concrete, Masonry
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
08/13/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/12/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/21/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
08/23/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
08/09/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/30/2023Pass-Final SP Permit WithdrawalPassView ↗
10/25/2023Fail-Final SP Permit WithdrawalFailView ↗
02/14/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/13/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 71
DateRequirementInspectorRole
10/05/2026Lighting controlsJUAN GOMEZenergy_progress
10/05/2026Fenestration and door U-factor and product ratingsJUAN GOMEZenergy_progress
10/05/2026Exterior lighting powerJUAN GOMEZenergy_progress
10/05/2026Interior lighting powerJUAN GOMEZenergy_progress
10/05/2026Fire-Resistance Rated ConstructionJUAN GOMEZprogress
10/05/2026Fenestration areasJUAN GOMEZenergy_progress
10/05/2026Fire-Resistant Penetrations and JointsJUAN GOMEZspecial
10/05/2026Energy Code Compliance InspectionsJUAN GOMEZprogress
10/05/2026Maintenance informationJUAN GOMEZenergy_progress
10/05/2026Fenestration air leakageJUAN GOMEZenergy_progress
03/27/2025Fenestration areasJUAN GOMEZenergy_progress
03/27/2025Fenestration air leakageJUAN GOMEZenergy_progress
03/27/2025Exterior lighting powerJUAN GOMEZenergy_progress
03/27/2025Interior lighting powerJUAN GOMEZenergy_progress
03/27/2025Lighting controlsJUAN GOMEZenergy_progress
03/27/2025Maintenance informationJUAN GOMEZenergy_progress
03/27/2025Fire-Resistant Penetrations and JointsJUAN GOMEZspecial
03/27/2025Energy Code Compliance InspectionsJUAN GOMEZprogress
03/27/2025Fire-Resistance Rated ConstructionJUAN GOMEZprogress
03/27/2025Fenestration and door U-factor and product ratingsJUAN GOMEZenergy_progress
10/17/2024Shutoff dampersJUAN GOMEZenergy_progress
10/17/2024Maintenance informationJUAN GOMEZenergy_progress
10/17/2024HVAC-R and service water heating system controlsJUAN GOMEZenergy_progress
10/17/2024HVAC-R and service water piping design and insulationJUAN GOMEZenergy_progress
10/17/2024Mechanical SystemsJUAN GOMEZspecial
Latest 25 of 71.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Webster BankBank / Financial branchFloor 1
Project B01099928 Alteration · LOC Issued · 10/22/2024
Project B00777532 Alteration · LOC Issued · 09/22/2022
Project B00777554 Alteration · LOC Issued · 09/22/2022
Project B00777564 Alteration · Filing Withdrawn · 09/22/2022
Project B00602120 Alteration · LOC Issued · 11/01/2021
Project B00602136 Alteration · LOC Issued · 11/01/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 94 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch16
08/31/2026B00602120-I1Request digital key ↗
08/31/2026B00602136-I1Request digital key ↗
08/28/2026B00777532-I1Request digital key ↗
Showing 3 of 16 on file for this type
▸Seals & Professional Certifications53
▸DOB NOWSpecial Inspector Seal & Signature19
10/06/2026B08007992-P2Open ↗
09/27/2026B08007992-P1Open ↗
08/31/2026B08015173-I1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWProgress Inspector Seal & Signature18
10/06/2026B08007992-P2Open ↗
10/06/2026B08007992-P2Open ↗
10/06/2026B08007992-P2Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/31/2026B00602120-I1Open ↗
08/31/2026B00602136-I1Open ↗
08/28/2026B00777532-I1Open ↗
Showing 3 of 16 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/13/2026B08007992-P1Open ↗
08/13/2026B08007992-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B08007992-I1Open ↗
▸Environmental & Asbestos16
▸DOB NOWDEP ACP-5: Asbestos Assessment Report16
08/31/2026B00602120-I1Open ↗
08/31/2026B00602136-I1Open ↗
08/28/2026B00777532-I1Open ↗
Showing 3 of 16 on file for this type
▸Inspections & Test Reports3
▸DOB NOWSOIL REPORT2
08/13/2026B08054856-I1Open ↗
08/13/2026B08054856-P1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B08054856-I1Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification2
08/13/2026B08007992-P1Open ↗
08/13/2026B08007992-I1Open ↗
▸DOB NOWWaiver Document1
08/13/2026B00777564-I1Open ↗