← Back
BuildNYC
Office, 20+ stories, with or without commercial
463 7TH AVENUE
MANHATTAN · BIN 1015222
💬 Discuss this project
1925Year Built
22Stories
O4Building Class
M1-9A/R12Zoning
408,511 sfGross Floor Area
88Units
LL97 Covered1 Active Violation 1 old, status unconfirmed ▸FISP: SAFE
Office, 20+ stories, with or without commercial · Owner of record: Arsenal Company · 19,750 sf lot · 20.68 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofJust Salad4p · 4 filings · 20 docs
Floor 11Adjmi - C.C. / J.T.R.63p · 7 filings · 20 docs
Floor 10Adams Company21p · 4 filings · 18 docs
Floor 9Inmocean29p · 3 filings · 20 docs
Floor 8Inmocean31p · 4 filings · 20 docs
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1Just SaladUnder Construction47p · 9 filings · 20 docs
MezzanineJust Salad28p · 3 filings · 20 docs
CellarJust Salad1p · 1 filing · 4 docs
Site & exteriorExterior restoration13p · 3 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Adams & Co. Real Estate26903/21/2026
Arsenal12903/22/2026
Adams & Company6203/22/2026
Adams Realty803/22/2026
Office103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Archetype Consultants5203/21/2026
Hierarch-E803/21/2026
JP Expedite603/21/2026
Mbe Code Zoning603/21/2026
Municipal Building Consultants203/21/2026
Millennium Designs of New York103/21/2026
A1 Expediting Service203/21/2026
Design Group in H K203/21/2026
Millennium Designs103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
National WallScaffold1007/08/2026
National WallGeneral Contractor907/08/2026
Moskowitz StuartElectrical703/21/2026
Matros Automated ElectricalElectrical703/21/2026
Pofi ConstructionGeneral Contractor407/08/2026
Noah Office RenovationGeneral Contractor407/08/2026
Matros Automated ElectricalElectrical303/22/2026
Bura ConstructionGeneral Contractor307/08/2026
Idk CoolingGeneral Contractor307/08/2026
The Manlyn Development GroupGeneral Contractor307/08/2026
BS GroupScaffold303/21/2026
Rockledge ScaffoldScaffold307/08/2026
Signs CadSign hanger307/08/2026
Plumbing P & HPlumbing207/08/2026
Centennial Elevator IndustriesElectrical203/21/2026
Skyline Fire Sprinkler CoFire Protection207/08/2026
George Breslaw PlumbingPlumbing207/08/2026
Fresh Aire Mechanicalspecialty_contractor203/21/2026
Y.S. ElectricElectrical103/21/2026
Metro Fire ProtectionFire Protection106/28/2026
Bellis ConstructionGeneral Contractor107/08/2026
VMC Plumbing & HeatingPlumbing107/08/2026
Ashlar MechanicalFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Alan D Marcus, PE1761703/04/2026
Jack Green Associates422702/28/2025
George J. Xerakias, PE1658311/11/2024
Paradigm Architecture5931203/05/2024
Asda Architecture + Desig2015307/27/2022
Special Testing & Consulting1688206/22/2022
Design Group in H&K1363109/28/2021
Building Lifecycle
All (237)Filed (41)Permit Issued (44)Signed Off (27)Facade (FISP) (15)Violation (60)Inspection (10)Objection (10)Special Inspection (30)
07/21/2026
Violation issued (ECB, closed)
Construction
03/12/2026
Signed off — Alteration
Mechanical work on the 10th floor (bathrooms) as indicated on drawings.
M01090075-I1
03/04/2026
Filed — Alteration
Mechanical work on the 10th floor (bathrooms) as indicated on drawings.
M01090075-P1
02/19/2026
Permit issued — General Construction
M00611345-I1-GC
09/29/2025
Signed off — Alteration
M01089948-I1
09/09/2025
Signed off — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00927484-I1
08/15/2025
Signed off — Alteration
Plumbing work on the 10th floor (bathrooms) as indicated on drawings.
M01090084-I1
07/25/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/27/2025
Cycle 9 facade report signed — SAFE
06/03/2025
Cycle 9 facade report submitted
05/29/2025
Signed off — Alteration
Exterior repairs consisting of sealant Application, Railing installation, masonry joint repointing, brick replacement and stone patching as per plans filed herewith. No change to use, egress or occupancy.
M00932295-I1
05/27/2025
Cycle 9 facade inspection completed
05/22/2025
Signed off — Alteration
Suspended scaffold installation and use as per plans filed herewith.
M01014499-I1
05/16/2025
Permit issued — Suspended Scaffold
M01014499-I1-SC
04/22/2025
Permit issued — General Construction
M00932295-I1-GC
03/21/2025
Permit issued — General Construction
M00611345-I1-GC
03/06/2025
Permit issued — Sprinklers
M01187712-I1-EW-SP
03/04/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/28/2025
Filed — Alteration
Sprinkler work on the 10th floor (bathrooms) as indicated on drawings.
M01187712-I1
02/27/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/19/2025
Signed off — Alteration
Suspended scaffold installation and use as per plans filed herewith.
M00970221-I1
02/18/2025
Permit issued — General Construction
M01089948-I1-GC
02/13/2025
Permit issued — Plumbing
M01090084-I1-PL
01/23/2025
Permit issued — Suspended Scaffold
M00970221-I1-SC
01/21/2025
Objection resolved — Addressed
11/26/2024
Permit issued — Mechanical Systems
M01090075-I1-MS
11/20/2024
Permit issued — General Construction
M01089948-I1-GC
11/15/2024
Filed — Alteration
Mechanical work on the 10th floor (bathrooms) as indicated on drawings.
M01090075-I1
11/15/2024
Filed — Alteration
Plumbing work on the 10th floor (bathrooms) as indicated on drawings.
M01090084-I1
11/12/2024
Filed — Alteration
M01089948-I1
11/12/2024
Special inspection requirement — Post-installed Anchors
George Xerakias
11/11/2024
Filed — Alteration
Suspended scaffold installation and use as per plans filed herewith.
M01014499-P2
10/22/2024
Special inspection requirement — Post-installed Anchors
George Xerakias
10/21/2024
Objection raised — Other
10/21/2024
Objection resolved — Addressed
10/21/2024
Objection raised — Admin
10/10/2024
Filed — Alteration
Suspended scaffold installation and use as per plans filed herewith.
M00970221-I1
09/12/2024
Permit issued — Sidewalk Shed
M00927484-I1-SH
08/01/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alan Marcus
08/01/2024
Special inspection requirement — Final
Alan Marcus
05/20/2024
Violation issued (ECB, closed)
Construction
05/20/2024
Violation issued (ECB, closed)
Construction
05/20/2024
Violation issued (ECB, closed)
Construction
05/16/2024
Signed off — Alteration
REPLACE FACE OF EXISTING ILLUMINATED ACCESSORY CABINET WALL SIGN, #104189334-SG, NO CHANGE TO USE, EGRESS OR OCCUPATION
M01021075-I1
05/07/2024
Permit issued — General Construction
M00932295-I1-GC
04/29/2024
Filed — Alteration
Suspended scaffold installation and use as per plans filed herewith.
M01014499-P1
04/17/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/05/2024
Filed — Alteration
REPLACE FACE OF EXISTING ILLUMINATED ACCESSORY CABINET WALL SIGN, #104189334-SG, NO CHANGE TO USE, EGRESS OR OCCUPATION
M01021075-I1
04/05/2024
Permit issued — Sign
M01021075-I1-SG
03/29/2024
Permit issued — General Construction
M00611345-I1-GC
03/15/2024
Special inspection requirement — Final
ADITYA DESAI
03/11/2024
Permit issued — Suspended Scaffold
M01014499-I1-SC
03/08/2024
Filed — Alteration
Suspended scaffold installation and use as per plans filed herewith.
M01014499-I1
03/05/2024
Filed — Alteration
Exterior repairs consisting of sealant Application, Railing installation, masonry joint repointing, brick replacement and stone patching as per plans filed herewith. No change to use, egress or occupancy.
M00932295-P1
03/04/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Anthony Addesso
03/04/2024
Special inspection requirement — Energy Code Compliance Inspections
Anthony Addesso
03/04/2024
Special inspection requirement — Masonry
Anthony Addesso
03/04/2024
Special inspection requirement — Air barrier - visual inspection
Anthony Addesso
03/04/2024
Special inspection requirement — Final
Anthony Addesso
Latest 60 of 237 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedNational Wall02/19/2026
DOB NOWSuspended ScaffoldSigned-offC.C.C. Renovation05/16/2025
DOB NOWGeneral ConstructionSigned-offPofi Construction04/22/2025
DOB NOWGeneral ConstructionPermit IssuedNational Wall03/21/2025
DOB NOWSprinklersPermit IssuedMetro Fire Protection03/06/2025
DOB NOWGeneral ConstructionSigned-offBura Construction02/18/2025
DOB NOWPlumbingSigned-offGeorge Breslaw Plumbing02/13/2025
DOB NOWSuspended ScaffoldSigned-offPofi Construction01/23/2025
DOB NOWMechanical SystemsSigned-offIdk Cooling11/26/2024
DOB NOWGeneral ConstructionSigned-offBura Construction11/20/2024
DOB NOWSidewalk ShedSigned-offRockledge Scaffold09/12/2024
DOB NOWGeneral ConstructionSigned-offPofi Construction05/07/2024
DOB NOWSignSigned-offSigns Cad04/05/2024
DOB NOWGeneral ConstructionPermit IssuedNational Wall03/29/2024
DOB NOWSuspended ScaffoldSigned-offC.C.C. Renovation03/11/2024
DOB NOWGeneral ConstructionSigned-offPofi Construction02/28/2024
DOB NOWSidewalk ShedSigned-offRockledge Scaffold09/12/2023
DOB NOWGeneral ConstructionPermit IssuedNational Wall02/09/2023
DOB NOWSignSigned-offSigns Cad08/31/2022
DOB NOWSignSigned-offSigns Cad08/31/2022
DOB NOWMechanical SystemsSigned-offThe Manlyn Development GR07/03/2022
DOB NOWGeneral ConstructionSigned-offThe Manlyn Development GR07/03/2022
DOB NOWPlumbingSigned-offM. Spinelli PLB & Heating06/28/2022
DOB NOWSprinklersSigned-offSkyline Fire Sprinkler Co04/15/2022
DOB NOWGeneral ConstructionPermit IssuedNational Wall03/15/2022
DOB NOWPlumbingSigned-offGeorge Breslaw Plumbing12/01/2021
DOB NOWMechanical SystemsSigned-offIdk Cooling10/16/2021
DOB NOWSprinklersSigned-offSkyline Fire Sprinkler Co10/12/2021
DOB NOWGeneral ConstructionSigned-offBura Construction10/06/2021
DOB NOWMechanical SystemsSigned-offFresh Aire Mechanical10/05/2021
DOB NOWConstruction FenceSigned-offNational Wall04/27/2021
DOB NOWGeneral ConstructionSigned-offNoah Office Renovation04/22/2021
DOB NOWPlumbingSigned-offPlumbing P & H04/21/2021
DOB NOWSprinklersSigned-offAshlar Mechanical04/21/2021
DOB NOWMechanical SystemsSigned-offNoah Office Renovation04/21/2021
DOB NOWGeneral ConstructionSigned-offBellis Construction04/16/2021
DOB NOWPlumbingSigned-offPlumbing P & H04/02/2021
DOB NOWMechanical SystemsSigned-offIdk Cooling03/24/2021
DOB NOWConstruction FenceSigned-offNational Wall03/05/2020
DOB NOWConstruction FenceSigned-offNational Wall11/12/2019
+ 54 more permits on file
18 projects · most recent 07/21/2026
General Wiring Lighting
FiledStatusContractorScope
07/21/2026Permit IssuedMatros Automated ElectricalGeneral Wiring
02/19/2026CompleteMatros Automated Electrical—
03/26/2025CompleteMatros Automated Electrical—
04/24/2024CompleteMatros Automated Electrical—
04/22/2024CompleteAnthony G Ferry—
12/08/2022CompleteMatros Automated Electrical—
10/03/2022CompleteJanon ElectricGeneral Wiring
07/06/2022CompleteMatros Automated ElectricalGeneral Wiring
04/07/2021CompleteDelta Power ElectricalGeneral Wiring
03/26/2021CompleteMatros Automated ElectricalGeneral Wiring
01/15/2020CompleteMatros Automated ElectricalGeneral Wiring
05/06/2019CompleteCedar Electrical ContractorsGeneral Wiring
03/12/2019CompleteMatros Automated Electrical1 meters, 1 new_meters
09/24/2018Permit IssuedY.S. ElectricGeneral Wiring, Lighting
05/02/2018CompleteHeso ElectricalGeneral Wiring
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
07/25/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/04/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/27/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/29/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/26/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/14/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/11/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/17/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/17/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/08/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 77
DateRequirementInspectorRole
11/12/2024Post-installed AnchorsGeorge Xerakiasspecial
10/22/2024Post-installed AnchorsGeorge Xerakiasspecial
08/01/2024FinalAlan Marcusprogress
08/01/2024Fire-Resistant Penetrations and JointsAlan Marcusspecial
03/15/2024FinalADITYA DESAIprogress
03/04/2024FinalAnthony Addessoprogress
03/04/2024Air barrier - visual inspectionAnthony Addessoenergy_progress
03/04/2024MasonryAnthony Addessospecial
03/04/2024Post-installed AnchorsAnthony Addessospecial
03/04/2024Structural Stability – Alterations of existing buildingsAnthony Addessospecial
03/04/2024Energy Code Compliance InspectionsAnthony Addessoprogress
05/23/2023Sprinkler SystemsJACK GREENspecial
03/15/2023Sprinkler SystemsJACK GREENspecial
04/14/2022FinalHackjong Choiprogress
03/28/2022FinalAlfonso DEliaprogress
03/28/2022Interior lighting powerAlfonso DEliaenergy_progress
03/28/2022Fire-Resistant Penetrations and JointsAlfonso DEliaspecial
03/28/2022Energy Code Compliance InspectionsAlfonso DEliaprogress
03/28/2022Lighting controlsAlfonso DEliaenergy_progress
03/17/2022HVAC-R and service water heating system controlsJACK GREENenergy_progress
03/17/2022Energy Code Compliance InspectionsJACK GREENprogress
03/17/2022Mechanical SystemsJACK GREENspecial
03/17/2022FinalJACK GREENprogress
03/17/2022Maintenance informationJACK GREENenergy_progress
03/17/2022HVAC-R and service water piping design and insulationJACK GREENenergy_progress
Latest 25 of 77.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Adams CompanyOfficeFloor 10
Project M01090075 Alteration · LOC Issued · 11/15/2024
Project M01090084 Alteration · LOC Issued · 11/15/2024
Project M01089948 Alteration · LOC Issued · 11/12/2024
Just SaladRestaurant / Food ServiceFloor 1, Mezzanine
Project M00719521 Alteration · LOC Issued · 08/31/2022
Project M00719525 Alteration · LOC Issued · 08/31/2022
Project M00663330 Alteration · LOC Issued · 06/22/2022
Project M00663344 Alteration · LOC Issued · 06/22/2022
Project M00663350 Alteration · LOC Issued · 06/22/2022
InmoceanOfficeFloors 8, 9
Project M00583816 Alteration · LOC Issued · 10/08/2021
Project M00583801 Alteration · LOC Issued · 10/04/2021
Project M00583842 Alteration · LOC Issued · 09/24/2021
Project M00583848 Alteration · LOC Issued · 09/24/2021
Adjmi - C.C. / J.T.ROfficeFloor 11
Project M00471119 Alteration · LOC Issued · 04/16/2021
Project M00471297 Alteration · LOC Issued · 04/16/2021
Project M00471104 Alteration · LOC Issued · 04/15/2021
Project M00471139 Alteration · LOC Issued · 04/15/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 2,182 on file (BIS + DOB NOW)
▸Plans & Drawings42
▸DOB NOWPlans/Sketch28
09/06/2026M00046976-I1Request digital key ↗
09/03/2026M00583848-P1Request digital key ↗
09/03/2026M00583848-I1Request digital key ↗
Showing 3 of 28 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems4
09/04/2026M00452657-P1Request digital key ↗
09/04/2026M00452657-I1Request digital key ↗
09/03/2026M00471104-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Plumbing4
09/04/2026M00452687-I1Request digital key ↗
09/04/2026M00452687-P1Request digital key ↗
09/03/2026M00471119-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - General Construction2
09/04/2026M00452567-I1Request digital key ↗
09/03/2026M00471297-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
09/03/2026M00471139-P1Request digital key ↗
09/01/2026M00471139-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence2
09/02/2026M00002537-P1Request digital key ↗
09/02/2026M00002537-I1Request digital key ↗
▸Applications & Permits422
▸BISPLAN / WORK APPROVAL APPLICATION264
01/23/2026122935477Open ↗
01/07/2026104342962Open ↗
10/31/2025104602486Open ↗
Showing 3 of 264 on file for this type
▸BISWORK PERMIT APPLICATION156
02/27/2023123704492Open ↗
02/17/2023123704492Open ↗
02/07/2023123704492Open ↗
Showing 3 of 156 on file for this type
▸DOB NOWHPD Certification Letter or CPC Special Permit2
08/13/2026M00932295-P1Open ↗
08/13/2026M00932295-I1Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISZRD1-Zoning Resolution Determination1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications534
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION258
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 258 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT81
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 81 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST74
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 74 on file for this type
▸DOB NOWProgress Inspector Seal & Signature50
09/29/2026M00663344-I1Open ↗
09/29/2026M00663344-I1Open ↗
09/02/2026M00719521-I1Open ↗
Showing 3 of 50 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature40
09/06/2026M00046976-I1Open ↗
09/04/2026M00452657-I1Open ↗
09/04/2026M00452687-P1Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature17
09/29/2026M00663344-I1Open ↗
09/01/2026M00663330-I1Open ↗
09/01/2026M00471139-P1Open ↗
Showing 3 of 17 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment166
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE78
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 78 on file for this type
▸BISEQUIPMENT USE PERMITS33
06/26/2024123407134Open ↗
06/12/2024123068072Open ↗
06/10/2024123068072Open ↗
Showing 3 of 33 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT23
06/26/2024123407134Open ↗
06/12/2024123068072Open ↗
06/10/2024123068072Open ↗
Showing 3 of 23 on file for this type
▸BISSCHEDULE B - PLUMBING9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISSELF-CERT PLUMBING NOTICE8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT3
05/15/2024123068072Open ↗
09/25/2023123407134Open ↗
Showing 2 of 3 on file for this type
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS3
05/15/2024123068072Open ↗
09/25/2023123407134Open ↗
08/04/2022123718860Open ↗
▸BISSPRINKLER SYSTEMS2
12/19/2022123704492Open ↗
10/28/2022122693228Open ↗
▸Safety & Tenant Protection32
▸DOB NOWHPD-1: Anti-Harassment Area Checklist22
09/04/2026M00452657-I1Open ↗
09/04/2026M00452687-P1Open ↗
09/04/2026M00452687-I1Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWCertificate of No Harassment10
09/04/2026M00452657-I1Open ↗
08/13/2026M00611345-I1Open ↗
Showing 2 of 10 on file for this type
▸Environmental & Asbestos144
▸BISASBESTOS: CERTIFICATION (DEP ACP5)93
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 93 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report30
09/06/2026M00046976-I1Open ↗
09/04/2026M00452657-I1Open ↗
09/04/2026M00452687-P1Open ↗
Showing 3 of 30 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance170
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS91
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 91 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS27
06/10/2024123068072Open ↗
Showing 1 of 27 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY11
10/22/2025123071772Open ↗
10/22/2025123071772Open ↗
10/16/2025122995349Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.9
09/03/2026M00583039-I1Open ↗
09/03/2026M00583816-I1Open ↗
09/02/2026M00663344-I1Open ↗
Showing 3 of 9 on file for this type
▸BISLIGHTING CONTROLS5
10/22/2025123071772Open ↗
10/16/2025122995349Open ↗
05/15/2024123068072Open ↗
Showing 3 of 5 on file for this type
▸BISINTERIOR LIGHTING POWER5
10/22/2025123071772Open ↗
10/16/2025122995349Open ↗
05/15/2024123068072Open ↗
Showing 3 of 5 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS5
10/22/2025123071772Open ↗
10/22/2025123071772Open ↗
05/15/2024123068072Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)5
10/22/2025123071772Open ↗
10/16/2025122995349Open ↗
05/15/2024123068072Open ↗
Showing 3 of 5 on file for this type
▸BIS* HVAC INSULATION AND SEALING3
05/15/2024123068072Open ↗
09/25/2023123407134Open ↗
Showing 2 of 3 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISELECTRIC MOTORS2
05/15/2024123068072Open ↗
09/25/2023123407134Open ↗
▸Inspections & Test Reports62
▸BISTECHNICAL REPORT: RESPONSIBILITY48
02/26/2026104342962Open ↗
02/25/2026104342962Open ↗
02/24/2026104342962Open ↗
Showing 3 of 48 on file for this type
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19758
02/24/2026104342962Open ↗
11/20/2025104602486Open ↗
11/20/2025102643766Open ↗
Showing 3 of 8 on file for this type
▸BISMECHANICAL SYSTEMS3
10/22/2025123071772Open ↗
05/15/2024123068072Open ↗
09/25/2023123407134Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)3
05/15/2024123068072Open ↗
09/25/2023123407134Open ↗
08/04/2022123718860Open ↗
▸Approvals, Objections & Sign-offs134
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST72
02/26/2026104342962Open ↗
11/21/2025102643766Open ↗
11/21/2025104602486Open ↗
Showing 3 of 72 on file for this type
▸BISADMINISTRATIVE OBJECTIONS17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION12
07/10/2023103860181Open ↗
Showing 1 of 12 on file for this type
▸BISSUPERSEDING LETTER8
02/26/2026104342962Open ↗
10/16/2025102820903Open ↗
10/16/2025102981631Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWTransit Authority Approval8
09/02/2026M00002537-I1Open ↗
09/02/2026M00663344-I1Open ↗
09/02/2026M00663330-I1Open ↗
Showing 3 of 8 on file for this type
▸BISFINAL7
10/22/2025123071772Open ↗
10/16/2025122995349Open ↗
05/15/2024123068072Open ↗
Showing 3 of 7 on file for this type
▸BISTRANSIT AUTHORITY/MTA/PANYNJ APPROVAL4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
03/12/2025122935477Open ↗
12/11/2024122935477Open ↗
Showing 2 of 3 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Cost, Insurance & Ownership201
▸BISCOST AFFIDAVIT190
10/16/2025102820903Open ↗
10/16/2025102981631Open ↗
07/17/2025103704378Open ↗
Showing 3 of 190 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW311
02/24/2026104342962Open ↗
11/20/2025104602486Open ↗
11/20/2025102643766Open ↗
Showing 3 of 11 on file for this type
▸Filing & Intake Forms233
▸BISEFILING COVER SHEET123
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 123 on file for this type
▸BISADDITIONAL INFORMATION61
03/12/2025122935477Open ↗
10/03/2022123407134Open ↗
Showing 2 of 61 on file for this type
▸BISBOROUGH INTAKE FORM47
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 47 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Other Documents20
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸DOB NOWManufacturer's Specifications4
08/13/2026M01014499-I1Open ↗
08/13/2026M01014499-P1Open ↗
08/13/2026M01014499-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWCalculations4
08/13/2026M01014499-P1Open ↗
08/13/2026M01014499-P2Open ↗
08/13/2026M00970221-I1Open ↗
Showing 3 of 4 on file for this type
▸BISMAINTENANCE INFORMATION3
05/15/2024123068072Open ↗
09/25/2023123407134Open ↗
08/04/2022123718860Open ↗
▸BISPERMANENT CERTIFICATE1
08/04/2022123718860Open ↗