| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/17/2025 | $1.7M | — | CATHERINE COLLINS TRUST → Private party | $582/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LAM ENGINEER PC | 5 | 12/03/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LXC CONSTRUCTION INC | General Contractor | 1 | 04/09/2026 |
| S & L PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LAM ENGINEER PC | 1180 | 5 | 12/03/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | S & L PLUMBING INC | 08/01/2025 |
| DOB NOW | General Construction | Signed-off | LXC CONSTRUCTION INC | 07/07/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2025 | Complete | HI-RITE ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/26/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/02/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 09/26/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/24/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/05/2025 | Fire-Resistant Penetrations and Joints | YUK LAM | special |
| 12/05/2025 | Structural Stability – Alterations of existing buildings | YUK LAM | special |
| 12/05/2025 | Maintenance information | YUK LAM | energy_progress |
| 12/05/2025 | Air barrier - visual inspection | YUK LAM | energy_progress |
| 12/05/2025 | Fenestration areas | YUK LAM | energy_progress |
| 12/05/2025 | Concrete - Cast-In-Place | YUK LAM | special |
| 12/05/2025 | Excavations - Sheeting, Shoring, and Bracing | YUK LAM | special |
| 12/05/2025 | Energy Code Compliance Inspections | YUK LAM | progress |
| 12/05/2025 | Fire-Resistance Rated Construction | YUK LAM | progress |
| 12/05/2025 | Final | YUK LAM | progress |
| 12/05/2025 | Fenestration and door U-factor and product ratings | YUK LAM | energy_progress |
| 12/05/2025 | Fenestration air leakage | YUK LAM | energy_progress |
| 12/05/2025 | Permanent certificate | YUK LAM | energy_progress |
| 12/05/2025 | Interior lighting power | YUK LAM | energy_progress |
| 12/02/2025 | Fire-Resistance Rated Construction | YUK LAM | progress |
| 12/02/2025 | Concrete - Cast-In-Place | YUK LAM | special |
| 12/02/2025 | Excavations - Sheeting, Shoring, and Bracing | YUK LAM | special |
| 12/02/2025 | Fire-Resistant Penetrations and Joints | YUK LAM | special |
| 12/02/2025 | Structural Stability – Alterations of existing buildings | YUK LAM | special |
| 12/02/2025 | Energy Code Compliance Inspections | YUK LAM | progress |
| 12/02/2025 | Final | YUK LAM | progress |
| 12/02/2025 | Air barrier - visual inspection | YUK LAM | energy_progress |
| 12/02/2025 | Fenestration air leakage | YUK LAM | energy_progress |
| 12/02/2025 | Fenestration areas | YUK LAM | energy_progress |
| 12/02/2025 | Fenestration and door U-factor and product ratings | YUK LAM | energy_progress |