1915Year Built
2Stories
A1Building Class
R2Zoning
1,344 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 4,000 sf lot · 0.34 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralCivilGeneral
Floor 27p · 1 filing · 20 docs
Floor 15p · 1 filing · 20 docs
Cellar2p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/29/2020$800K—— → —$595/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Alan Yang Architecture DPC603/24/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PROTON CCM LLCGeneral Contractor1107/08/2026
AMERICAN STANDARD P&H CORORP.Plumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ALAN YANG ARCHITECTURE9490203/24/2025
CG CONSULTING ENGINEERING8226206/10/2024
Building Lifecycle
All (36)Filed (6)Permit Issued (6)Signed Off (3)Inspection (6)Special Inspection (15)
05/21/2026
Signed off — Alteration
Adding two bathrooms
Q01051937-S2
05/21/2026
Signed off — Alteration
Adding two bathrooms
Q01051937-S4
05/14/2026
Signed off — Alteration
Adding two bathrooms
Q01051937-I1
04/15/2026
Permit issued — General Construction
Q01051937-I1-GC
04/15/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/09/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/09/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/04/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/04/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/20/2025
Permit issued — Plumbing
Q01051937-S2-PL
04/15/2025
Permit issued — Earth Work
Q01051937-S1-FO-EA
04/11/2025
Special inspection requirement — Fenestration air leakage
Alan Yang
04/11/2025
Special inspection requirement — Air barrier - visual inspection
Alan Yang
04/11/2025
Special inspection requirement — Fenestration areas
Alan Yang
04/11/2025
Special inspection requirement — Insulation placement and R values
Alan Yang
04/11/2025
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
Alan Yang
04/11/2025
Special inspection requirement — Final
Alan Yang
04/11/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Alan Yang
03/24/2025
Filed — Alteration
Adding two bathrooms
Q01051937-P1
02/24/2025
Permit issued — Structural
Q01051937-S3-ST
02/04/2025
Permit issued — Construction Fence
Q01051937-S4-FN
02/03/2025
Permit issued — General Construction
Q01051937-I1-GC
01/27/2025
Filed — Alteration
Adding two bathrooms
Q01051937-S4
06/10/2024
Filed — Alteration
Adding two bathrooms
Q01051937-S3
06/09/2024
Filed — Alteration
Adding two bathrooms
Q01051937-S1
06/09/2024
Special inspection requirement — Designated Seismic System
CHENG GU
06/08/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
CHENG GU
06/08/2024
Special inspection requirement — Post-installed Anchors
CHENG GU
06/07/2024
Filed — Alteration
Adding two bathrooms
Q01051937-S2
06/03/2024
Special inspection requirement — Final
CHENG GU
06/03/2024
Special inspection requirement — Subgrade Inspections
CHENG GU
06/03/2024
Special inspection requirement — Concrete - Cast-In-Place
CHENG GU
05/28/2024
Special inspection requirement — Final
CHENG GU
05/28/2024
Special inspection requirement — Footing and Foundation
CHENG GU
05/18/2024
Filed — Alteration
Adding two bathrooms
Q01051937-I1
12/20/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPROTON CCM LLC04/15/2026
DOB NOWPlumbingSigned-offAMERICAN STANDARD P&H CORORP.11/20/2025
DOB NOWEarth WorkPermit IssuedPROTON CCM LLC04/15/2025
DOB NOWStructuralPermit IssuedPROTON CCM LLC02/24/2025
DOB NOWConstruction FenceSigned-offPROTON CCM LLC02/04/2025
DOB NOWGeneral ConstructionSigned-offPROTON CCM LLC02/03/2025
1 project · most recent 03/24/2025
Water/Sanitary
FiledStatusContractorScope
03/24/2025Signed-offAMERICAN STANDARD P&H CORWater/Sanitary
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
04/15/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/09/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/09/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/04/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/04/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
12/20/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
04/11/2025Fenestration air leakageAlan Yangenergy_progress
04/11/2025Air barrier - visual inspectionAlan Yangenergy_progress
04/11/2025Fenestration areasAlan Yangenergy_progress
04/11/2025Insulation placement and R valuesAlan Yangenergy_progress
04/11/2025Wall Panels, Curtain Walls, and VeneersAlan Yangspecial
04/11/2025FinalAlan Yangprogress
04/11/2025Fenestration and door U-factor and product ratingsAlan Yangenergy_progress
06/09/2024Designated Seismic SystemCHENG GUspecial
06/08/2024Structural Stability – Alterations of existing buildingsCHENG GUspecial
06/08/2024Post-installed AnchorsCHENG GUspecial
06/03/2024FinalCHENG GUprogress
06/03/2024Subgrade InspectionsCHENG GUspecial
06/03/2024Concrete - Cast-In-PlaceCHENG GUspecial
05/28/2024FinalCHENG GUprogress
05/28/2024Footing and FoundationCHENG GUprogress
▾Documents — 45 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/20/2026Q01051937-S4Request digital key ↗
08/20/2026Q01051937-S3Request digital key ↗
08/20/2026Q01051937-S2Request digital key ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q01051937-I1Open ↗
08/13/2026Q01051937-P1Open ↗
▸Seals & Professional Certifications21
▸DOB NOWProgress Inspector Seal & Signature9
09/01/2026Q01051937-S3Open ↗
08/29/2026Q01051937-S1Open ↗
08/29/2026Q01051937-S1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/01/2026Q01051937-S3Open ↗
09/01/2026Q01051937-S3Open ↗
09/01/2026Q01051937-S3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/20/2026Q01051937-S4Open ↗
08/20/2026Q01051937-S3Open ↗
08/20/2026Q01051937-S2Open ↗
Showing 3 of 6 on file for this type
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026Q01051937-I1Open ↗
08/13/2026Q01051937-P1Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/20/2026Q01051937-S2Open ↗
08/20/2026Q01051937-S1Open ↗
08/20/2026Q01051937-I1Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/20/2026Q01051937-I1Open ↗
08/20/2026Q01051937-P1Open ↗
▸Inspections & Test Reports1
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026Q01051937-S1Open ↗
▸Other Documents8
▸DOB NOWPlot Diagram3
08/13/2026Q01051937-P1Open ↗
08/13/2026Q01051937-S1Open ↗
08/13/2026Q01051937-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026Q01051937-I1Open ↗
08/13/2026Q01051937-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q01051937-P1Open ↗
08/13/2026Q01051937-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01051937-S1Open ↗