| Owner | Filings | Most Recent |
|---|---|---|
| FORD LEASING PROPERTY LIMITED LIABILITY COMPANY | 2 | 03/22/2026 |
| FORD LEASING CORP | 2 | 03/22/2026 |
| FORELEASING PROPERTY LIMI | 1 | 03/22/2026 |
| GROUND UP CONSTRUCTION TEAM INC. | 1 | 03/22/2026 |
| FORD LEASING PROPERTY | 8 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IMC ARCHITECTURE DPC | 3 | 10/29/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| METROPOLIS GROUP INC | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GROUND UP CONSTRUCTION TE | General Contractor | 4 | 07/08/2026 |
| PCS ELECTRICAL SVCS INC | Electrical | 1 | 03/22/2026 |
| UNIPIPE PLBG&HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PSI AGENCY INC. | 254 | 3 | 10/29/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | GROUND UP CONSTRUCTION TE | 12/15/2021 |
| DOB NOW | Mechanical Systems | Signed-off | GROUND UP CONSTRUCTION TE | 10/22/2021 |
| DOB NOW | Plumbing | Signed-off | UNIPIPE PLBG&HTG CORP | 09/29/2021 |
| BIS | OT | ISSUED | GROUND UP CONSTRUCTION TE | 12/14/2021 |
| BIS | OT | ISSUED | GROUND UP CONSTRUCTION TE | 09/22/2021 |
| BIS | OT | ISSUED | CARLOS HUMBERTO AVILA VIL | 11/20/2020 |
| BIS | OT | ISSUED | 770 ELECTRIC CORP | 09/05/2019 |
| BIS | OT | ISSUED | DNA CONTRACTING LLC | 12/17/2015 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 10/29/2015 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 08/24/2015 |
| BIS | OT | ISSUED | KNS BUILDING REST. INC | 07/09/2015 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 10/30/2014 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 10/29/2013 |
| BIS | OT | ISSUED | RICONDA MAINTENANCE INC | 05/20/2013 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 11/21/2012 |
| BIS | OT | ISSUED | RICONDA MAINTENANCE INC | 08/29/2012 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 08/25/2011 |
| BIS | OT | ISSUED | RICONDA MAINTENANCE INC | 03/31/2006 |
| BIS | PL | ISSUED | BELL FUEL OIL, LLC | 01/25/2002 |
| BIS | BL | ISSUED | ABILENE, INC | 12/12/2001 |
| BIS | OT | ISSUED | ABILENE INC | 12/20/2000 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/24/2021 | Complete | PCS ELECTRICAL SVCS INC | General Wiring |
| 10/13/2019 | Complete | GRID CITY ELECTRIC, CORP | 1 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/11/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/10/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/10/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/09/2021 | Pass-Final PL - Underground | Pass | View ↗ |
| 11/04/2021 | Fail-Final PL - Underground | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/31/2021 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |
| 08/24/2020 | Shutoff dampers | MAURICIO ANDRADE | energy_progress |
| 07/31/2020 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |
| 07/30/2020 | Mechanical Systems | MAURICIO ANDRADE | special |
| 07/30/2020 | Final | MAURICIO ANDRADE | progress |