← Back
Four families
The 489 Seventh Avenue Condominium
489 7 AVENUE · BIN 3027082
💬 Discuss this project
1920Year Built
4Stories
C3Building Class
R6AZoning
3,900 sfGross Floor Area
4Units
Rent Stabilized4 Open Violations ▸FDNY Report ↗
Four families · Owner of record: 489 7TH AVE LLC · 1,485 sf lot · 2.63 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbing
Roof30p · 1 filing · 20 docs
Floor 422p · 2 filings · 20 docs
Floor 321p · 1 filing · 20 docs
Floor 221p · 2 filings · 20 docs
Floor 120p · 1 filing · 20 docs
Cellar29p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
VAN LEENEN DEVELOPMENTS3207/08/2026
RELIABLE ENTERPRISES707/08/2026
489 7TH AVE LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/13/2024$2.5M—DANKYLE REALTY II LLC → 489 7TH AVE LLC$641/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ERIC SAFYAN ARCHITECT PC1103/17/2026
MJE PROFESSIONAL SERVICES201/15/2025
HENRY MONT112/23/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JOSEPH FELLNER1103/21/2026
SNR EXPEDITING DESIGN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CITY LINE INTERIORS INCGeneral Contractor607/08/2026
RELIABLE ENTERPRISES INCGeneral Contractor207/08/2026
ETHOS PLUMBING CORPPlumbing207/08/2026
ICE AGE MECHANICAL CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BARRY STRUCTURAL ENGINEER749403/17/2026
ERIC SAFYAN ARCHITECTPC32481003/17/2026
HRF SERVICES CORP5616212/10/2025
Building Lifecycle
All (107)Filed (14)Permit Issued (10)Signed Off (8)Violation (15)Inspection (12)Objection (18)Special Inspection (30)
04/30/2026
Signed off — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-I1
04/23/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/03/2026
Special inspection requirement — Exterior lighting power
Eric Safyan
04/03/2026
Special inspection requirement — Energy Code Compliance Inspections
Eric Safyan
04/03/2026
Special inspection requirement — Fenestration air leakage
Eric Safyan
04/03/2026
Special inspection requirement — Fire-Resistance Rated Construction
Eric Safyan
04/03/2026
Special inspection requirement — Fenestration areas
Eric Safyan
04/03/2026
Special inspection requirement — Lighting controls
Eric Safyan
04/03/2026
Special inspection requirement — Lighting in dwelling units
Eric Safyan
04/03/2026
Special inspection requirement — Interior lighting power
Eric Safyan
04/03/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Eric Safyan
04/03/2026
Special inspection requirement — Metering
Eric Safyan
04/03/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Eric Safyan
04/03/2026
Special inspection requirement — Insulation placement and R values
Eric Safyan
04/03/2026
Special inspection requirement — Air barrier - visual inspection
Eric Safyan
04/03/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
MICHAEL BARRY
03/17/2026
Filed — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-P5
03/16/2026
Special inspection requirement — Fenestration air leakage
Eric Safyan
03/16/2026
Special inspection requirement — Metering
Eric Safyan
03/16/2026
Special inspection requirement — Lighting controls
Eric Safyan
03/16/2026
Special inspection requirement — Interior lighting power
Eric Safyan
03/16/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Eric Safyan
03/16/2026
Special inspection requirement — Air barrier - visual inspection
Eric Safyan
03/16/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Eric Safyan
03/16/2026
Special inspection requirement — Lighting in dwelling units
Eric Safyan
03/16/2026
Special inspection requirement — Fenestration areas
Eric Safyan
03/16/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
MICHAEL BARRY
03/16/2026
Special inspection requirement — Energy Code Compliance Inspections
Eric Safyan
03/16/2026
Special inspection requirement — Exterior lighting power
Eric Safyan
03/16/2026
Special inspection requirement — Fire-Resistance Rated Construction
Eric Safyan
03/16/2026
Special inspection requirement — Insulation placement and R values
Eric Safyan
01/28/2026
Signed off — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-S1
01/23/2026
Objection raised — Admin
01/23/2026
Objection resolved — Addressed
01/23/2026
Special inspection requirement — HVAC-R and service water heating system controls
Eric Safyan
01/23/2026
Special inspection requirement — HVAC-R and service water heating equipment
Eric Safyan
01/16/2026
Signed off — Alteration
Plumbing work filed in conjunction with the renovation of floors 2-4. Kitchen and bathroom work.
B01072465-I1
01/16/2026
Signed off — Alteration
Plumbing work filed in conjunction with the renovation of floors 2-4. Kitchen and bathroom work.
B01072465-S3
01/16/2026
Signed off — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-S3
01/12/2026
Objection resolved — Addressed
01/02/2026
Objection raised — Admin
12/26/2025
Filed — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-P4
12/22/2025
Signed off — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-S2
12/10/2025
Filed — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-P3
12/05/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/19/2025
Violation issued (HPD, closed)
I
10/30/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
10/22/2025
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01167387-I1
10/22/2025
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01167350-I1
10/01/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/05/2025
Violation issued (HPD, closed)
A
05/06/2025
Permit issued — General Construction
B01072465-I1-GC
05/06/2025
Permit issued — General Construction
B01093061-I1-GC
04/29/2025
Filed — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-P2
04/28/2025
Filed — Alteration
Plumbing work filed in conjunction with the renovation of floors 2-4. Kitchen and bathroom work.
B01072465-P1
04/04/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/20/2025
Filed — Alteration CO
Convert from 4 family and store to 4 family. Partition work at cellar and 1st floor. New bulkhead. Replace windows.
B01093061-P1
02/13/2025
Permit issued — Structural
B01093061-S2-ST
02/10/2025
Permit issued — Mechanical Systems
B01093061-S1-MS
02/05/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
Latest 60 of 107 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offCITY LINE INTERIORS05/06/2025
DOB NOWGeneral ConstructionPermit IssuedCITY LINE INTERIORS05/06/2025
DOB NOWStructuralSigned-offCITY LINE INTERIORS02/13/2025
DOB NOWMechanical SystemsSigned-offICE AGE MECHANICAL CORP02/10/2025
DOB NOWPlumbingSigned-offETHOS PLUMBING CORP01/30/2025
DOB NOWSidewalk ShedSigned-offRELIABLE ENTERPRISES INC01/17/2025
DOB NOWSupported ScaffoldSigned-offRELIABLE ENTERPRISES INC01/15/2025
DOB NOWGeneral ConstructionPermit IssuedCITY LINE INTERIORS11/01/2024
DOB NOWPlumbingSigned-offETHOS PLUMBING CORP09/27/2024
DOB NOWGeneral ConstructionSigned-offCITY LINE INTERIORS09/23/2024
1 project · most recent 03/17/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
03/17/2026Signed-offETHOS PLUMBING CORPGas, Storm, Water/Sanitary
2 projects · most recent 01/17/2025
General Wiring
FiledStatusContractorScope
01/17/2025CompleteRICHARD NEU—
09/25/2024CompleteNYCO ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
04/23/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/05/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/30/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/01/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/04/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/05/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
02/05/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/03/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/31/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/24/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/16/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/06/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 84
DateRequirementInspectorRole
04/03/2026Fire-Resistant Penetrations and JointsEric Safyanspecial
04/03/2026Air barrier - visual inspectionEric Safyanenergy_progress
04/03/2026Interior lighting powerEric Safyanenergy_progress
04/03/2026Fenestration and door U-factor and product ratingsEric Safyanenergy_progress
04/03/2026Fenestration air leakageEric Safyanenergy_progress
04/03/2026Lighting in dwelling unitsEric Safyanenergy_progress
04/03/2026Exterior lighting powerEric Safyanenergy_progress
04/03/2026MeteringEric Safyanenergy_progress
04/03/2026Fenestration areasEric Safyanenergy_progress
04/03/2026Lighting controlsEric Safyanenergy_progress
04/03/2026Insulation placement and R valuesEric Safyanenergy_progress
04/03/2026Fire-Resistance Rated ConstructionEric Safyanprogress
04/03/2026Energy Code Compliance InspectionsEric Safyanprogress
04/03/2026Structural Stability – Alterations of existing buildingsMICHAEL BARRYspecial
03/16/2026Lighting controlsEric Safyanenergy_progress
03/16/2026Fire-Resistant Penetrations and JointsEric Safyanspecial
03/16/2026Structural Stability – Alterations of existing buildingsMICHAEL BARRYspecial
03/16/2026Energy Code Compliance InspectionsEric Safyanprogress
03/16/2026Fire-Resistance Rated ConstructionEric Safyanprogress
03/16/2026Fenestration areasEric Safyanenergy_progress
03/16/2026Air barrier - visual inspectionEric Safyanenergy_progress
03/16/2026Fenestration and door U-factor and product ratingsEric Safyanenergy_progress
03/16/2026Lighting in dwelling unitsEric Safyanenergy_progress
03/16/2026Insulation placement and R valuesEric Safyanenergy_progress
03/16/2026Exterior lighting powerEric Safyanenergy_progress
Latest 25 of 84.
▾Documents — 92 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
08/24/2026B01072465-P1Request digital key ↗
08/24/2026B01072465-S3Request digital key ↗
08/24/2026B01072465-I1Request digital key ↗
Showing 3 of 13 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION2
11/12/2025322122396Open ↗
10/24/2025322122396Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWHouse Number Verification: TOPO Stamp4
08/13/2026B01093061-P3Open ↗
08/13/2026B01093061-I1Open ↗
08/13/2026B01093061-P2Open ↗
Showing 3 of 4 on file for this type
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
11/14/2025322122396Open ↗
▸Seals & Professional Certifications48
▸DOB NOWProgress Inspector Seal & Signature21
08/31/2026B01093061-P4Open ↗
08/31/2026B01093061-P4Open ↗
08/29/2026B01072465-S3Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/24/2026B01072465-P1Open ↗
08/24/2026B01072465-S3Open ↗
08/24/2026B01072465-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature13
08/31/2026B01093061-P4Open ↗
08/28/2026B01093061-P5Open ↗
08/28/2026B01093061-P5Open ↗
Showing 3 of 13 on file for this type
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist4
08/13/2026B01093061-P5Open ↗
08/13/2026B01093061-I1Open ↗
08/13/2026B01093061-P3Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos12
▸DOB NOWDEP ACP-5: Asbestos Assessment Report12
08/24/2026B01072465-I1Open ↗
08/24/2026B01072465-P1Open ↗
08/24/2026B01072465-S3Open ↗
Showing 3 of 12 on file for this type
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
10/24/2025322122396Open ↗
▸Other Documents7
▸DOB NOWProperty Ownership Certification4
08/17/2026B01093061-I1Open ↗
08/17/2026B01093061-P5Open ↗
08/17/2026B01093061-P3Open ↗
Showing 3 of 4 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
11/14/2025322122396Open ↗
11/14/2025322122396Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
11/14/2025322122396Open ↗