| Owner | Filings | Most Recent |
|---|---|---|
| 51 East 80th Street | 9 | 03/21/2026 |
| Perranporth | 8 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/15/2019 | $21.5M | — | — → — | $2,422/sf building |
| 07/24/2014 | $23.5M | — | 51 EAST 80TH STREET LLC → NORTH FIFTH,LLC | $2,648/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Raad | 7 | 09/25/2024 |
| Sarah Jacoby Architect | 3 | 08/05/2024 |
| Mohammad Ahead, PE | 2 | 01/23/2024 |
| Mje Professional Services | 2 | 08/25/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| Joseph Fellner | 3 | 03/21/2026 |
| Louis Striar | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Pal-Mar Plumbing & Heating | Plumbing | 5 | 07/08/2026 |
| Reliable Enterprises | Scaffold | 3 | 03/21/2026 |
| Rael Automatic Sprinkler Co | Fire Protection | 3 | 07/08/2026 |
| Pam Air Conditioning | specialty_contractor | 1 | 07/08/2026 |
| Smi Construction Mangement | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Raad | 7727 | 7 | 09/25/2024 |
| Norman C. Lok | 818 | 2 | 01/23/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Pal-Mar Plumbing & Heating | 07/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Pam Air Conditioning | 04/19/2024 |
| DOB NOW | Sprinklers | Signed-off | Rael Automatic Sprinkler Co | 04/02/2024 |
| DOB NOW | General Construction | Signed-off | Smi Construction Mangemen | 01/31/2024 |
| DOB NOW | Plumbing | Signed-off | Pal-Mar Plumbing & Heating | 12/12/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Reliable Enterprises | 08/24/2023 |
| DOB NOW | Plumbing | Signed-off | Pal-Mar Plumbing & Heating | 03/29/2023 |
| DOB NOW | Sprinklers | Signed-off | Rael Automatic Sprinkler Co | 03/27/2023 |
| DOB NOW | Plumbing | Signed-off | Pal-Mar Plumbing & Heating | 08/03/2022 |
| DOB NOW | Sprinklers | Signed-off | Rael Automatic Sprinkler Co | 03/25/2022 |
| DOB NOW | Plumbing | Signed-off | Pal-Mar Plumbing & Heating | 07/20/2021 |
| BIS | OT | ISSUED | Smi Construction Mangement | 12/20/2023 |
| BIS | OT | ISSUED | Smi Construction Mangement | 12/20/2023 |
| BIS | OT | ISSUED | Smi Construction Mangement | 03/07/2023 |
| BIS | OT | ISSUED | Smi Construction Mangement | 03/07/2023 |
| BIS | OT | ISSUED | Smi Construction Mangement | 12/14/2022 |
| BIS | OT | ISSUED | Smi Construction Mangement | 12/14/2022 |
| BIS | OT | ISSUED | Smi Construction Mangement | 12/14/2022 |
| BIS | OT | ISSUED | Smi Construction Mangement | 12/14/2022 |
| BIS | OT | ISSUED | Smi Construction Mangement | 04/01/2022 |
| BIS | OT | ISSUED | Smi Construction Mangement | 04/01/2022 |
| BIS | OT | ISSUED | Smi Construction Mangement | 06/29/2021 |
| BIS | OT | ISSUED | Smi Construction Mangement | 06/29/2021 |
| BIS | PL | ISSUED | Z.W. Plumbing & Heating | 05/01/2013 |
| BIS | — | ISSUED | Forte Remodeling | 03/08/2013 |
| BIS | EQ | ISSUED | Phoenix Sutton STR | 09/10/2012 |
| BIS | EQ | ISSUED | Phoenix Sutton STR | 09/05/2012 |
| BIS | — | ISSUED | Forte Remodeling | 07/26/2012 |
| BIS | EQ | ISSUED | Phoenix Bridging | 05/24/2012 |
| BIS | — | ISSUED | Forte Remodeling | 05/18/2012 |
| BIS | EQ | ISSUED | Phoenix Bridging | 05/11/2012 |
| BIS | PL | ISSUED | Z.W. Plumbing & Heating | 04/09/2012 |
| BIS | — | ISSUED | Forte Remodeling | 01/10/2012 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2025 | Complete | Joseph Sgroi & Sons | General Wiring |
| 08/25/2023 | Complete | Richard Neu | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/15/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/10/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/05/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/01/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/17/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/17/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/26/2024 | Sprinkler Systems | NICHOLAS AZADIAN | special |
| 09/26/2024 | Fire-Resistant Penetrations and Joints | NICHOLAS AZADIAN | special |
| 09/24/2024 | Sprinkler Systems | NICHOLAS AZADIAN | special |
| 09/24/2024 | Fire-Resistant Penetrations and Joints | NICHOLAS AZADIAN | special |
| 08/22/2024 | Final | NICHOLAS AZADIAN | progress |
| 08/22/2024 | Mechanical Systems | NICHOLAS AZADIAN | special |
| 08/22/2024 | HVAC and service water heating equipment | NICHOLAS AZADIAN | energy_progress |
| 08/22/2024 | HVAC and service water heating system controls | NICHOLAS AZADIAN | energy_progress |
| 08/22/2024 | HVAC insulation and sealing | NICHOLAS AZADIAN | energy_progress |
| 08/15/2024 | HVAC and service water heating system controls | NICHOLAS AZADIAN | energy_progress |
| 08/15/2024 | Mechanical Systems | NICHOLAS AZADIAN | special |
| 08/15/2024 | Final | NICHOLAS AZADIAN | progress |
| 08/15/2024 | HVAC and service water heating equipment | NICHOLAS AZADIAN | energy_progress |
| 08/15/2024 | HVAC insulation and sealing | NICHOLAS AZADIAN | energy_progress |
| 08/05/2024 | Energy Code Compliance Inspections | Sarah Jacoby | progress |
| 08/05/2024 | HVAC insulation and sealing | Sarah Jacoby | energy_progress |
| 09/15/2022 | Energy Code Compliance Inspections | Sarah Jacoby | progress |
| 09/15/2022 | HVAC insulation and sealing | Sarah Jacoby | energy_progress |
| 03/28/2022 | Sprinkler Systems | NICHOLAS AZADIAN | special |
| 03/28/2022 | Fire-Resistant Penetrations and Joints | NICHOLAS AZADIAN | special |