← Back
Elevator cooperative
Hip To Hip Theatre Company
52-30 39 DRIVE · BIN 4431300
💬 Discuss this project
1963Year Built
12Stories
D4Building Class
R7-1Zoning
441,929 sfGross Floor Area
442Units
LL97 CoveredRent Stabilized13 Open Violations ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: BERKELEY COOP TOWERS SEC 2 · 94,807 sf lot · 4.66 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 72p · 1 filing · 3 docs
Floor 6
Floor 51p · 1 filing · 7 docs
Floor 4
Floor 3
Floor 2
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
STEEL SYSTEMS507/08/2026
KINGS GROUP NY CORP703/22/2026
GABRIEL MANAGEMENT203/22/2026
BERKELEY CO-OP TOWERS503/22/2026
BERKELEY TOWERS SECTION II303/22/2026
BERKELEY COOPERATIVE TOWERS803/22/2026
ATLAS BUILDING CONSULTANTS103/22/2026
BERKLY COOP TOWER203/21/2026
BERKELEY TOWERS403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AR ARCHITECT P.C303/17/2023
JONG HAE CHANG ARCHITECT203/07/2023
MICHAEL ALMON, ARCHITECT306/02/2022
ASHRAF CORP103/01/2022
ROYAL ENGINEERING, P.C103/22/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rigid Structural Design, LLC103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KINGS GROUP NY CORPGeneral Contractor603/21/2026
OVERALL RENOVATION INCGeneral Contractor303/21/2026
STEEL SYSTEMS LLCGeneral Contractor207/08/2026
HEALY WOODWORKS INCGeneral Contractor107/08/2026
CK PLUMBING & MECH INCPlumbing107/08/2026
DPH PLUMBING & HTG CORPPlumbing107/08/2026
BISHUNDAT, CHRISTOPHERElectrical103/21/2026
F1 MECHANICAL INCPlumbing107/08/2026
SHUIR ELEC'L CONTR'S CORPElectrical103/22/2026
CUBENINE INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AR ARCHITECT P.C.1171303/17/2023
JONG HAE CHANG ARCHITECT6169203/07/2023
MICHAEL ALMON, ARCHITECT5114306/02/2022
Building Lifecycle
All (115)Filed (10)Permit Issued (10)Signed Off (6)Facade (FISP) (12)Violation (60)Inspection (12)Special Inspection (5)
05/06/2026
Violation issued (HPD, closed)
A
01/07/2026
Violation issued (HPD, closed)
C
08/05/2025
Violation issued (HPD, open)
A
10/04/2023
Violation issued (HPD, open)
B
10/04/2023
Violation issued (HPD, open)
B
10/04/2023
Violation issued (HPD, open)
B
10/04/2023
Violation issued (HPD, open)
A
10/04/2023
Violation issued (HPD, open)
B
09/18/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
Q00029139-I1
06/21/2023
Signed off — Alteration
COMBINE TWO APARTMENTS, 7R AND 7N UNDER TPPN #3/97 AND RENOVATION
Q00709468-I1
06/04/2023
Violation issued (HPD, closed)
A
06/04/2023
Violation issued (HPD, open)
B
05/09/2023
Violation issued (HPD, closed)
A
05/09/2023
Violation issued (HPD, closed)
A
05/05/2023
Signed off — Alteration
INTERIOR RENOVATION OF APT UNIT #5H. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00832179-S1
05/05/2023
Signed off — Alteration
INTERIOR RENOVATION OF APT UNIT #5H. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00832179-I1
04/21/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/20/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
04/20/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/04/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/27/2023
Violation issued (HPD, closed)
A
03/17/2023
Filed — Alteration
COMBINE TWO APARTMENTS, 7R AND 7N UNDER TPPN #3/97 AND RENOVATION
Q00709468-P1
03/17/2023
Permit issued — Plumbing
Q00832179-S1-PL
03/07/2023
Filed — Alteration
INTERIOR RENOVATION OF APT UNIT #5H. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00832179-S1
03/07/2023
Permit issued — General Construction
Q00832179-I1-GC
03/07/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jong Hae Kim
02/28/2023
Filed — Alteration
INTERIOR RENOVATION OF APT UNIT #5H. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00832179-I1
02/17/2023
Cycle 9 facade report submitted
02/17/2023
Cycle 9 facade report signed — SAFE
02/12/2023
Violation issued (HPD, closed)
A
02/12/2023
Violation issued (HPD, open)
B
02/12/2023
Violation issued (HPD, closed)
A
02/12/2023
Violation issued (HPD, closed)
A
02/12/2023
Violation issued (HPD, closed)
C
02/01/2023
Signed off — Alteration
APPLICATION TO COMBINE APTS. #6D & #6E PER TPPN #03/97. IN APT #6E : REMOVE RANGE & CAP GAS, NEW BAR SINK, TOILET & LAV ON EXIST. ROUGH. REMOVE BATHTUB & CONVERT TO STALL SHOWER. IN #6D KITCHEN : REPLACE AND RELOCATE SINK & DW ON EXISTING ROUGHING.
Q00630265-I1
01/25/2023
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/23/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/16/2023
Cycle 9 facade inspection completed
12/02/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/11/2022
Violation issued (HPD, open)
A
10/11/2022
Violation issued (HPD, closed)
A
10/11/2022
Violation issued (HPD, closed)
C
10/11/2022
Violation issued (HPD, closed)
C
09/29/2022
Permit issued — Plumbing
Q00740097-I1-PL
09/26/2022
Permit issued — General Construction
Q00709468-I1-GC
09/08/2022
Violation issued (HPD, closed)
A
09/08/2022
Violation issued (HPD, closed)
A
09/08/2022
Violation issued (HPD, closed)
C
09/08/2022
Violation issued (HPD, closed)
C
09/08/2022
Violation issued (HPD, closed)
A
09/08/2022
Violation issued (HPD, closed)
C
09/08/2022
Violation issued (HPD, closed)
A
09/08/2022
Violation issued (HPD, closed)
C
09/03/2022
Violation issued (HPD, closed)
A
09/03/2022
Violation issued (HPD, closed)
A
09/03/2022
Violation issued (HPD, closed)
C
09/03/2022
Violation issued (HPD, closed)
A
09/03/2022
Violation issued (HPD, closed)
C
09/03/2022
Violation issued (HPD, closed)
C
08/26/2022
Violation issued (HPD, closed)
B
Latest 60 of 115 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCK PLUMBING & MECH INC03/17/2023
DOB NOWGeneral ConstructionSigned-offCUBENINE03/07/2023
DOB NOWPlumbingPermit IssuedF1 MECHANICAL INC09/29/2022
DOB NOWGeneral ConstructionSigned-offHEALY WOODWORKS09/26/2022
DOB NOWSidewalk ShedPermit IssuedSTEEL SYSTEMS LLC04/29/2022
DOB NOWSidewalk ShedPermit IssuedSTEEL SYSTEMS LLC03/03/2022
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP02/15/2022
DOB NOWGeneral ConstructionSigned-offOVERALL RENOVATION INC01/05/2022
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP10/02/2018
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP03/23/2018
BISOTISSUEDPNA CONTRACTING CORP09/06/2020
BISOTISSUEDCUSTOM DESIGNS INC 311/21/2019
BISPLISSUEDTRI STATE PLBG & HTG INC10/23/2018
BISOTISSUEDYOFRESH HICKSVILLE LLC10/09/2018
BISOTISSUEDAPA GROUP INC05/25/2018
BISPLISSUEDF1 MECHANICAL INC01/18/2018
BISOTISSUEDHEALY WOODWORKS INC01/18/2018
BISOTISSUEDAPA GROUP INC07/25/2016
BISEQISSUEDSPRING SCAFFOLDING LLC06/02/2016
BISEQISSUEDROCKLEDGE SCAFFOLD CORP08/04/2014
BISEQISSUEDROCKLEDGE SCAFFOLD CORP06/01/2012
BISOTISSUEDYATES REST GROUP LTD05/03/2012
BISEQISSUEDROCKLEDGE SCAFFOLD CORP06/29/2011
BISOTISSUEDYATES REST GROUP LTD05/13/2011
BISOTISSUEDYATES REST GROUP LTD10/21/2010
BISEQISSUEDROCKLEDGE SCAFFOLD CORP07/02/2010
BISOTISSUEDDJM RESTORATION, INC.11/28/2007
BISOTISSUEDDJM CONTRACTING04/18/2007
BISEQISSUEDVERTICAL SCAFFOLD, LLC06/08/2006
BISOTISSUEDDJM CONTRACTING10/28/2005
BISEQISSUEDSPRING SCAFFOLDING03/01/2004
BISMHISSUEDCRM INTERNATIONAL12/03/2002
BISPLISSUEDPP COUSIN INC04/11/2002
BISOTISSUEDCRM ENERGY SYSTEMS04/04/2002
BISOTISSUEDSATO CONSTRUCTION CO.INC08/13/2001
BISFSISSUEDBETA MECH BETTER ENERGY GRP12/26/1997
BISOTISSUEDBETA MECH BETTER ENERGY GRP12/26/1997
BISPLISSUEDEBM PLUMBING CORP11/12/1997
BIS—ISSUEDFLAG WATER PROOFING05/05/1993
BIS—ISSUEDBERKLEY COOP TOWER04/21/1993
+ 1 more permits on file
6 projects · most recent 10/13/2022
General Wiring
FiledStatusContractorScope
10/13/2022CompleteSHUIR ELEC'L CONTR'S CORP—
02/17/2022Permit IssuedTOP SHELF ELECTRIC CORP—
09/25/2018CompleteYORK ELEC'L CONTR'S INC.General Wiring
06/05/2018CompleteYORK ELEC'L CONTR'S INC.General Wiring
03/23/2018Permit IssuedMEO ELECTRIC CORP—
01/30/2018CompleteSHUIR ELEC'L CONTR'S CORPGeneral Wiring
1 project · most recent 03/01/2022
Sidewalk Shed
FiledStatusContractorScope
03/01/2022Permit IssuedSTEEL SYSTEMS LLCSidewalk Shed
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
04/21/2023Pass-Final General Construction Non-Directive 14PassView ↗
04/20/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/20/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/04/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/25/2023Fail-Final General Construction Non-Directive 14FailView ↗
01/23/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/02/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/17/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/13/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
05/09/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/09/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/18/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/07/2023Fire-Resistant Penetrations and JointsJong Hae Kimspecial
06/02/2022Fire-Resistant Penetrations and Jointsmichael almonspecial
06/01/2022Fire-Resistant Penetrations and Jointsmichael almonspecial
11/12/2021Fire-Resistant Penetrations and Jointsmichael almonspecial
11/12/2021Finalmichael almonprogress
▾Documents — 192 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/29/2026Q00029139-I1Request digital key ↗
08/27/2026Q00630190-I1Request digital key ↗
08/26/2026Q00689344-I1Request digital key ↗
Showing 3 of 10 on file for this type
▸Applications & Permits28
▸BISPLAN / WORK APPROVAL APPLICATION15
09/02/2020440623880Open ↗
11/27/2019421938489Open ↗
01/19/2019421683592Open ↗
Showing 3 of 15 on file for this type
▸BISWORK PERMIT APPLICATION12
09/06/2020440623880Open ↗
11/27/2019421938489Open ↗
11/07/2018421683592Open ↗
Showing 3 of 12 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
03/11/2019421683592Open ↗
▸Seals & Professional Certifications44
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION14
11/27/2019421938489Open ↗
08/07/2019421533344Open ↗
03/11/2019421683592Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/29/2026Q00029139-I1Open ↗
08/26/2026Q00630265-P1Open ↗
08/26/2026Q00630265-I1Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
09/02/2020440623880Open ↗
11/27/2019421938489Open ↗
01/19/2019421683592Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/28/2026Q00630190-I1Open ↗
08/28/2026Q00832179-S1Open ↗
08/25/2026Q00630265-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
09/02/2020440623880Open ↗
06/01/2016440315124Open ↗
08/01/2014440159301Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
11/27/2019421938489Open ↗
01/19/2019421683592Open ↗
07/06/2010420210765Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
09/02/2020440623880Open ↗
06/01/2016440315124Open ↗
08/01/2014440159301Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
07/06/2010420210765Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/28/2026Q00630190-I1Open ↗
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
01/19/2019421683592Open ↗
01/05/2019421556220Open ↗
11/03/2018421683592Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection7
▸BISTenant Protection Plan and Notes7
11/27/2019421938489Open ↗
01/19/2019421683592Open ↗
10/13/2017421533344Open ↗
Showing 3 of 7 on file for this type
▸Environmental & Asbestos16
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/26/2026Q00630265-P1Open ↗
08/26/2026Q00630265-I1Open ↗
08/25/2026Q00832179-S1Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)6
09/02/2020440623880Open ↗
11/27/2019421938489Open ↗
01/19/2019421683592Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
11/20/2013420210765Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
10/22/2010420191615Open ↗
▸Energy Compliance20
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS9
11/27/2019421938489Open ↗
08/07/2019421533344Open ↗
03/11/2019421683592Open ↗
Showing 3 of 9 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
08/07/2019421533344Open ↗
03/11/2019421683592Open ↗
07/24/2017421331990Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING2
06/01/2016440315124Open ↗
08/01/2014440159301Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
09/28/2020440623880Open ↗
09/02/2020440623880Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
09/02/2020440623880Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
09/28/2020440623880Open ↗
▸BISNYCECC ANALYSIS1
09/02/2020440623880Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026Q00709468-I1Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
09/28/2020440623880Open ↗
09/02/2020440623880Open ↗
08/01/2014440159301Open ↗
▸Approvals, Objections & Sign-offs19
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST13
09/28/2020440623880Open ↗
08/12/2019421533344Open ↗
08/08/2019421533344Open ↗
Showing 3 of 13 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
10/13/2017421533344Open ↗
09/28/2017421556220Open ↗
07/06/2010420210765Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION2
09/17/2016440315124Open ↗
03/07/2015440159301Open ↗
▸Cost, Insurance & Ownership13
▸BISCOST AFFIDAVIT12
09/02/2020440623880Open ↗
11/27/2019421938489Open ↗
08/12/2019421533344Open ↗
Showing 3 of 12 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
09/28/2020440623880Open ↗
▸Filing & Intake Forms26
▸BISADDITIONAL INFORMATION11
04/17/2020421938489Open ↗
04/17/2020421938489Open ↗
01/10/2019421556220Open ↗
Showing 3 of 11 on file for this type
▸BISEFILING COVER SHEET7
11/27/2019421938489Open ↗
01/19/2019421683592Open ↗
10/13/2017421533344Open ↗
Showing 3 of 7 on file for this type
▸BISBOROUGH INTAKE FORM5
08/08/2019421533344Open ↗
04/18/2019421683592Open ↗
03/23/2019421683592Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
09/02/2020440623880Open ↗
06/01/2016440315124Open ↗
08/01/2014440159301Open ↗
▸Other Documents1
▸DOB NOWBSA Meeting Minutes/BSA Resolution1
08/29/2026Q00029139-I1Open ↗