| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q01405742 ↗ | 46-01 39 AVENUE QUEENS | Alteration | Permit Issued | 05/28/2026 | 09/22/2026 | Design MICHAEL ALMON, ARCHITECT Contractor HI-TECH PLUMBING & HEATING | REMOVE RANGE & CAP GAS SUPPLY. REMOVE DISHWASHER & REPLACE KITCHEN SINK w/ BAR SINK. NO CHANGE TO TRAP, DRAIN, VENT OR SUPPLY PIPING PROPOS… |
| Q01382663 ↗ | 20-25 26 STREET QUEENS | Alteration | Permit Issued | 04/17/2026 | 06/24/2026 | Design MICHAEL ALMON, ARCHITECT Contractor PM MECHANICAL GROUP CORP | RELOCATION OF SINK FIXTURE W/PIPING. INSTALL & HOOKUP OF APPLIANCES |
| M01015227 ↗ | 263 WEST END AVENUE MANHATTAN | Alteration | Permit Issued | 08/06/2024 | 05/04/2026 | Design MICHAEL ALMON, ARCHITECT Contractor VILIMAS MECHANICAL CORP | INTERIOR RENOVATION OF DEMISED 2ND FLOOR APARTMENT #2A, WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN OCCUPANCY, USE, EGRESS OR EXITS IS P… |
| Q01325993 ↗ | 37-33 84 STREET QUEENS | Alteration | Signed-off | 12/18/2025 | 02/19/2026 | Design MICHAEL ALMON, ARCHITECT Contractor CORRIGAN SERVICE CORP | REMOVAL OF INTERIOR NON-LOAD BEARING PARTITION & CONSTRUCTION OF DROPPED HEADER AROUND ENLARGED KITCHEN. PATCH OF DEMO SCARS & WALL & FLOOR… |
| M01034959 ↗ | MAIN STREET MANHATTAN | Alteration | Signed-off | 04/22/2024 | 07/05/2024 | Design MICHAEL ALMON, ARCHITECT Contractor OLEGCHINYAYEV CORP | INTERIOR RENOVATION, PARTITIONS, DOORS, WALL & FLOOR FINISHES WITHIN DEMISED SHAREHOLDER'S APARTMENT PER PLANS FILED HEREIN. NO CHANGE TO US… |
| M00900353 ↗ | CLINTON STREET MANHATTAN | Alteration | Signed-off | 08/03/2023 | 05/31/2024 | Design SRW ENGINEERS Owner BERKOWNERS Contractor TECHNICAL COMFORT OF NY* | Installation of a New 4 Ton Heat Pump connected to three indoor inits. Located at each entrance and the middle of the first floor lobby. As… |
| Name | Projects together | Most recent |
|---|---|---|
| SRW ENGINEERS | 1 | 08/14/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| SHAIRA CONSTRUCTION CORP | 8 | 04/11/2023 |
| HORBRIDGE PLUMBING & HEAT | 3 | 07/06/2021 |
| TYME CONSTRUCTION CORP | 3 | 07/08/2021 |
| CORRIGAN SERVICE CORP | 2 | 05/28/2026 |
| TOP DOG PLBG & HTG CORP | 2 | 10/11/2022 |
| XH&RC PLUMBING HEATING | 2 | 09/14/2023 |
| CPJR IMPROVEMENT CORP | 1 | 04/25/2022 |
| HI-TECH PLUMBING & HEATING LLC | 1 | 05/28/2026 |
| JADCOM CONSTRUCTION CORP | 1 | 08/06/2024 |
| JMW PLUMBING, INC | 1 | 06/02/2022 |
| JOHN'S PLBG & HTG, INC | 1 | 04/11/2023 |
| KISHAN PLBG & HEATING INC | 1 | 12/07/2021 |
| KJH BUILDING & DEV CORP | 1 | 09/07/2021 |
| NICE PLUMBING CORP | 1 | 06/10/2021 |
| OLEGCHINYAYEV CORP | 1 | 04/22/2024 |
| OVERALL RENOVATION INC | 1 | 11/19/2021 |
| PM MECHANICAL GROUP CORP | 1 | 04/17/2026 |
| R.J. WELLBROCK INC | 1 | 06/26/2023 |
| ROYALTY CONST GROUP INC | 1 | 06/02/2021 |
| SIMPLY DIVINE RENOVATION | 1 | 09/14/2023 |
| TECHNICAL COMFORT OF NY* | 1 | 08/14/2025 |
| TMS PLBG & HEATING CORP | 1 | 03/16/2021 |
| TRI CITY MECHANICAL GROUP | 1 | 04/17/2026 |
| TWO-TONE CONTRACTING CORP | 1 | 06/20/2022 |
| TWO-TONE GROUP CORP | 1 | 10/11/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| RENAISSANCE PROPERTIES CORP. | 5 | 04/11/2023 |
| 6838 MANSE STREET | 2 | 04/25/2022 |
| BERKOWNERS | 1 | 08/14/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| SOL BUILDING CONSULTING SERVICES | 1 | 08/14/2025 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q01405742 ↗ | 46-01 39 AVENUE QUEENS | Alteration | Permit Issued | 05/28/2026 | 09/22/2026 | Design MICHAEL ALMON, ARCHITECT Contractor HI-TECH PLUMBING & HEATING | REMOVE RANGE & CAP GAS SUPPLY. REMOVE DISHWASHER & REPLACE KITCHEN SINK w/ BAR SINK. NO CHANGE TO TRAP, DRAIN, VENT OR SUPPLY PIPING PROPOS… |
| Q01382663 ↗ | 20-25 26 STREET QUEENS | Alteration | Permit Issued | 04/17/2026 | 06/24/2026 | Design MICHAEL ALMON, ARCHITECT Contractor PM MECHANICAL GROUP CORP | RELOCATION OF SINK FIXTURE W/PIPING. INSTALL & HOOKUP OF APPLIANCES |
| M01015227 ↗ | 263 WEST END AVENUE MANHATTAN | Alteration | Permit Issued | 08/06/2024 | 05/04/2026 | Design MICHAEL ALMON, ARCHITECT Contractor VILIMAS MECHANICAL CORP | INTERIOR RENOVATION OF DEMISED 2ND FLOOR APARTMENT #2A, WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN OCCUPANCY, USE, EGRESS OR EXITS IS P… |
| Q01325993 ↗ | 37-33 84 STREET QUEENS | Alteration | Signed-off | 12/18/2025 | 02/19/2026 | Design MICHAEL ALMON, ARCHITECT Contractor CORRIGAN SERVICE CORP | REMOVAL OF INTERIOR NON-LOAD BEARING PARTITION & CONSTRUCTION OF DROPPED HEADER AROUND ENLARGED KITCHEN. PATCH OF DEMO SCARS & WALL & FLOOR… |
| M01034959 ↗ | MAIN STREET MANHATTAN | Alteration | Signed-off | 04/22/2024 | 07/05/2024 | Design MICHAEL ALMON, ARCHITECT Contractor OLEGCHINYAYEV CORP | INTERIOR RENOVATION, PARTITIONS, DOORS, WALL & FLOOR FINISHES WITHIN DEMISED SHAREHOLDER'S APARTMENT PER PLANS FILED HEREIN. NO CHANGE TO US… |
| M00900353 ↗ | CLINTON STREET MANHATTAN | Alteration | Signed-off | 08/03/2023 | 05/31/2024 | Design SRW ENGINEERS Owner BERKOWNERS Contractor TECHNICAL COMFORT OF NY* | Installation of a New 4 Ton Heat Pump connected to three indoor inits. Located at each entrance and the middle of the first floor lobby. As… |
| Q00933236 ↗ | 77-11 35 AVENUE QUEENS | Alteration | Signed-off | 09/14/2023 | 10/03/2023 | Design MICHAEL ALMON, ARCHITECT Contractor SIMPLY DIVINE RENOVATION | INTERIOR ALTERATION TO APARTMENT. CONVERTING FROM 1BR TO 2BR. WORK INCLUDES PARTITIONS, DOORS, WALL & FLOOR FINISHES PER PLANS FILED HEREI… |
| Q00921925 ↗ | 110-50 71 ROAD QUEENS | Alteration | Signed-off | 09/14/2023 | 09/25/2023 | Design MICHAEL ALMON, ARCHITECT Contractor XH&RC PLUMBING HEATING | INTERIOR RENOVATION, PARTITIONS, DOORS, CABINETRY, WALL & FLOOR FINISHES - ALL WITHIN DEMISED SHAREHOLDER'S APARTMENT PER PLANS FILED HEREIN… |
| Q00822035 ↗ | 1 STATION SQUARE QUEENS | Alteration | Signed-off | 02/24/2023 | 05/17/2023 | Design MICHAEL ALMON, ARCHITECT Contractor R.J. WELLBROCK INC | NEW & REPLACEMENT DOMESTIC FIXTURES AND HORZ. BRANCH PIPING - CONNECTIONS TO EXISTING BUILDING RISERS |
| M00838647 ↗ | 632 BROADWAY MANHATTAN | Alteration | Signed-off | 03/08/2023 | 04/13/2023 | Design MICHAEL ALMON, ARCHITECT Contractor G.A. PLBG & HTG INC | WORK ON FULL FLOOR SINGLE TENENT OFFICE SUITE. INSTALL OF INTERIOR PARTITIONS, DOORS, FIXTURES, WALL & FLOOR FINISHES AS PER PLANS FILED HER… |
| M00837982 ↗ | 264 WEST 40 STREET MANHATTAN | Alteration | Signed-off | 03/13/2023 | 04/12/2023 | Design MICHAEL ALMON, ARCHITECT Contractor SHAIRA CONSTRUCTION CORP | INTERIOR ALTERATION TO DEMISE FLOOR FOR MULTIPLE TENANTS. INSTALL NON-LOAD BEARING RATED & NON-RATED INTERIOR PARTITIONS, DOORS, FIXTURES, … |
| Q00821977 ↗ | 1 STATION SQUARE QUEENS | Alteration | Signed-off | 02/24/2023 | 04/04/2023 | Design MICHAEL ALMON, ARCHITECT Contractor XH&RC PLUMBING HEATING | INTERIOR ALTERATIONS WITHIN DEMISED APARTMENT UNIT. RELATED PLUMBING WORK TO BE FILED UNDER SEPARATE APPLICATION. NO CHANGE TO OCCUPANCY,… |
| M00776567 ↗ | 627 BROADWAY MANHATTAN | Alteration | Signed-off | 08/12/2022 | 11/04/2022 | Design MICHAEL ALMON, ARCHITECT Contractor SHAIRA CONSTRUCTION CORP | INTERIOR ALTERATIONS OF SINGLE TENANT FLOOR - FULL FLOOR & MEZZ.. INSTALL NON-LOAD BEARING INTERIOR PARTITIONS, DOORS, FIXTURES, WALL & FLOO… |
| M00793980 ↗ | MAIN STREET MANHATTAN | Alteration | Signed-off | 08/29/2022 | 10/31/2022 | Design MICHAEL ALMON, ARCHITECT Contractor TOP DOG PLBG & HTG CORP | REPLACEMENT OF FIXTURES ON EXISTING ROUGHING. DEMO AND REBUILD OF ONE (1) SITE BUILT STALL SHOWER - CONNECT TO EXISTING ROUGHING |
| M00793926 ↗ | MAIN STREET MANHATTAN | Alteration | Signed-off | 08/29/2022 | 10/06/2022 | Design MICHAEL ALMON, ARCHITECT Contractor TWO-TONE GROUP CORP | INTERIOR RENOVATION, PARTITIONS, DOORS, CABINETRY, WALL & FLOOR FINISHES WITHIN DEMISED SHAREHOLDER'S APARTMENT, PER PLANS FILED HEREIN. NO … |
| M00755517 ↗ | MAIN STREET MANHATTAN | Alteration | Signed-off | 06/20/2022 | 07/28/2022 | Design MICHAEL ALMON, ARCHITECT Contractor TOP DOG PLBG & HTG CORP | FILED IN CONJUNCTION WITH M00754733-I1. REPLACEMENT OF 4 FIXTURES ON EXISTING ROUGHING. DEMO AND REBUILD OF ONE (1) SITE BUILT SHOWER STALL… |
| M00754733 ↗ | MAIN STREET MANHATTAN | Alteration | Signed-off | 06/20/2022 | 07/27/2022 | Design MICHAEL ALMON, ARCHITECT Contractor TWO-TONE CONTRACTING CORP | INTERIOR RENOVATION, PARTITIONS, DOORS, CABINETRY, WALL & FLOOR FINISHES WITHIN DEMISED SHAREHOLDER'S APARTMENT, PER PLANS FILED HEREIN. NO… |
| Q00630069 ↗ | 68-38 MANSE STREET QUEENS | Alteration | Signed-off | 11/16/2021 | 04/22/2022 | Design MICHAEL ALMON, ARCHITECT Owner 6838 MANSE STREET Contractor CPJR IMPROVEMENT CORP | MISC. ALTERATION TO (1) FAMILY RESIDENCE. NEW MECHANICAL AS PER PLANS FILED HEREWITH. NO CHANGE TO OCCUMAPNCY, USE, CONSTRUCTION CLASS, EX… |
| Q00481600 ↗ | 39-74 46 STREET QUEENS | Alteration | Signed-off | 06/02/2021 | 04/19/2022 | Design MICHAEL ALMON, ARCHITECT Contractor ROYALTY CONST GROUP INC | INTERIOR RENOVATION OF (1) FAMILY RESIDENCE. NEW MECH. HEAT PUMP IN OSP & FLRS 001, 002. ALTERATION OF DOOR & WINDOW AT REAR W/O CHANGE TO … |
| M00684621 ↗ | 632 BROADWAY MANHATTAN | Alteration | Signed-off | 03/02/2022 | 03/03/2022 | Design MICHAEL ALMON, ARCHITECT Contractor SHAIRA CONSTRUCTION CORP | WORK ON FULL FLOOR SINGLE TENENT OFFICE SUITE. INSTALL OF INTERIOR PARTITIONS, DOORS, FIXTURES, WALL & FLOOR FINISHES AS PER PLANS FILED HER… |
| Q00449924 ↗ | 22-66 24 STREET QUEENS | Alteration | Signed-off | 01/08/2021 | 03/03/2022 | Design MICHAEL ALMON, ARCHITECT Contractor KJH BUILDING & DEV CORP | Renovation and Extension of Detached Garage |
| Q00630265 ↗ | 52-30 39 DRIVE QUEENS | Alteration | Signed-off | 11/19/2021 | 02/15/2022 | Design MICHAEL ALMON, ARCHITECT Contractor DPH PLUMBING & HTG CORP | APPLICATION TO COMBINE APTS. #6D & #6E PER TPPN #03/97. IN APT #6E : REMOVE RANGE & CAP GAS, NEW BAR SINK, TOILET & LAV ON EXIST. ROUGH. RE… |
| Q00639382 ↗ | 68-38 MANSE STREET QUEENS | Alteration | Signed-off | 12/07/2021 | 01/13/2022 | Design MICHAEL ALMON, ARCHITECT Owner 6838 MANSE STREET Contractor BT'S PLUMBING AND HEATING | MISC. ALTERATION TO (1) FAMILY RESIDENCE. REMOVAL OF BOILER & STEAM HEATING SYSTEM. NEW DOMESTIC HWH & FIXTURE CHANGES - NO CHANGE OF OCCU… |
| Q00630190 ↗ | 52-30 39 DRIVE QUEENS | Alteration | Signed-off | 11/19/2021 | 01/05/2022 | Design MICHAEL ALMON, ARCHITECT Contractor OVERALL RENOVATION INC | APPLICATION FILED TO COMBINE APTS #6D & #6E TO CREATE LARGER RESIDENTIAL UNIT. REMOVAL OF PARTITION BETWEEN UNTS AND CONVERSION OF #6E KITC… |
| Q00549454 ↗ | 1 STATION SQUARE QUEENS | Alteration | Signed-off | 07/06/2021 | 10/22/2021 | Design MICHAEL ALMON, ARCHITECT Contractor HORBRIDGE PLUMBING & HEAT | NEW REPLACEMENT FIXTURES ON EXISTING ROUGH AS PER PLANS FILED HEREIN. |
| Q00549292 ↗ | 1 STATION SQUARE QUEENS | Alteration | Signed-off | 07/06/2021 | 10/20/2021 | Design MICHAEL ALMON, ARCHITECT Contractor HORBRIDGE PLUMBING & HEAT | NEW REPLACEMENT FIXTURES ON EXISTING ROUGH AS PER PLANS FILED HEREIN. |
| Q00549416 ↗ | 1 STATION SQUARE QUEENS | Alteration | Signed-off | 07/06/2021 | 10/20/2021 | Design MICHAEL ALMON, ARCHITECT Contractor HORBRIDGE PLUMBING & HEAT | NEW REPLACEMENT FIXTURES ON EXISTING ROUGH AS PER PLANS FILED HEREIN. |
| M00604677 ↗ | 632 BROADWAY MANHATTAN | Alteration | Signed-off | 10/12/2021 | 10/13/2021 | Design MICHAEL ALMON, ARCHITECT Contractor SHAIRA CONSTRUCTION CORP | CONSTRUCTION OF FULL FLOOR SINGLE TENENT OFFICE SUITE. INSTALL OF INTERIOR PARTITIONS, DOORS, FIXTURES, WALL & FLOOR FINISHES AS PER PLANS … |
| Q00548290 ↗ | 1 STATION SQUARE QUEENS | Alteration | Signed-off | 07/08/2021 | 09/08/2021 | Design MICHAEL ALMON, ARCHITECT Contractor TYME CONSTRUCTION CORP | INTERIOR ALTERATIONS WITHIN DEMISED APARTMENT UNIT. REPLACEMENT OF EXTERIOR DOOR & WINDOWS IN EXISTING OPENINGS. RELATED PLUMBING WORK TO BE… |
| Q00549388 ↗ | 1 STATION SQUARE QUEENS | Alteration | Signed-off | 07/06/2021 | 09/08/2021 | Design MICHAEL ALMON, ARCHITECT Contractor TYME CONSTRUCTION CORP | INTERIOR ALTERATIONS WITHIN DEMISED APARTMENT UNIT. REPLACEMENT OF EXTERIOR DOOR & WINDOWS IN EXISTING OPENINGS. RELATED PLUMBING WORK TO BE… |
| Q00549435 ↗ | 1 STATION SQUARE QUEENS | Alteration | Signed-off | 07/06/2021 | 09/08/2021 | Design MICHAEL ALMON, ARCHITECT Contractor TYME CONSTRUCTION CORP | INTERIOR ALTERATIONS WITHIN DEMISED APARTMENT UNIT. REPLACEMENT OF EXTERIOR DOOR & WINDOWS IN EXISTING OPENINGS. RELATED PLUMBING WORK TO BE… |
| Q00481620 ↗ | 39-74 46 STREET QUEENS | Alteration | Signed-off | 06/10/2021 | 08/04/2021 | Design MICHAEL ALMON, ARCHITECT Contractor NICE PLUMBING CORP | NEW SUPPLY, SANITARY, VENT PIPING & FIXTURES. REMOVE EXISTING HW HEATER, STEAM BOILER AND STEAM HEATING SYSTEM AND INSTALL NEW GAS FIRED CO… |
| M00548133 ↗ | 632 BROADWAY MANHATTAN | Alteration | Signed-off | 07/01/2021 | 07/08/2021 | Design MICHAEL ALMON, ARCHITECT Contractor SHAIRA CONSTRUCTION CORP | CONSTRUCTION OF FULL FLOOR SINGLE TENENT OFFICE SUITE. INSTALL OF INTERIOR PARTITIONS, DOORS, FIXTURES, MILLWORK, AND WALL & FLOOR FINISHES… |
| M00535634 ↗ | 62 WEST 45 STREET MANHATTAN | Alteration | Signed-off | 06/10/2021 | 06/17/2021 | Design MICHAEL ALMON, ARCHITECT Contractor SHAIRA CONSTRUCTION CORP | INSTALL OF INTERIOR PARTITIONS, SUSPENDED CEILINGS, MILLWORK, FIXTURES, AND WALL & FLOOR FINISHES AS PER PLANS FILED HEREWITH. INSTALL OF I… |
| M00521965 ↗ | 632 BROADWAY MANHATTAN | Alteration | Signed-off | 05/17/2021 | 05/20/2021 | Design MICHAEL ALMON, ARCHITECT Contractor SHAIRA CONSTRUCTION CORP | CONSTRUCTION OF FULL FLOOR SINGLE TENANT OFFICE SUITE. INSTALLATION OF INTERIOR PARTITIONS, DOORS, FIXTURES, WALL & FLOOR FINISHES, AND MILL… |
| B00407947 ↗ | 682 HUMBOLDT STREET BROOKLYN | Alteration | Signed-off | 10/14/2020 | 11/13/2020 | Design MICHAEL ALMON, ARCHITECT Contractor TMS PLBG & HEATING CORP | RELOCATION OF KITCHEN SINK. INSTALL OF NEW (3) PIECE BATHROOM. NEW UTILITY SINK, WASHING MACHINE & GAS DRYER |
| Building | Filings | Most Recent |
|---|---|---|
| 46-01 39 AVENUE ↗ | 2 | 05/28/2026 |
| 20-25 26 STREET ↗ | 1 | 04/17/2026 |
| 37-33 84 STREET ↗ | 1 | 12/18/2025 |
| 263 WEST END AVENUE ↗ | 1 | 08/06/2024 |
| MAIN STREET ↗ | 7 | 04/22/2024 |
| 110-50 71 ROAD ↗ | 1 | 09/14/2023 |
| 77-11 35 AVENUE ↗ | 1 | 09/14/2023 |
| CLINTON STREET ↗ | 1 | 08/03/2023 |
| 1 STATION SQUARE ↗ | 10 | 06/26/2023 |
| 632 BROADWAY ↗ | 8 | 04/11/2023 |
| 264 WEST 40 STREET ↗ | 1 | 03/13/2023 |
| 627 BROADWAY ↗ | 1 | 08/12/2022 |
| 52-30 39 DRIVE ↗ | 3 | 06/02/2022 |
| 68-38 MANSE STREET ↗ | 3 | 04/25/2022 |
| 62 WEST 45 STREET ↗ | 2 | 04/18/2022 |
| 39-74 46 STREET ↗ | 2 | 06/10/2021 |
| 682 HUMBOLDT STREET ↗ | 2 | 03/16/2021 |
| 22-66 24 STREET ↗ | 1 | 01/08/2021 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 05/21/2026 | Fire-Resistant Penetrations and Joints | 46-01 39 AVENUE | michael almon | special |
| 04/03/2026 | Fire-Resistant Penetrations and Joints | 20-25 26 STREET | michael almon | special |
| 04/03/2026 | Structural Stability – Alterations of existing buildings | 20-25 26 STREET | michael almon | special |
| 04/03/2026 | Final | 20-25 26 STREET | michael almon | progress |
| 04/03/2026 | Energy Code Compliance Inspections | 20-25 26 STREET | michael almon | progress |
| 04/03/2026 | Lighting in dwelling units | 20-25 26 STREET | michael almon | energy_progress |
| 04/03/2026 | Duct leakage testing, insulation and design | 20-25 26 STREET | michael almon | energy_progress |
| 04/03/2026 | Fenestration and door U-factor and product ratings | 20-25 26 STREET | michael almon | energy_progress |
| 08/04/2024 | Final | 263 WEST END AVENUE | michael almon | progress |
| 04/23/2024 | Energy Code Compliance Inspections | 263 WEST END AVENUE | michael almon | progress |
| 04/23/2024 | Fire-Resistant Penetrations and Joints | 263 WEST END AVENUE | michael almon | special |
| 04/23/2024 | Lighting in dwelling units | 263 WEST END AVENUE | michael almon | energy_progress |
| 04/22/2024 | Lighting in dwelling units | MAIN STREET | michael almon | energy_progress |
| 04/12/2024 | Fire-Resistant Penetrations and Joints | MAIN STREET | michael almon | special |
| 04/12/2024 | Final | MAIN STREET | michael almon | progress |
| 04/12/2024 | Energy Code Compliance Inspections | MAIN STREET | michael almon | progress |
| 08/18/2023 | Fire-Resistant Penetrations and Joints | 110-50 71 ROAD | michael almon | special |
| 08/18/2023 | Energy Code Compliance Inspections | 110-50 71 ROAD | michael almon | progress |
| 08/18/2023 | Final | 110-50 71 ROAD | michael almon | progress |
| 07/05/2023 | Lighting in dwelling units | 1 STATION SQUARE | michael almon | energy_progress |
| 07/05/2023 | Final | 1 STATION SQUARE | michael almon | progress |
| 07/05/2023 | Fire-Resistant Penetrations and Joints | 1 STATION SQUARE | michael almon | special |
| 07/05/2023 | Fire-Resistant Penetrations and Joints | 1 STATION SQUARE | michael almon | special |
| 06/15/2023 | Fire-Resistant Penetrations and Joints | 1 STATION SQUARE | michael almon | special |
| 04/04/2023 | Fire-Resistant Penetrations and Joints | 632 BROADWAY | michael almon | special |
| 03/14/2023 | Fire-Resistant Penetrations and Joints | 632 BROADWAY | michael almon | special |
| 03/14/2023 | Final | 632 BROADWAY | michael almon | progress |
| 03/09/2023 | Final | 632 BROADWAY | michael almon | progress |
| 03/09/2023 | Fire-Resistant Penetrations and Joints | 632 BROADWAY | michael almon | special |
| 10/12/2022 | Fire-Resistant Penetrations and Joints | MAIN STREET | michael almon | special |
| 09/29/2022 | Fire-Resistant Penetrations and Joints | MAIN STREET | michael almon | special |
| 09/29/2022 | Energy Code Compliance Inspections | MAIN STREET | michael almon | progress |
| 09/29/2022 | Final | MAIN STREET | michael almon | progress |
| 09/29/2022 | Lighting in dwelling units | MAIN STREET | michael almon | energy_progress |
| 08/08/2022 | Fire-Resistant Penetrations and Joints | 627 BROADWAY | michael almon | special |
| 07/18/2022 | Final | 627 BROADWAY | michael almon | progress |
| 06/09/2022 | Energy Code Compliance Inspections | MAIN STREET | michael almon | progress |
| 06/09/2022 | Final | MAIN STREET | michael almon | progress |
| 06/09/2022 | Fire-Resistant Penetrations and Joints | MAIN STREET | michael almon | special |
| 06/02/2022 | Fire-Resistant Penetrations and Joints | 52-30 39 DRIVE | michael almon | special |
| 06/01/2022 | Fire-Resistant Penetrations and Joints | 52-30 39 DRIVE | michael almon | special |
| 04/19/2022 | Fire-Resistant Penetrations and Joints | 62 WEST 45 STREET | michael almon | special |
| 04/19/2022 | Final | 62 WEST 45 STREET | michael almon | progress |
| 04/19/2022 | Energy Code Compliance Inspections | 62 WEST 45 STREET | michael almon | progress |
| 04/19/2022 | Lighting controls | 62 WEST 45 STREET | michael almon | energy_progress |
| 04/19/2022 | Interior lighting power | 62 WEST 45 STREET | michael almon | energy_progress |
| 04/18/2022 | Fire-Resistant Penetrations and Joints | 62 WEST 45 STREET | michael almon | special |
| 04/18/2022 | Energy Code Compliance Inspections | 62 WEST 45 STREET | michael almon | progress |
| 04/18/2022 | Final | 62 WEST 45 STREET | michael almon | progress |
| 04/18/2022 | Interior lighting power | 62 WEST 45 STREET | michael almon | energy_progress |