← Back
BuildNYC
Condo, residential tower (mixed-use, multi-family elevator) [derived]
Spears Condominium
525 WEST 22ND STREET · BIN 1012329
💬 Discuss this project
1930Year Built
6Stories
RMBuilding Class
M1-5Zoning
88,671 sfGross Floor Area
34Units
LL97 CoveredRent Stabilized16 Active Violations ▸
Condo, residential tower (mixed-use, multi-family elevator) [derived] · 19,503 sf lot · 4.55 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofSpears CondominiumUnder Construction44p · 9 filings · 20 docs
BulkheadElevator modernization5p · 1 filing · 15 docs
PenthouseUnit PHB, Unit PHE19p · 6 filings · 20 docs
Floor 7Spears CondominiumUnder Construction27p · 4 filings · 20 docs
Floor 6Unit 6FUnder Construction41p · 8 filings · 20 docs
Floor 5Spears Condominium16p · 3 filings · 20 docs
Floor 4Spears Condominium6p · 1 filing · 8 docs
Floor 3Key Hall Residence, Unit 3E, Unit S30010p · 2 filings · 16 docs
Floor 2Unit 2E11p · 3 filings · 20 docs
Floor 1Miles McEnery Gallery22p · 9 filings · 20 docs
CellarSpears Condominium6p · 2 filings · 8 docs
Site & exteriorHeavy duty sidewalk shed installation7p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Spears Building Condominium9910/17/2026
Chelsea Warehouse Associates2507/08/2026
Savanna Partners903/21/2026
Shareholder603/21/2026
Turtle Bay Partners203/21/2026
Condominiu203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Outsource Consultants603/21/2026
J. Callahan Consulting303/21/2026
Agouti Construction Consulting203/21/2026
Noel Building Consulting803/21/2026
Metropolis Group403/21/2026
East Coast Expediting803/21/2026
Cornerstone Consulting303/21/2026
Beam Living403/21/2026
Hwangs Building Management103/21/2026
Patuxent Engineering603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Andamio ScaffoldingScaffold1107/08/2026
Opc ManagementGeneral Contractor809/02/2026
Everest ScaffoldingScaffold707/08/2026
Blackstone Heating & ACGeneral Contractor603/21/2026
Gregg NY PlumbingPlumbing510/17/2026
Clover AirGeneral Contractor507/08/2026
Anesis ServicesFire Protection307/08/2026
Alphacraft Construction*General Contractor303/21/2026
A Plus PlumbingPlumbing307/08/2026
Shawmut Woodworking & SupplyGeneral Contractor203/21/2026
Air Depot Commercial RefrigerationGeneral Contractor203/21/2026
AM&G Waterproofingspecialty_contractor207/08/2026
Integrated Project DeliveGeneral Contractor207/08/2026
Mgi Designed InteriorsGeneral Contractor207/08/2026
Velocity Plumbing & HeatingPlumbing107/08/2026
Elpo Electrical ContgElectrical103/22/2026
Moller & Moller Inc.d/B/AElectrical103/21/2026
Copper-City ElectricElectrical103/21/2026
Eis Electric Corp DbaElectrical103/21/2026
Integkral Design & ConstructionGeneral Contractor104/09/2026
Plane Remodeling CompanyGeneral Contractor107/08/2026
Premier InteriorsGeneral Contractor107/08/2026
Up Construction and RestorationGeneral Contractor107/03/2026
Arcon Plumbing SolutionsPlumbing107/08/2026
A + SprinklerFire Protection107/08/2026
Advanced Electric DesignElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
H2 Architects4595208/14/2026
Steel Core Engineering PL1098308/14/2026
H. A. Bader Consultants2332108/21/2025
Crosscheck Inspection Services544107/25/2024
Amaracon Testing & Inspec5842207/22/2024
Fsi Architecture354507/22/2024
SD Testing & Inspection S7010101/25/2024
PSI Agency254201/17/2024
Special Inspection Services1200404/18/2022
Domani Inspection Service843410/17/2019
Building Lifecycle
All (254)Filed (35)Permit Issued (47)Signed Off (20)Violation (47)Inspection (11)Objection (64)Special Inspection (30)
10/16/2026
Permit issued — Plumbing
M00954674-I1-PL
10/13/2026
Signed off — Alteration
Install a new heating/cooling system. No change of use, egress, or occupancy under this application.
M00954780-I1
10/13/2026
Signed off — Alteration
Direct replacement of existing boiler. No change of use, egress, or occupancy under this application.
M00977295-I1
09/16/2026
Objection resolved — Addressed
09/01/2026
Permit issued — Mechanical Systems
M00954780-I1-MS
08/31/2026
Permit issued — Boiler Equipment
M00977295-I1-BE
08/26/2026
Permit issued — General Construction
M00954641-I1-GC
08/26/2026
Objection raised — Scope
08/20/2026
Signed off — Alteration
In conjunction with Interior renovation of existing unit on the 5th Floor. Plumbing work only.
M01074626-I1
08/14/2026
Filed — Alteration
Interior renovation of apartment PHE @ 6th and 7th Floor. Removal and replacement of interior partitions and finish work. No change of use egress or occupancy under this application.
M00954641-P1
08/14/2026
Filed — Alteration
Replacement of bathroom, kitchen, laundry fixtures, and boiler. No change of use, egress, or occupancy under this application.
M00954674-P1
08/14/2026
Filed — Alteration
Install a new heating/cooling system. No change of use, egress, or occupancy under this application.
M00954780-P1
08/05/2026
Signed off — Alteration
M01072723-I1
07/06/2026
Signed off — Alteration
Masonry wall repairs at B-line units, as per plans filed herewith. No change in occupancy, use or egress.
M01042403-I1
07/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alexander Sheyman
07/01/2026
Special inspection requirement — HVAC-R and service water heating equipment
Alexander Sheyman
07/01/2026
Special inspection requirement — Energy Code Compliance Inspections
Alexander Sheyman
07/01/2026
Special inspection requirement — Mechanical Systems
Alexander Sheyman
07/01/2026
Special inspection requirement — Heating Systems
Alexander Sheyman
07/01/2026
Special inspection requirement — Duct leakage testing, insulation and design
Alexander Sheyman
07/01/2026
Special inspection requirement — HVAC-R and service water heating system controls
Alexander Sheyman
07/01/2026
Special inspection requirement — Metering
Alexander Sheyman
07/01/2026
Special inspection requirement — Maintenance information
Alexander Sheyman
07/01/2026
Special inspection requirement — Final
Alexander Sheyman
07/01/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Alexander Sheyman
07/01/2026
Special inspection requirement — Shutoff dampers
Alexander Sheyman
06/11/2026
Signed off — Alteration
Renovation of bathrooms in apartment 3E as per plans file herewith. no change to use, egress or occupancy
M01263015-I1
01/23/2026
Permit issued — General Construction
M01263015-I1-GC
01/05/2026
Objection resolved — Addressed
12/16/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/14/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/29/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
09/02/2025
Objection resolved — Addressed
09/02/2025
Objection resolved — Resolved
08/29/2025
Filed — Alteration
In conjunction with Interior renovation of existing unit on the 5th Floor. Plumbing work only.
M01074626-P1
08/27/2025
Objection raised — Other
08/27/2025
Objection raised — Admin
08/27/2025
Objection raised — Admin
08/27/2025
Objection raised — Other
08/21/2025
Filed — Alteration
Renovation of bathrooms in apartment 3E as per plans file herewith. no change to use, egress or occupancy
M01263015-I1
08/21/2025
Filed — Alteration
Renovation of bathrooms in apartment 3E as per plans file herewith. no change to use, egress or occupancy
M01263015-S1
08/06/2025
Permit issued — Mechanical Systems
M00954780-I1-MS
08/04/2025
Permit issued — General Construction
M00954641-I1-GC
05/30/2025
Permit issued — Plumbing
M00954674-I1-PL
04/16/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/16/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/20/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
12/20/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/13/2024
Permit issued — Plumbing
M01074626-I1-PL
12/10/2024
Permit issued — General Construction
M01072723-I1-GC
10/17/2024
Signed off — Alteration
Structural work associated with roof elevator bulkhead extension. No change in occupancy, use or egress.
M00849189-I1
10/07/2024
Permit issued — Structural
M01042403-I1-ST
10/01/2024
Permit issued — Boiler Equipment
M00977295-I1-BE
09/03/2024
Permit issued — Plumbing
M00954674-I1-PL
09/03/2024
Objection resolved — Addressed
08/23/2024
Objection resolved — Addressed
08/21/2024
Permit issued — Mechanical Systems
M00954780-I1-MS
08/13/2024
Permit issued — General Construction
M00954641-I1-GC
08/05/2024
Objection raised — Other
08/05/2024
Objection raised — Scope
Latest 60 of 254 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedGregg NY Plumbing10/16/2026
DOB NOWMechanical SystemsSigned-offOpc Management09/01/2026
DOB NOWBoiler EquipmentSigned-offGregg NY Plumbing08/31/2026
DOB NOWGeneral ConstructionPermit IssuedOpc Management08/26/2026
DOB NOWGeneral ConstructionSigned-offIntegkral Design Construction01/23/2026
DOB NOWMechanical SystemsSigned-offOpc Management08/06/2025
DOB NOWGeneral ConstructionPermit IssuedOpc Management08/04/2025
DOB NOWPlumbingPermit IssuedGregg NY Plumbing05/30/2025
DOB NOWPlumbingSigned-offArcon Plumbing Solutions12/13/2024
DOB NOWGeneral ConstructionSigned-offPlane Remodeling Company12/10/2024
DOB NOWStructuralSigned-offUp Construction and Restoration10/07/2024
DOB NOWBoiler EquipmentSigned-offGregg NY Plumbing10/01/2024
DOB NOWPlumbingPermit IssuedGregg NY Plumbing09/03/2024
DOB NOWMechanical SystemsSigned-offOpc Management08/21/2024
DOB NOWGeneral ConstructionPermit IssuedOpc Management08/13/2024
DOB NOWMechanical SystemsPermit IssuedAir Depot Commercial Refrigeration02/06/2024
DOB NOWSprinklersSigned-offThomas Fay11/03/2023
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding08/30/2023
DOB NOWStructuralPermit IssuedAM&G Waterproofing07/12/2023
DOB NOWGeneral ConstructionSigned-offAM&G Waterproofing06/15/2023
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding09/02/2022
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding09/02/2022
DOB NOWSprinklersSigned-offThomas Fay04/04/2022
DOB NOWGeneral ConstructionSigned-offPremier Interiors02/16/2022
DOB NOWSprinklersSigned-offThomas Fay12/29/2021
DOB NOWMechanical SystemsSigned-offMgi Designed Interiors11/16/2021
DOB NOWMechanical SystemsSigned-offClover Air11/15/2021
DOB NOWGeneral ConstructionSigned-offMgi Designed Interiors10/25/2021
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding09/29/2021
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding09/29/2021
DOB NOWStructuralSigned-offShawmut Woodworking & Supply09/29/2021
DOB NOWMechanical SystemsSigned-offBlackstone Heating & AC07/30/2021
DOB NOWSupported ScaffoldSigned-offEverest Scaffolding06/08/2021
DOB NOWMechanical SystemsSigned-offBlackstone Heating & AC04/21/2021
DOB NOWPlumbingSigned-offVelocity Plumbing & Heating04/01/2021
DOB NOWGeneral ConstructionSigned-offAlphacraft Construction*03/31/2021
DOB NOWSidewalk ShedSigned-offEverest Scaffolding02/18/2021
DOB NOWMechanical SystemsSigned-offClover Air11/09/2020
DOB NOWPlumbingSigned-offA Plus Plumbing10/28/2020
DOB NOWSupported ScaffoldSigned-offEverest Scaffolding06/11/2020
+ 57 more permits on file
2 projects · most recent 08/14/2026
Heating and Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
08/14/2026Signed-offOpc ManagementHeating and Air Conditioning Systems, Heating Systems
Heat / Cool
Daikin RXTQ60TAVJU 57,000 BTU · Vrf Outdoor ×5
RZQ42TAVJUA 47,000 BTU · Vrf Outdoor ×5
Heating
Navien NHB-080 80,000 BTU · Boiler ×5
01/25/2024Permit IssuedAir Depot Commercial RefrigerationHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MXZ-SM60NAM 60,000 BTU · Condensing Unit ×1
4 projects · most recent 08/14/2026
Water/Sanitary Gas
FiledStatusContractorScope
08/14/2026Permit IssuedSuper Max ConsultingGas, Water/Sanitary
08/29/2025Signed-offArcon Plumbing SolutionsGas, Water/Sanitary
08/21/2025——Water/Sanitary
01/17/2024——Gas, Water/Sanitary
21 projects · most recent 08/18/2026
General Wiring Lighting
FiledStatusContractorScope
08/18/2026Permit IssuedAMC Electrical ServicesGeneral Wiring
08/18/2026Permit IssuedAMC Electrical ServicesGeneral Wiring
05/26/2026CompleteAMC Electrical ServicesGeneral Wiring
02/11/2026CompleteR-2 ElectricGeneral Wiring
10/01/2025Permit IssuedEis Electric Corp DbaGeneral Wiring
12/04/2024Permit IssuedCMY ElectricalGeneral Wiring
10/17/2024CompleteY.S. ElectricGeneral Wiring, Lighting
09/12/2024CompleteRND ElectricGeneral Wiring
06/20/2024CompleteGMJ Electric—
12/16/2023Permit IssuedY.S. ElectricGeneral Wiring
05/31/2023CompleteJam Electrical—
07/25/2022Permit IssuedRobert Chimenti6 meters, 1 new_meters
12/03/2021CompleteElpo Electrical ContgGeneral Wiring
04/20/2021CompleteElpo Electrical ContgGeneral Wiring
04/02/2021CompleteBanner ElectricGeneral Wiring
1 project · most recent 07/22/2024
Masonry
FiledStatusContractorScope
07/22/2024Signed-offUp Construction and RestorationMasonry
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
12/16/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/29/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
04/16/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/16/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/20/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/20/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/14/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/07/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/08/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/09/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 107
DateRequirementInspectorRole
07/01/2026Shutoff dampersAlexander Sheymanenergy_progress
07/01/2026HVAC-R and service water piping design and insulationAlexander Sheymanenergy_progress
07/01/2026Heating SystemsAlexander Sheymanspecial
07/01/2026HVAC-R and service water heating equipmentAlexander Sheymanenergy_progress
07/01/2026Maintenance informationAlexander Sheymanenergy_progress
07/01/2026Duct leakage testing, insulation and designAlexander Sheymanenergy_progress
07/01/2026Energy Code Compliance InspectionsAlexander Sheymanprogress
07/01/2026Mechanical SystemsAlexander Sheymanspecial
07/01/2026HVAC-R and service water heating system controlsAlexander Sheymanenergy_progress
07/01/2026Fire-Resistant Penetrations and JointsAlexander Sheymanspecial
07/01/2026FinalAlexander Sheymanprogress
07/01/2026MeteringAlexander Sheymanenergy_progress
04/26/2024FinalCONNIE PISANIprogress
04/26/2024MasonryCONNIE PISANIspecial
04/26/2024Tenant Protection Plan ComplianceJames Cicalospecial
04/26/2024Structural Stability – Alterations of existing buildingsCONNIE PISANIspecial
04/26/2024Post-installed AnchorsCONNIE PISANIspecial
01/08/2024Energy Code Compliance InspectionsMAURICIO ANDRADEprogress
01/08/2024Fire-Resistant Penetrations and JointsMAURICIO ANDRADEspecial
01/03/2024Energy Code Compliance InspectionsMAURICIO ANDRADEprogress
01/03/2024Fire-Resistance Rated ConstructionMAURICIO ANDRADEprogress
01/03/2024Lighting in dwelling unitsMAURICIO ANDRADEenergy_progress
01/03/2024Lighting controlsMAURICIO ANDRADEenergy_progress
01/03/2024Fire-Resistant Penetrations and JointsMAURICIO ANDRADEspecial
12/14/2023Heating SystemsAlexander Sheymanspecial
Latest 25 of 107.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Key Hall ResidenceResidentialFloor 3
Project M01263015 Alteration · LOC Issued · 08/21/2025
Miles McEnery GalleryArts / Culture / EntertainmentFloor 1
Project M00595310 Alteration · LOC Issued · 10/08/2021
Project M00595394 Alteration · LOC Issued · 10/08/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 978 on file (BIS + DOB NOW)
▸Plans & Drawings35
▸DOB NOWPlans/Sketch25
09/03/2026M00595394-P1Request digital key ↗
09/03/2026M00595394-I1Request digital key ↗
09/03/2026M00595310-I1Request digital key ↗
Showing 3 of 25 on file for this type
▸DOB NOWPlans/Sketch - Plumbing3
09/05/2026M00193583-I1Request digital key ↗
09/04/2026M00448825-I1Request digital key ↗
08/15/2026M00448825-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/15/2026M00193600-I1Request digital key ↗
08/15/2026M00409772-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/04/2026M00353015-I1Request digital key ↗
08/15/2026M00353015-P5Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
08/14/2026M00448262-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00307108-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
08/14/2026M00193615-I1Request digital key ↗
▸Applications & Permits181
▸BISPLAN / WORK APPROVAL APPLICATION94
07/30/2024123508837Open ↗
07/23/2024123508837Open ↗
11/14/2023140940766Open ↗
Showing 3 of 94 on file for this type
▸BISWORK PERMIT APPLICATION84
03/17/2023101959276Open ↗
02/22/2023101959276Open ↗
12/30/2021140940766Open ↗
Showing 3 of 84 on file for this type
▸DOB NOWHPD Certification Letter or CPC Special Permit2
08/13/2026M00409772-I1Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWState DEC Permit1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications198
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION80
03/13/2020123740531Open ↗
03/13/2020123740531Open ↗
03/13/2020123740531Open ↗
Showing 3 of 80 on file for this type
▸DOB NOWProgress Inspector Seal & Signature38
09/27/2026M00849207-P1Open ↗
09/02/2026M00595310-I1Open ↗
09/02/2026M00595310-I1Open ↗
Showing 3 of 38 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature36
09/05/2026M00193583-I1Open ↗
09/05/2026M00307108-I1Open ↗
09/04/2026M00353015-I1Open ↗
Showing 3 of 36 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature22
09/23/2026M00977295-I1Open ↗
09/02/2026M00595310-I1Open ↗
09/02/2026M00595310-I1Open ↗
Showing 3 of 22 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST9
03/10/2020123740531Open ↗
Showing 1 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT7
03/10/2020123740531Open ↗
06/03/2019140849447Open ↗
Showing 2 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
09/02/2020140940766Open ↗
▸Trade Schedules & Equipment82
▸BISSELF-CERT PLUMBING NOTICE27
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 27 on file for this type
▸BISSCHEDULE B - PLUMBING26
10/04/2021123059126Open ↗
03/29/2021123059126Open ↗
03/22/2021123059126Open ↗
Showing 3 of 26 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE17
10/22/2019123043170Open ↗
10/15/2019123043170Open ↗
06/07/2019123043170Open ↗
Showing 3 of 17 on file for this type
▸BISEQUIPMENT USE PERMITS5
11/09/2021123059126Open ↗
08/25/2021123059126Open ↗
03/05/2020123043170Open ↗
Showing 3 of 5 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT4
11/09/2021123059126Open ↗
03/05/2020123043170Open ↗
Showing 2 of 4 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
12/18/2022101959276Open ↗
▸Safety & Tenant Protection83
▸DOB NOWHPD-1: Anti-Harassment Area Checklist35
09/05/2026M00307108-I1Open ↗
09/04/2026M00353015-I1Open ↗
09/04/2026M00448825-I1Open ↗
Showing 3 of 35 on file for this type
▸BISANTI-HARASSMENT CHECKLIST16
03/10/2020123740531Open ↗
Showing 1 of 16 on file for this type
▸BISHPD-1 - Anti-Harassment Area Checklist10
09/02/2020140940766Open ↗
06/03/2019140849447Open ↗
Showing 2 of 10 on file for this type
▸BISTenant Protection Plan and Notes8
08/09/2019123883823Open ↗
09/18/2020140940766Open ↗
06/03/2019140849447Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWTenant Protection Plan4
08/13/2026M00193600-I1Open ↗
08/13/2026M00193615-I1Open ↗
08/13/2026M00193583-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWCertificate of No Harassment4
08/13/2026M00448262-I1Open ↗
08/13/2026M00849207-P1Open ↗
08/13/2026M00409772-I1Open ↗
Showing 3 of 4 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISHPD: SRO MD CERTIFICATE OF NO HARASSMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos64
▸DOB NOWDEP ACP-5: Asbestos Assessment Report29
09/05/2026M00193583-I1Open ↗
09/04/2026M00448825-I1Open ↗
09/03/2026M00594685-I1Open ↗
Showing 3 of 29 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)18
09/17/2020140940766Open ↗
08/09/2019123883823Open ↗
06/03/2019140849447Open ↗
Showing 3 of 18 on file for this type
▸BISTHIS IS NOT AN ASBESTOS PROJECT13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/26/2026M01072723-I1Open ↗
08/13/2026M01074626-I1Open ↗
▸Energy Compliance79
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS38
03/06/2020123043170Open ↗
03/06/2020123043170Open ↗
10/01/2019123883823Open ↗
Showing 3 of 38 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS18
08/25/2021123059126Open ↗
08/25/2021123059126Open ↗
03/06/2020123043170Open ↗
Showing 3 of 18 on file for this type
▸BISTR8: Energy Code Progress Inspections8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)3
08/05/2024123508837Open ↗
01/04/2024140940766Open ↗
12/06/2022123883823Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
08/25/2021123059126Open ↗
08/25/2021123059126Open ↗
09/02/2020140940766Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS3
08/05/2024123508837Open ↗
01/04/2024140940766Open ↗
12/05/2022123883823Open ↗
▸BISTECHNICAL REPORT: ENERGY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.3
09/03/2026M00594685-I1Open ↗
Showing 1 of 3 on file for this type
▸Inspections & Test Reports13
▸BISTECHNICAL REPORT: RESPONSIBILITY9
11/15/2022101959276Open ↗
11/02/2022101959276Open ↗
11/02/2022101959276Open ↗
Showing 3 of 9 on file for this type
▸BISMASONRY2
08/05/2024123508837Open ↗
08/05/2024123508837Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
01/04/2024140940766Open ↗
12/05/2022123883823Open ↗
▸Approvals, Objections & Sign-offs62
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST26
08/14/2024122397940Open ↗
08/07/2024123508837Open ↗
01/08/2024140940766Open ↗
Showing 3 of 26 on file for this type
▸BISADMINISTRATIVE OBJECTIONS13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸DOB NOWHigh Line Parks Approval9
09/05/2026M00307108-I1Open ↗
09/04/2026M00448825-I1Open ↗
08/13/2026M00849207-I1Open ↗
Showing 3 of 9 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
09/18/2020140940766Open ↗
05/11/2020123740531Open ↗
03/06/2020123043170Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
03/31/2023101959276Open ↗
03/17/2023101959276Open ↗
02/14/2023101959276Open ↗
▸BISFINAL3
08/05/2024123508837Open ↗
01/04/2024140940766Open ↗
12/05/2022123883823Open ↗
▸BISSUPERSEDING LETTER2
03/17/2023101959276Open ↗
Showing 1 of 2 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership68
▸BISCOST AFFIDAVIT62
08/13/2024122397940Open ↗
07/22/2024123508837Open ↗
09/07/2022101959276Open ↗
Showing 3 of 62 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW33
08/05/2024123508837Open ↗
01/04/2024140940766Open ↗
12/05/2022123883823Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE2
03/01/2023101959276Open ↗
01/26/2023101959276Open ↗
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
09/17/2020140940766Open ↗
▸Filing & Intake Forms76
▸BISEFILING COVER SHEET33
03/10/2020123740531Open ↗
08/09/2019123883823Open ↗
Showing 2 of 33 on file for this type
▸BISADDITIONAL INFORMATION22
11/21/2023140940766Open ↗
12/29/2020123059126Open ↗
09/18/2020140940766Open ↗
Showing 3 of 22 on file for this type
▸BISBOROUGH INTAKE FORM16
01/17/2023101959276Open ↗
12/21/2022101959276Open ↗
04/27/2020102831562Open ↗
Showing 3 of 16 on file for this type
▸BISeFiling Job Application Cover Sheet5
09/02/2020140940766Open ↗
06/03/2019140849447Open ↗
Showing 2 of 5 on file for this type
▸Other Documents11
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION7
11/23/2020123883823Open ↗
11/16/2020123883823Open ↗
11/16/2020123883823Open ↗
Showing 3 of 7 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSUBSTANTIAL IMPROVEMENT CALCULATIONS1
09/02/2020140940766Open ↗