| Owner | Filings | Most Recent |
|---|---|---|
| HAPPIER | 42 | 07/08/2026 |
| SANO DEMOLITION CORP. | 5 | 03/22/2026 |
| S53 | 14 | 03/22/2026 |
| C&M DRYWALL & ACOUSTIC CO | 11 | 03/22/2026 |
| AMS CONTRACTRO INC. | 1 | 03/22/2026 |
| AMS CONTRACTOR | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/20/2020 | $5.0M | — | ERIKA WAREHOUSE CORP. → S53 LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| INCA ARCHITECTURE PLLC | 3 | 03/10/2026 |
| GEMINI ENGINEERING GROUP | 8 | 08/14/2025 |
| KUSHNER STUDIOS | 2 | 09/05/2024 |
| DON PENN CONSULTING ENGINEER | 3 | 01/03/2023 |
| SYED ENGINEERING, P.C. | 2 | 12/10/2021 |
| ENIGMA ENGINEERING PLLC | 2 | 09/28/2021 |
| H & O ENGINEERING, DPC | 3 | 06/09/2021 |
| KEY CIVIL ENGINEERING PC | 4 | 07/13/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 5 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 15 | 03/21/2026 |
| KUSHNER STUDIOS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| C&M DRYWALL & ACOUSTIC CO | General Contractor | 14 | 07/08/2026 |
| DEVO FIRE PROTECTION INC | Fire Protection | 6 | 07/08/2026 |
| AMS CONTRACTOR INC | General Contractor | 6 | 03/21/2026 |
| SANO DEMOLITION CORP | General Contractor | 3 | 03/21/2026 |
| TESTERMAN PLBG & HTG INC | Plumbing | 3 | 07/08/2026 |
| LEBESS MECHANICAL CORP | General Contractor | 3 | 03/21/2026 |
| AAA'S ELECTL CONTG CORP | Electrical | 2 | 03/22/2026 |
| SLC RESTORATION CORP | General Contractor | 1 | 07/08/2026 |
| KEY CIVIL ENGINEERING P C | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SPECIAL TESTING & CONSULT | 1688 | 13 | 09/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Standpipe | Signed-off | DEVO FIRE PROTECTION INC | 12/02/2025 |
| DOB NOW | Standpipe | Signed-off | DEVO FIRE PROTECTION INC | 08/01/2024 |
| DOB NOW | Standpipe | Signed-off | DEVO FIRE PROTECTION INC | 08/01/2024 |
| DOB NOW | Structural | Signed-off | C&M DRYWALL & ACOUSTIC CO | 07/29/2024 |
| DOB NOW | General Construction | Signed-off | SLC RESTORATION CORP | 05/01/2024 |
| DOB NOW | Curb Cut | Signed-off | C&M DRYWALL & ACOUSTIC CO | 03/21/2024 |
| DOB NOW | Curb Cut | Signed-off | C&M DRYWALL & ACOUSTIC CO | 03/21/2024 |
| DOB NOW | Plumbing | Signed-off | TESTERMAN PLBG & HTG INC | 03/11/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | LEBESS MECHANICAL CORP | 09/20/2022 |
| DOB NOW | Construction Fence | Signed-off | C&M DRYWALL & ACOUSTIC CO | 04/28/2022 |
| DOB NOW | Standpipe | Signed-off | DEVO FIRE PROTECTION INC | 04/08/2022 |
| DOB NOW | Sprinklers | Signed-off | DEVO FIRE PROTECTION INC | 04/06/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | AMS CONTRACTOR INC | 03/23/2022 |
| DOB NOW | Sprinklers | Signed-off | DEVO FIRE PROTECTION INC | 10/12/2021 |
| DOB NOW | Plumbing | Signed-off | TESTERMAN PLBG & HTG INC | 07/30/2021 |
| DOB NOW | Plumbing | Signed-off | TESTERMAN PLBG & HTG INC | 07/28/2021 |
| DOB NOW | Construction Fence | Signed-off | C&M DRYWALL & ACOUSTIC CO | 03/25/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | AMS CONTRACTOR INC | 03/23/2021 |
| DOB NOW | Construction Fence | Signed-off | SANO DEMOLITION CORP | 01/15/2021 |
| BIS | — | ISSUED | C&M DRYWALL & ACOUSTIC CO | 03/20/2024 |
| BIS | — | ISSUED | C&M DRYWALL & ACOUSTIC CO | 05/05/2023 |
| BIS | — | ISSUED | C&M DRYWALL & ACOUSTIC CO | 06/14/2022 |
| BIS | — | ISSUED | C&M DRYWALL & ACOUSTIC CO | 06/14/2022 |
| BIS | — | ISSUED | C&M DRYWALL & ACOUSTIC CO | 04/01/2022 |
| BIS | — | ISSUED | C&M DRYWALL & ACOUSTIC CO | 04/01/2022 |
| BIS | — | ISSUED | C&M DRYWALL & ACOUSTIC CO | 04/08/2021 |
| BIS | — | ISSUED | C&M DRYWALL & ACOUSTIC CO | 04/08/2021 |
| BIS | — | ISSUED | SANO DEMOLITION CORP | 02/05/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/03/2023 | Permit Issued | LEBESS MECHANICAL CORP | Air Conditioning Systems, Generators, Heating Systems, Ventilation Systems | Cooling Mitsubishi Electric PURY-ER-336 336,000 BTU · Vrf Outdoor ×20 Heating Navien NFB-C-301 293,000 BTU · Boiler ×8 Ventilation Aaon RN250 7,575 CFM ×4 Generators Generac SG-100 341,214 BTU · Generator ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2026 | Permit Issued | METHOD ELECTRIC LLC | General Wiring |
| 08/21/2026 | Permit Issued | METHOD ELECTRIC LLC | — |
| 09/24/2024 | Permit Issued | AAA'S ELECTL CONTG CORP | General Wiring |
| 08/23/2024 | Complete | AAA'S ELECTL CONTG CORP | — |
| 10/26/2022 | Permit Issued | AAA'S ELECTL CONTG CORP | 3 meters, 3 new_meters |
| 12/17/2021 | Permit Issued | AAA'S ELECTL CONTG CORP | — |
| 08/19/2021 | Permit Issued | AAA'S ELECTL CONTG CORP | — |
| 03/20/2021 | Complete | RICHARD NEU | — |
| 04/19/2018 | Complete | CORE ELECTRIC MEP INDS LL | 1 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/06/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/06/2024 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 08/06/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 08/01/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/01/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/22/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 03/06/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/21/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/27/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/27/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/13/2022 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/17/2021 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/14/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/10/2021 | Pass-Final PL - Underground | Pass | View ↗ |
| 08/06/2021 | Fail-Final PL - Underground | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/13/2024 | Fire-Resistant Penetrations and Joints | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 09/13/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 09/13/2024 | HVAC and service water heating system controls | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 09/13/2024 | HVAC and service water heating equipment | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 09/10/2024 | Final | EUGENE BIFULCO | progress |
| 07/24/2024 | Post-installed Anchors | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 07/24/2024 | Fire-Resistant Penetrations and Joints | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 07/24/2024 | Sprinkler Systems | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 07/24/2024 | Standpipe Systems | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 07/08/2024 | HVAC and service water heating system controls | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 07/08/2024 | HVAC and service water heating equipment | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 07/08/2024 | Fire-Resistant Penetrations and Joints | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 07/08/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 06/17/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 06/17/2024 | Fire-Resistant Penetrations and Joints | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 06/17/2024 | HVAC and service water heating equipment | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 06/17/2024 | HVAC and service water heating system controls | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 12/07/2022 | Maintenance information | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 12/07/2022 | Permanent certificate | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 12/07/2022 | HVAC insulation and sealing | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 12/07/2022 | Shutoff dampers | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 12/07/2022 | HVAC and service water heating equipment | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 12/07/2022 | HVAC and service water heating system controls | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 12/07/2022 | Fire-Resistant Penetrations and Joints | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 12/07/2022 | Heating Systems | SEBASTIAN SETTEDUCATE JR., P.E | special |