| Owner | Filings | Most Recent |
|---|---|---|
| RESTORING COMMUNITIES HDFC | 19 | 07/08/2026 |
| PLATINUM SERVICES NY | 9 | 07/08/2026 |
| RESTORING COMMUNITIES HOUSING DEVELOPMEN T FUND COR | 4 | 03/22/2026 |
| HOUSING PRESERVATION AND DEV. | 7 | 03/22/2026 |
| HPD -HOUSING PRESERVATION | 1 | 03/22/2026 |
| N.Y.C.HOUSING PRESERVATIO | 6 | 03/22/2026 |
| HOUSING PARSERVATION & DV | 1 | 03/22/2026 |
| NEIGHBORHOOD RESTORE HDFC | 1 | 03/22/2026 |
| SKYWORX CONTRACTING | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| FL&M ENGINEERING DESIGN &INSPECTION | 2 | 11/24/2025 |
| EJC ENGINEERING, PLLC | 12 | 07/27/2023 |
| CHI F. LAU ARCHITECT, P.C. | 1 | 11/30/2022 |
| ASHRAF CORP | 2 | 03/24/2022 |
| MOHAMMAD AHEAD, PE | 1 | 03/10/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| BMB BUILDING CONSULTING | 26 | 03/21/2026 |
| GREEN STUDIO | 4 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PLATINUM SERVICES NY LLC | General Contractor | 5 | 07/08/2026 |
| RAPID CONTRACTING INC | General Contractor | 2 | 03/21/2026 |
| A.A.D. CONSTRUCTION CORP | General Contractor | 2 | 07/08/2026 |
| PLBG P & H INC | Plumbing | 1 | 07/08/2026 |
| MC SUPERSTRUCTURE INC | General Contractor | 1 | 04/09/2026 |
| BRUCHE MECHANICAL NY LLC | Fire Protection | 1 | 07/08/2026 |
| AMR ELEC'L CONTRG CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| METRIC CONSULTING AND INS | 1803 | 12 | 07/27/2023 |
| URBAN ARCHITECTURAL INITI | 8064 | 12 | 07/27/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | MC SUPERSTRUCTURE INC | 10/17/2025 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 05/16/2023 |
| DOB NOW | Construction Fence | Signed-off | A.A.D. CONSTRUCTION CORP | 12/29/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 07/18/2022 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 03/24/2022 |
| DOB NOW | Supported Scaffold | Signed-off | RAPID CONTRACTING INC | 03/10/2022 |
| DOB NOW | Sprinklers | Signed-off | BRUCHE MECHANICAL NY LLC | 02/12/2022 |
| DOB NOW | Mechanical Systems | Signed-off | A.A.D. CONSTRUCTION CORP | 11/24/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 07/26/2021 |
| BIS | — | ISSUED | A.A.D. CONSTRUCTION CORP | 02/22/2023 |
| BIS | — | ISSUED | A.A.D. CONSTRUCTION CORP | 08/09/2022 |
| BIS | — | ISSUED | A.A.D. CONSTRUCTION CORP | 11/24/2021 |
| BIS | EQ | ISSUED | SKYWORX CONTRACTING INC | 09/06/2013 |
| BIS | FB | ISSUED | DUAL FUEL PLUMBING AND HEATING | 11/10/1997 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/13/2025 | Permit Issued | SOLAS ELECTRICAL CORP | — |
| 10/15/2025 | Permit Issued | NASH ELECTRIC SERVICES IN | — |
| 12/02/2023 | Complete | AMR ELEC'L CONTRG CORP | General Wiring |
| 07/20/2021 | Complete | ILLUMINOUS ELECTRIC CORP. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/24/2025 | Permit Issued | MC SUPERSTRUCTURE INC | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/04/2023 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 10/04/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/21/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/08/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 07/17/2023 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 07/10/2023 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 07/10/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/07/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/07/2023 | Fire-Resistant Penetrations and Joints | Jorge Chang | special |
| 08/07/2023 | HVAC insulation and sealing | SEAN BRENNAN | energy_progress |
| 08/07/2023 | Energy Code Compliance Inspections | SEAN BRENNAN | progress |
| 08/07/2023 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 07/18/2023 | HVAC insulation and sealing | SEAN BRENNAN | energy_progress |
| 07/18/2023 | Fire-Resistant Penetrations and Joints | Jorge Chang | special |
| 07/18/2023 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 07/18/2023 | Energy Code Compliance Inspections | SEAN BRENNAN | progress |
| 05/02/2023 | Fire-Resistant Penetrations and Joints | Jorge Chang | special |
| 05/02/2023 | HVAC insulation and sealing | SEAN BRENNAN | energy_progress |
| 05/02/2023 | Energy Code Compliance Inspections | SEAN BRENNAN | progress |
| 05/02/2023 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 01/25/2023 | Final | Jorge Chang | progress |
| 01/25/2023 | Fire-Resistant Penetrations and Joints | Jorge Chang | special |
| 01/25/2023 | Heating Systems | SAMI HAJJAR P.E | special |
| 01/25/2023 | Mechanical Systems | SAMI HAJJAR P.E | special |
| 01/25/2023 | Energy Code Compliance Inspections | SEAN BRENNAN | progress |
| 01/25/2023 | Maintenance information | SEAN BRENNAN | energy_progress |
| 01/25/2023 | HVAC insulation and sealing | SEAN BRENNAN | energy_progress |
| 01/25/2023 | HVAC and service water heating system controls | SEAN BRENNAN | energy_progress |
| 01/25/2023 | HVAC and service water heating equipment | SEAN BRENNAN | energy_progress |
| 11/08/2022 | HVAC insulation and sealing | SEAN BRENNAN | energy_progress |
| 11/08/2022 | Fire-Resistant Penetrations and Joints | Jorge Chang | special |
| 11/08/2022 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 11/08/2022 | Energy Code Compliance Inspections | SEAN BRENNAN | progress |