| Owner | Filings | Most Recent |
|---|---|---|
| ZEZE HOLDINGS, LLC | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/22/2025 | $2.2M | — | Private party → 534 WEST 149TH STREET LLC | $646/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NKM ENGINEERING PLLC | 1 | 05/26/2026 |
| BARRY STRUCTURAL ENGINEERING, PLLC | 1 | 01/07/2026 |
| OSTERMIER ARCHITECTURE PLLC | 3 | 10/02/2025 |
| TSS ENGINEERS | 1 | 10/02/2025 |
| FRANK PIZZURRO ARCHITECTS PC | 1 | 03/22/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| CAVALRY LLC | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| VESTA CONSTRUCTION, INC | General Contractor | 3 | 07/08/2026 |
| W3M INC | General Contractor | 3 | 03/21/2026 |
| MEGA PLBG CORP | Fire Protection | 1 | 07/08/2026 |
| BROOKLYN SOLARWORKS LLC | General Contractor | 1 | 07/08/2026 |
| NICE PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 1 | 05/26/2026 |
| BARRY STRUCTURAL ENGINEER | 749 | 1 | 01/07/2026 |
| CHUN ENGINEERING CONSULTA | 9605 | 1 | 10/02/2025 |
| TSS ENGINEERS | 4492 | 2 | 10/02/2025 |
| FP ARCHITECTS PC | 2734 | 1 | 03/22/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | BROOKLYN SOLARWORKS LLC | 05/28/2026 |
| DOB NOW | Structural | Permit Issued | VESTA CONSTRUCTION, INC | 03/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | VESTA CONSTRUCTION, INC | 03/03/2026 |
| DOB NOW | Plumbing | Permit Issued | NICE PLUMBING CORP | 02/26/2026 |
| DOB NOW | Sprinklers | Permit Issued | REAL PLUMBING CORP | 02/26/2026 |
| DOB NOW | General Construction | Permit Issued | VESTA CONSTRUCTION, INC | 02/20/2026 |
| DOB NOW | General Construction | Signed-off | W3M INC | 04/17/2024 |
| BIS | — | ISSUED | S.MACEDO CONSTRUCTION CORP | 03/18/2004 |
| BIS | — | ISSUED | S.MACEDO CONSTRUCTION CORP | 01/08/2004 |
| BIS | PL | ISSUED | QUEENS, THE MECHANICAL CORP | 04/10/2003 |
| BIS | OT | ISSUED | METROTRANS CONSTRUCTION | 06/23/1999 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/07/2026 | Permit Issued | VESTA CONSTRUCTION, INC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-2C-20 NAHZ4 22,000 BTU · Condensing Unit ×1 MXZ-3C-30NAHZ4 27,600 BTU · Condensing Unit ×1 MXZ-SM 48NAMHZ2 48,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2026 | Permit Issued | REAL PLUMBING CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2026 | Permit Issued | NICE PLUMBING CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/21/2026 | Permit Issued | BROOKYLN SOLARWORKS, LLC | — |
| 03/23/2026 | Permit Issued | A.L. ELECTRICAL CORP. | 2 meters, 2 new_meters |
| 02/12/2026 | Permit Issued | A.L. ELECTRICAL CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2026 | Permit Issued | VESTA CONSTRUCTION, INC | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/26/2026 | Permit Issued | BROOKLYN SOLARWORKS LLC | 10 panels, 4.4 kw, 851 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/04/2026 | Preliminary | bassam (sam) rimawi | progress |
| 01/29/2026 | Structural Steel - Details | MICHAEL BARRY | special |
| 01/29/2026 | Structural Steel - High Strength Bolting | MICHAEL BARRY | special |
| 01/27/2026 | Permanent certificate | bassam (sam) rimawi | energy_progress |
| 01/27/2026 | Shutoff dampers | bassam (sam) rimawi | energy_progress |
| 01/27/2026 | Duct leakage testing, insulation and design | bassam (sam) rimawi | energy_progress |
| 01/05/2026 | Construction Utilizing CLT or SCL, Type IV | MICHAEL BARRY | special |
| 12/29/2025 | Heating Systems | bassam (sam) rimawi | special |
| 12/29/2025 | Permanent certificate | CHRISTINA OSTERMIER | energy_progress |
| 12/29/2025 | Fire-Resistant Penetrations and Joints | bassam (sam) rimawi | special |
| 12/23/2025 | Lighting controls | JAMES CHUN | energy_progress |
| 10/01/2025 | Fire-Resistant Penetrations and Joints | bassam (sam) rimawi | special |
| 09/30/2025 | Final | bassam (sam) rimawi | progress |
| 09/30/2025 | HVAC-R and service water heating system controls | bassam (sam) rimawi | energy_progress |
| 09/30/2025 | HVAC-R and service water heating equipment | bassam (sam) rimawi | energy_progress |
| 09/30/2025 | HVAC-R and service water piping design and insulation | bassam (sam) rimawi | energy_progress |
| 09/30/2025 | Maintenance information | bassam (sam) rimawi | energy_progress |
| 09/30/2025 | Sprinkler Systems | bassam (sam) rimawi | special |
| 09/30/2025 | Final | MICHAEL BARRY | progress |
| 09/30/2025 | Fire-Resistant Penetrations and Joints | JAMES CHUN | special |
| 09/30/2025 | Energy Code Compliance Inspections | JAMES CHUN | progress |
| 09/30/2025 | Fire-Resistance Rated Construction | JAMES CHUN | progress |
| 09/30/2025 | Interior lighting power | JAMES CHUN | energy_progress |
| 09/30/2025 | Fenestration air leakage | JAMES CHUN | energy_progress |
| 09/30/2025 | Lighting in dwelling units | JAMES CHUN | energy_progress |