Whole building & multi-floor projectsStair E feature wall modifications4 filings
General construction modifications taking place on the 2-12th floors (Stair E Feature Wall) as per plans filed herewith. No change in use, egress or occupancy
On file for this project
6 documents
INSTALLATION OF A TEMPORARY SCAFFOLD ACCESS PLATFORMS & ART WALL SUPPORT AS PER PLANS DURING RENOVATION OF THE EXISTING BUILDING. NO CHANGE IN USE, EGRESS OR OCCUPATION. SCAFFOLD TO COMPLY WITH 2014 NYC BUILDING CODE, CHAPTER 33
On file for this project
3 documents
INSTALLATION OF A SHAFT PLATFORM AS PER PLANS DURING GENERAL CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SHAFT PLATFORM TO COMPLY WITH 2014 NYC BUILDING CODE, CHAPTER 33.
On file for this project
3 documents
Latest 3 of 4 filings on this floor.
RoofOxford Properties19p · 16 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods · Structural
Sprinkler modifications taking place on the 4th fl as per plans filed herewith. No change in use, egress or occupancy
On file for this project
8 documents · 1 drawing sheet
Mechanical modifications taking place on the 2nd floor & roof (associated to 2nd fl work only) as per plans filed herewith. No change in use, egress or occupancy
On file for this project
18 documents · 4 drawing sheets
General construction modifications taking place on the 2nd floor & roof (associated to 2nd floor work only) as per plans filed herewith. No change in use, egress or occupancy
On file for this project
21 documents · 2 drawing sheets
Latest 3 of 16 filings on this floor.
Floor 12Oxford Properties50p · 15 filings · 20 docs
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold
General construction modifications taking place on the Cellar & 12th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
5 documents · 3 drawing sheets
Sprinkler modifications taking place on the 12th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
9 documents · 4 drawing sheets
Structural modifications taking place on the 12th floor Terrace as per plans filed herewith. No change in use, egress or occupancy
On file for this project
22 documents · 4 drawing sheets
Latest 3 of 15 filings on this floor.
Floor 11GoogleUnder Construction71p · 17 filings · 20 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
Standpipe modifications taking place on the 11th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
1 document · 3 drawing sheets
Sprinkler modifications taking place on the 11th fl as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 6 drawing sheets
General construction modifications taking place on the 11th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
6 documents · 21 drawing sheets
Latest 3 of 17 filings on this floor.
Floor 10Oxford Properties31p · 7 filings · 20 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
plumbing modifications taking place on the 10th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
5 documents · 3 drawing sheets
Sprinkler modifications taking place on the 10th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
9 documents · 4 drawing sheets
Standpipe modifications taking place on the 10 floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
5 documents · 3 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 9Oxford Properties48p · 9 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
Sprinkler modifications taking place on the 9th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
10 documents · 6 drawing sheets
Standpipe modifications taking place on the 9th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
5 documents · 3 drawing sheets
Mechanical modifications taking place on the 9th floor & roof (associated to 9th fl scope) as per plans filed herewith. No change in use, egress or occupancy
On file for this project
18 documents · 10 drawing sheets
Latest 3 of 9 filings on this floor.
Floor 88th floor sprinkler modifications31p · 7 filings · 14 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
Sprinkler modifications taking place on the 8th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
10 documents · 3 drawing sheets
General construction modifications taking place on the 8th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
13 documents · 9 drawing sheets
Structural modifications taking place on the 8th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
11 documents · 3 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 7Structural scope for new mechanical units and partitions29p · 7 filings · 14 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
General construction modifications taking place on the 7th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
14 documents · 14 drawing sheets
Structural modifications taking place on the 7th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
5 documents · 3 drawing sheets
Mechanical modifications taking place on the 7th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
15 documents · 6 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 6Oxford Properties46p · 9 filings · 14 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
General construction modifications taking place on the 6th floor & roof (only work associated 6ht fl) to as per plans filed herewith. No change in use, egress or occupancy
On file for this project
28 documents · 28 drawing sheets
Mechanical modifications taking place on the 6th floor & roof (work associated to 6th fll scope) as per plans filed herewith. No change in use, egress or occupancy
On file for this project
25 documents · 6 drawing sheets
Structural modifications taking place on the 6th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
11 documents · 3 drawing sheets
Latest 3 of 9 filings on this floor.
Floor 5Oxford Properties41p · 13 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
Sprinkler modifications taking place in the Cellar as per plans filed herewith. No change in use, egress or occupancy
On file for this project
10 documents · 1 drawing sheet
Sprinkler modifications taking place on the 5th floor per plans filed herewith. No change in use, egress or occupancy
On file for this project
8 documents · 3 drawing sheets
Standpipe modifications taking place on the 5th floor per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 3 drawing sheets
Latest 3 of 13 filings on this floor.
Floor 4Oxford Properties73p · 24 filings · 20 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
plumbing modifications taking place on the 4th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
3 documents · 1 drawing sheet
General construction modifications taking place on the 4th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
3 documents · 8 drawing sheets
Sprinkler modifications taking place on the 4th fl as per plans filed herewith. No change in use, egress or occupancy
On file for this project
8 documents · 1 drawing sheet
Latest 3 of 24 filings on this floor.
Floor 3Oxford Properties92p · 20 filings · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
Sprinkler modifications taking place on the 3rd floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
10 documents · 7 drawing sheets
Standpipe modifications taking place on the 3rd floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 5 drawing sheets
Sprinkler modifications taking place on the 3rd & 4th floors as per plans filed herewith. No change in use, egress or occupancy
On file for this project
8 documents · 3 drawing sheets
Latest 3 of 20 filings on this floor.
Floor 2GoogleUnder Construction60p · 22 filings · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
Structural modifications taking place on the 2nd floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
33 documents · 34 drawing sheets
Sprinkler modifications taking place on the 2nd floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
7 documents · 1 drawing sheet
Standpipe modifications taking place on the 2nd floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 22 filings on this floor.
Floor 1Oxford PropertiesUnder Construction98p · 25 filings · 20 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Curb Cut · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
General construction modifications taking place on the 1st floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 3 drawing sheets
plumbing modifications taking place on the 1st floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
5 documents · 1 drawing sheet
Structural modifications taking place on the 1st floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 25 filings on this floor.
MezzanineOxford Properties17p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Sprinkler modifications taking place on the Mezzanine as per plans filed herewith. No change in use, egress or occupancy
On file for this project
10 documents · 2 drawing sheets
General construction modifications taking place on the Mezzanine as per plans filed herewith. No change in use, egress or occupancy
On file for this project
15 documents · 5 drawing sheets
Structural modifications taking place on the Mezzanine as per plans filed herewith. No change in use, egress or occupancy
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
CellarOxford Properties55p · 14 filings · 20 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
Sprinkler modifications taking place in the Cellar as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents
General construction modifications taking place on the Cellar & 12th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
5 documents · 11 drawing sheets
Mechanical modifications taking place in the Cellar as per plans filed herewith. No change in use, egress or occupancy
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 14 filings on this floor.
Site & exteriorGoogle12 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Plumbing · Sidewalk Shed · Sign · Supported Scaffold
INSTALL NON-ILLUMINATED EXTERIOR SIGN ON WALL (GOOGLE)
On file for this project
2 documents · 3 drawing sheets
INSTALLATION OF PLYWOOD FENCE, AS PER DRAWINGS. PLYWOOD FENCE SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
10 documents · 12 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED DURING BUILDING ALTERATION, FILED SEPARATELY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED TO BE INSTALLED ON ROADWAY. DOT PERMITS BY OTHERS.
On file for this project
14 documents · 12 drawing sheets
Latest 3 of 12 filings on this floor.