← Back
BuildNYC
Elevator apt, fireproof with stores
Oskar
572 11TH AVENUE · BIN 1090460
💬 Discuss this project
2016Year Built
13Stories
D6Building Class
R9Zoning
184,117 sfGross Floor Area
165Units
LL97 CoveredRent Stabilized17 Active Violations ▸FISP: SWARMP
Elevator apt, fireproof with stores · Owner of record: VHH Oskar · 16,969 sf lot · 10.85 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsWaterproofing1 filing
RoofTemporary pipe scaffold installation1p · 1 filing · 3 docs
Floor 1The Learning Experience15p · 8 filings · 20 docs
CellarThe Learning Experience2p · 3 filings · 20 docs
Site & exteriorNail Studio Lure3 filings · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Mezuyon8804/09/2026
The Moinian Group4907/08/2026
VHH Oskar203/22/2026
Midtown Market Diner203/21/2026
Diner 43103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SNR Expediting Design403/21/2026
Synergy Building Consultants203/21/2026
William Vitacco Associates803/21/2026
EA Design Group603/21/2026
AE Design Solution203/21/2026
Louis Striar203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Thesquare NYCGeneral Contractor407/08/2026
Zaq ConstructionGeneral Contractor307/08/2026
Bedrock Plumbing & HeatingPlumbing207/08/2026
Reliable EnterprisesScaffold203/21/2026
Plescia Construction & DevelopmentGeneral Contractor107/08/2026
Blue Jay ContractingScaffold104/09/2026
Everest ScaffoldingScaffold107/08/2026
A1 SpecializedSign hanger105/29/2026
Agius Plumbing & HeatingPlumbing107/08/2026
Expert Fire SprinklerFire Protection107/08/2026
HP ServicesPlumbing107/08/2026
PSI PartnersFire Protection107/08/2026
Abmg General ContractingGeneral Contractor107/08/2026
Blue Jay ContractingGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
KZ Engineering4665208/26/2025
Versai8133206/11/2025
TL Engineering1222605/02/2025
Jack Green Associates422401/14/2025
M/P/S Engineering1588110/15/2020
Special Testing & Consulting1688103/11/2020
Building Lifecycle
All (165)Filed (22)Permit Issued (18)Signed Off (15)Facade (FISP) (3)Violation (60)Inspection (13)Objection (4)Special Inspection (30)
08/14/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/27/2026
Signed off — Alteration
ILLUMINATED NON-ADVERTISING ACCESSORY WALL SIGN - NAIL STUDIO LURE. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
M01224231-I1
05/11/2026
Permit issued — Sign
M01224231-I1-SG
05/11/2026
Violation issued (HPD, open)
B
05/11/2026
Violation issued (HPD, open)
B
05/11/2026
Violation issued (HPD, open)
B
03/07/2026
Violation issued (HPD, open)
B
02/13/2026
Signed off — Alteration
Installation of suspended scaffold for facade inspection/ repair.
M01229628-I1
01/21/2026
Signed off — Alteration
M01239373-I1
11/26/2025
Violation issued (HPD, closed)
B
10/28/2025
Violation issued (HPD, open)
A
10/28/2025
Violation issued (HPD, closed)
B
10/28/2025
Violation issued (HPD, open)
B
10/28/2025
Violation issued (HPD, closed)
B
08/29/2025
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01279122-I1
08/29/2025
Permit issued — Supported Scaffold
M01279122-I1-SF
08/28/2025
Special inspection requirement — Post-installed Anchors
Karol Zdancewicz
08/28/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Karol Zdancewicz
08/27/2025
Objection raised — Other
08/27/2025
Objection resolved — Addressed
08/26/2025
Filed — Alteration
Installation of suspended scaffold for facade inspection/ repair.
M01229628-P1
08/25/2025
Special inspection requirement — Post-installed Anchors
Karol Zdancewicz
08/25/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Karol Zdancewicz
06/27/2025
Signed off — Alteration
SPRINKLERS WORK FOR NAIL SALON ON FIRST FLOOR AT EXISTING 13-STORY MIXED USE BUILDING. NO CHANGE IN USE, OCCUPANCY, EGRESS AND STRUCTURE UNDER THIS APPLICATION.
M01115945-S3
06/24/2025
Permit issued — General Construction
M01239373-I1-GC
06/11/2025
Filed — Alteration
M01239373-I1
06/03/2025
Signed off — Alteration
SPRINKLERS WORK FOR NAIL SALON ON FIRST FLOOR AT EXISTING 13-STORY MIXED USE BUILDING. NO CHANGE IN USE, OCCUPANCY, EGRESS AND STRUCTURE UNDER THIS APPLICATION.
M01115945-S1
05/22/2025
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01230139-I1
05/22/2025
Permit issued — Sidewalk Shed
M01230139-I1-SH
05/22/2025
Permit issued — Suspended Scaffold
M01229628-I1-SC
05/22/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/21/2025
Filed — Alteration
Installation of suspended scaffold for facade inspection/ repair.
M01229628-I1
05/20/2025
Violation issued (ECB, closed)
Local Law
05/19/2025
Filed — Alteration
ILLUMINATED NON-ADVERTISING ACCESSORY WALL SIGN - NAIL STUDIO LURE. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
M01224231-I1
05/19/2025
Signed off — Alteration
SPRINKLERS WORK FOR NAIL SALON ON FIRST FLOOR AT EXISTING 13-STORY MIXED USE BUILDING. NO CHANGE IN USE, OCCUPANCY, EGRESS AND STRUCTURE UNDER THIS APPLICATION.
M01115945-I1
05/19/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/16/2025
Signed off — Alteration
SPRINKLERS WORK FOR NAIL SALON ON FIRST FLOOR AT EXISTING 13-STORY MIXED USE BUILDING. NO CHANGE IN USE, OCCUPANCY, EGRESS AND STRUCTURE UNDER THIS APPLICATION.
M01115945-S2
05/14/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
05/09/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/05/2025
Special inspection requirement — Tenant Protection Plan Compliance
Simon Lee
05/05/2025
Special inspection requirement — Interior lighting power
Simon Lee
05/05/2025
Special inspection requirement — Lighting controls
Simon Lee
05/05/2025
Special inspection requirement — Energy Code Compliance Inspections
Simon Lee
05/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Simon Lee
05/02/2025
Filed — Alteration
SPRINKLERS WORK FOR NAIL SALON ON FIRST FLOOR AT EXISTING 13-STORY MIXED USE BUILDING. NO CHANGE IN USE, OCCUPANCY, EGRESS AND STRUCTURE UNDER THIS APPLICATION.
M01115945-P3
04/29/2025
Filed — Alteration
SPRINKLERS WORK FOR NAIL SALON ON FIRST FLOOR AT EXISTING 13-STORY MIXED USE BUILDING. NO CHANGE IN USE, OCCUPANCY, EGRESS AND STRUCTURE UNDER THIS APPLICATION.
M01115945-P1
04/29/2025
Filed — Alteration
SPRINKLERS WORK FOR NAIL SALON ON FIRST FLOOR AT EXISTING 13-STORY MIXED USE BUILDING. NO CHANGE IN USE, OCCUPANCY, EGRESS AND STRUCTURE UNDER THIS APPLICATION.
M01115945-P2
04/23/2025
Special inspection requirement — Energy Code Compliance Inspections
Simon Lee
04/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Simon Lee
04/23/2025
Special inspection requirement — Duct leakage testing, insulation and design
04/23/2025
Special inspection requirement — Tenant Protection Plan Compliance
04/23/2025
Special inspection requirement — Mechanical Systems
Simon Lee
04/23/2025
Special inspection requirement — Final
Simon Lee
04/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Simon Lee
04/21/2025
Special inspection requirement — Energy Code Compliance Inspections
Simon Lee
04/21/2025
Special inspection requirement — Interior lighting power
04/21/2025
Special inspection requirement — Lighting controls
04/21/2025
Special inspection requirement — Tenant Protection Plan Compliance
04/14/2025
Signed off — Alteration
APPLICATION FILED FOR MECHANICAL MODIFICATIONS/ADDITIONS ON THE 1ST FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01113048-S1
03/28/2025
Signed off — Alteration
Removal of a portion of the existing facade glass, to install a new entry for a retail space
M01159427-I1
Latest 60 of 165 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSignSigned-offMad Signs05/11/2026
DOB NOWSupported ScaffoldPermit IssuedBlue Jay Contracting08/29/2025
DOB NOWGeneral ConstructionSigned-offBlue Jay Contracting06/24/2025
DOB NOWSidewalk ShedPermit IssuedReliable Enterprises05/22/2025
DOB NOWSuspended ScaffoldSigned-offSHR3 Construction05/22/2025
DOB NOWGeneral ConstructionSigned-offPlescia Construction & Development03/18/2025
DOB NOWGeneral ConstructionSigned-offZaq Construction11/24/2024
DOB NOWMechanical SystemsSigned-offThesquare NYC11/19/2024
DOB NOWMechanical SystemsSigned-offZaq Construction11/13/2024
DOB NOWPlumbingSigned-offHP Services11/13/2024
DOB NOWSprinklersSigned-offExpert Fire Sprinkler11/13/2024
DOB NOWPlumbingSigned-offAgius Plumbing & Heating10/25/2024
DOB NOWGeneral ConstructionSigned-offThesquare NYC10/21/2024
DOB NOWPlumbingSigned-offBedrock Plumbing & Heating03/30/2022
DOB NOWSprinklersSigned-offMora Fire Protection03/02/2022
DOB NOWPlumbingSigned-offBedrock Plumbing & Heating03/30/2020
DOB NOWMechanical SystemsSigned-offAbmg General Contracting03/27/2020
DOB NOWSupported ScaffoldSigned-offEverest Scaffolding10/05/2018
BISOTISSUEDAbmg General Contracting04/01/2021
BISOTISSUEDAbmg General Contracting04/01/2021
BISOTISSUEDProduction Contracting04/27/2020
BISOTISSUEDAbmg General Contracting04/16/2020
BISOTISSUEDAbmg General Contracting04/16/2020
BISSDISSUEDHeadquarters Mechanical12/04/2019
BISSPISSUEDPlumbing NYC10/11/2019
BISPLISSUEDSchumacher & Farley P&H10/01/2019
BISOTISSUEDProduction Contracting06/10/2019
BISPLISSUEDHeadquarters Mechanical05/09/2019
BIS—RE-ISSUEDTishman Construction09/19/2018
BISSPISSUEDPrecision Plumbing Services07/30/2018
BISEQISSUEDTishman Construction06/21/2018
BISSDISSUEDHeadquarters Mechanical04/06/2018
BISOTISSUEDTishman Construction03/19/2018
BISEQISSUEDSafway Atlantic03/07/2018
BISPLISSUEDHeadquarters Mechanical03/01/2018
BISEQISSUEDSafway Atlantic01/31/2018
BISEQISSUEDSafway Atlantic01/23/2018
BISSDISSUEDHeadquarters Mechanical01/09/2018
BISBLISSUEDG.bassolino Plumbing12/29/2017
BISOTISSUEDTishman Construction12/22/2017
+ 28 more permits on file
12 projects · most recent 03/11/2026
General Wiring
FiledStatusContractorScope
03/11/2026Permit IssuedA Electrical Main Service—
05/22/2025Permit IssuedRichard Neu—
01/15/2025CompleteAsko Electric Construction & MaintenanceGeneral Wiring
10/30/2024CompleteRonan ElectricalGeneral Wiring
09/11/2024Permit IssuedOmd Electrical1 meters, 1 new_meters
02/25/2022Permit IssuedTop Shelf ElectricGeneral Wiring
04/19/2020Permit IssuedRem & Sons Lic Electric ContGeneral Wiring
10/09/2019CompleteTop Shelf Electric6 meters, 1 new_meters
10/02/2019CompleteM.C. Electrical NYGeneral Wiring
09/27/2019CompleteM.C. Electrical NY—
07/29/2019CompleteTop Shelf Electric6 meters
02/01/2019CompleteTop Shelf ElectricGeneral Wiring
2 projects · most recent 08/29/2025
Scaffold Sidewalk Shed
FiledStatusContractorScope
08/29/2025Permit IssuedBlue Jay ContractingScaffold
05/22/2025Permit IssuedReliable EnterprisesSidewalk Shed
▾Field Inspections (DOB CAP) — 13
DateTypeResultReport
08/14/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/22/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/19/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/14/2025Pass-Final General Construction Non-Directive 14PassView ↗
05/09/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/27/2025Certified Water and Sanitary-WS-Sanitary Piping-Water TestCertifiedView ↗
03/20/2025Certified Water and Sanitary-WS-Sanitary Piping-Water TestCertifiedView ↗
03/17/2025Certified Sprinkler (PL)-SP-Fixtures (PL)-FinishCertifiedView ↗
03/17/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/12/2025Certified Water and Sanitary-WS-Sanitary Piping-Water TestCertifiedView ↗
02/24/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/25/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/24/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 50
DateRequirementInspectorRole
08/28/2025Post-installed AnchorsKarol Zdancewiczspecial
08/28/2025Alternative Materials - OTCR Buildings Bulletin NumberKarol Zdancewiczspecial
08/25/2025Post-installed AnchorsKarol Zdancewiczspecial
08/25/2025Alternative Materials - OTCR Buildings Bulletin NumberKarol Zdancewiczspecial
05/05/2025Tenant Protection Plan ComplianceSimon Leespecial
05/05/2025Interior lighting powerSimon Leeenergy_progress
05/05/2025Lighting controlsSimon Leeenergy_progress
05/05/2025Energy Code Compliance InspectionsSimon Leeprogress
05/05/2025Fire-Resistant Penetrations and JointsSimon Leespecial
04/23/2025Energy Code Compliance InspectionsSimon Leeprogress
04/23/2025Fire-Resistant Penetrations and JointsSimon Leespecial
04/23/2025Duct leakage testing, insulation and design—energy_progress
04/23/2025Tenant Protection Plan Compliance—special
04/23/2025Mechanical SystemsSimon Leespecial
04/23/2025FinalSimon Leeprogress
04/21/2025Fire-Resistant Penetrations and JointsSimon Leespecial
04/21/2025Energy Code Compliance InspectionsSimon Leeprogress
04/21/2025Interior lighting power—energy_progress
04/21/2025Lighting controls—energy_progress
04/21/2025Tenant Protection Plan Compliance—special
12/31/2024Tenant Protection Plan ComplianceLAWRENCE GREENspecial
12/31/2024Fenestration and door U-factor and product ratingsLAWRENCE GREENenergy_progress
12/23/2024FinalLAWRENCE GREENprogress
10/07/2024Duct leakage testing, insulation and designJACK GREENenergy_progress
10/07/2024Shutoff dampersJACK GREENenergy_progress
Latest 25 of 50.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Nail Studio LurePersonal services—
Project M01224231 Alteration · LOC Issued · 05/19/2025
The Learning ExperienceEducationCellar, Floor 1
Project M00309154 Alteration · LOC Issued · 03/11/2020
Project M00309165 Alteration · LOC Issued · 03/11/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 924 on file (BIS + DOB NOW)
▸Plans & Drawings23
▸DOB NOWPlans/Sketch19
09/06/2026M01239186-I1Request digital key ↗
09/06/2026M00083437-I1Request digital key ↗
08/26/2026M01113047-I1Request digital key ↗
Showing 3 of 19 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
09/05/2026M00309154-I1Request digital key ↗
08/15/2026M00309154-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/05/2026M00309165-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/04/2026M00405594-I1Request digital key ↗
▸Applications & Permits170
▸BISPLAN / WORK APPROVAL APPLICATION115
11/03/2025122459375Open ↗
10/28/2025122459375Open ↗
05/29/2022103940176Open ↗
Showing 3 of 115 on file for this type
▸BISWORK PERMIT APPLICATION51
04/01/2021123841218Open ↗
04/01/2021123841218Open ↗
04/27/2020123841218Open ↗
Showing 3 of 51 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISApplication Withdrawal/Address Change Form OP-1131
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWHPD Certification Letter or CPC Special Permit1
08/13/2026M01239373-I1Open ↗
▸Seals & Professional Certifications205
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION88
07/17/2020122459375Open ↗
04/06/2020122926067Open ↗
04/06/2020122932835Open ↗
Showing 3 of 88 on file for this type
▸DOB NOWProgress Inspector Seal & Signature26
09/02/2026M01115945-P1Open ↗
09/02/2026M01115945-P1Open ↗
09/02/2026M01115945-P1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature21
09/05/2026M00309154-I1Open ↗
09/05/2026M00309154-P1Open ↗
09/05/2026M00309165-I1Open ↗
Showing 3 of 21 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST19
04/04/2022123841218Open ↗
02/14/2020123841218Open ↗
06/06/2019123684110Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature19
09/02/2026M01115945-P1Open ↗
09/01/2026M01113047-I1Open ↗
09/01/2026M01115945-S3Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT16
04/07/2021141000967Open ↗
02/14/2020123841218Open ↗
02/14/2020123841218Open ↗
Showing 3 of 16 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
04/07/2021141000967Open ↗
Showing 1 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
04/07/2021141000967Open ↗
Showing 1 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Trade Schedules & Equipment40
▸BISSCHEDULE B - PLUMBING13
09/27/2019140457495Open ↗
Showing 1 of 13 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE7
06/06/2019123684110Open ↗
Showing 1 of 7 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA6
06/07/2021123889934Open ↗
Showing 1 of 6 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSELF-CERT PLUMBING NOTICE4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEQUIPMENT USE PERMITS3
10/21/2022122459375Open ↗
Showing 1 of 3 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection48
▸DOB NOWHPD-2: Clinton Special District Anti-Harassment Checklist20
09/05/2026M00309165-I1Open ↗
08/13/2026M00309154-I1Open ↗
08/13/2026M00405594-I1Open ↗
Showing 3 of 20 on file for this type
▸BISANTI-HARASSMENT CHECKLIST: CLINTON11
02/14/2020123841218Open ↗
02/14/2020123841218Open ↗
06/10/2019123684110Open ↗
Showing 3 of 11 on file for this type
▸BISTENANT PROTECTION PLAN AND NOTES3
08/20/2021123889934Open ↗
04/16/2021123841218Open ↗
Showing 2 of 3 on file for this type
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSRO MD ANTI-HARASSMENT CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
04/10/2020123841218Open ↗
Showing 1 of 2 on file for this type
▸BISCLINTON DISTRICT: ANTI-HARASSMENT CHECKLIST2
04/07/2021141000967Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWCertificate of No Harassment2
08/13/2026M01113047-I1Open ↗
08/13/2026M01239373-I1Open ↗
▸BISSTREET TREE SIGNOFF1
09/22/2020122459375Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
04/01/2021123841218Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00309154-I1Open ↗
▸Environmental & Asbestos39
▸DOB NOWOER: Notice to Proceed10
08/13/2026M01113047-I1Open ↗
08/13/2026M00083437-I1Open ↗
08/13/2026M00309154-I1Open ↗
Showing 3 of 10 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED8
04/07/2021141000967Open ↗
03/27/2020123841218Open ↗
03/02/2020123841218Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWOER: Notice of Satisfaction8
08/13/2026M00083437-I1Open ↗
08/13/2026M00309154-I1Open ↗
08/13/2026M01113048-S1Open ↗
Showing 3 of 8 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION4
12/04/2025122705322Open ↗
10/28/2020123684110Open ↗
09/16/2020140748485Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISOER NNO TCO PHASE 21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance17
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS10
03/27/2020123841218Open ↗
02/14/2020123841218Open ↗
01/27/2020122459375Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
08/24/2020123684110Open ↗
Showing 1 of 2 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
07/15/2022123841218Open ↗
08/20/2020122459375Open ↗
▸BISPRELIMINARY COMMISSIONING REPORT CERTIFICATION2
10/22/2020122459375Open ↗
10/22/2020122459375Open ↗
▸BISLIGHTING CONTROLS1
07/15/2022123841218Open ↗
▸Inspections & Test Reports31
▸BISTECHNICAL REPORT: RESPONSIBILITY17
04/11/2022123841218Open ↗
04/11/2022123841218Open ↗
04/01/2022123841218Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX8
04/27/2020123841218Open ↗
04/27/2020123841218Open ↗
04/27/2020123841218Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER6
03/27/2020123841218Open ↗
Showing 1 of 6 on file for this type
▸Approvals, Objections & Sign-offs77
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST41
09/19/2022123841218Open ↗
08/20/2021123889934Open ↗
07/02/2021123889934Open ↗
Showing 3 of 41 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION17
03/27/2020123841218Open ↗
03/27/2020123841218Open ↗
12/27/2019140457495Open ↗
Showing 3 of 17 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE10
11/03/2025122459375Open ↗
10/30/2025122459375Open ↗
10/28/2025122459375Open ↗
Showing 3 of 10 on file for this type
▸BISADMINISTRATIVE OBJECTIONS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSUPERSEDING LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISFA LETTER OF DEFECT : FD-FALD1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership29
▸BISCOST AFFIDAVIT18
08/20/2021123889934Open ↗
07/01/2021123889934Open ↗
04/07/2021141000967Open ↗
Showing 3 of 18 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW33
07/15/2022123841218Open ↗
04/06/2021123265778Open ↗
10/28/2020123684110Open ↗
▸BISDEPT OF FINANCE VERIFICATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Filing & Intake Forms159
▸BISADDITIONAL INFORMATION64
12/08/2025122459375Open ↗
04/12/2022123841218Open ↗
12/02/2021141000967Open ↗
Showing 3 of 64 on file for this type
▸BISBOROUGH INTAKE FORM62
04/01/2021123841218Open ↗
02/05/2021123841218Open ↗
07/17/2020122459375Open ↗
Showing 3 of 62 on file for this type
▸BISEFILING COVER SHEET25
02/14/2020123841218Open ↗
02/14/2020123841218Open ↗
Showing 2 of 25 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET8
04/07/2021141000967Open ↗
Showing 1 of 8 on file for this type
▸Other Documents40
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION25
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 25 on file for this type
▸BISDHCR DOCUMENT4
03/23/2021123265778Open ↗
10/28/2020123684110Open ↗
09/25/2020140748485Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWManufacturer's Specifications2
08/13/2026M01229628-P1Open ↗
08/13/2026M01229628-I1Open ↗
▸DOB NOWCalculations2
08/13/2026M01229628-P1Open ↗
08/13/2026M01229628-I1Open ↗
▸DOB NOWDHCR Document2
08/13/2026M00405594-I1Open ↗
08/13/2026M00309154-I1Open ↗
▸BISHPD: COMPLETION NOTICE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISENVIRONMENTAL "E" DEP NOTICE TO PROCEED1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPLOT DIAGRAM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWMultiple Dwelling Special District Feasibility of Government Funded Rehabilitation1
08/13/2026M00083437-I1Open ↗
▸DOB NOWMultiple Dwelling Special District Notice to Community Board1
08/13/2026M00083437-I1Open ↗