| Owner | Filings | Most Recent |
|---|---|---|
| JONERO, LLC | 10 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| J&R DESIGN AND INSPECTION CORP. | 3 | 09/06/2022 |
| LONGTIN SOLUTIONS LLC | 2 | 07/05/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| HIGH QUALITY 338 | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMERICAN STANDARD P&H CORORP. | Plumbing | 4 | 07/08/2026 |
| KJK ELECTRIC INC | Electrical | 1 | 03/21/2026 |
| KJK ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| JOHN KAMBOURAKIS | Electrical | 1 | 03/21/2026 |
| CHAMPION MECHANICAL INC | General Contractor | 1 | 07/08/2026 |
| HIGH QUALITY CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| ZHENG LI | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| J&R DESIGN AND INSPECTION | 6637 | 3 | 09/06/2022 |
| LONGTIN SOLUTIONS LLC | 8320 | 2 | 07/05/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | AMERICAN STANDARD P&H CORORP. | 07/22/2022 |
| DOB NOW | Mechanical Systems | Signed-off | HIGH QUALITY CONSTRUCTION | 07/21/2022 |
| DOB NOW | Mechanical Systems | Signed-off | CHAMPION MECHANICAL | 06/14/2022 |
| BIS | OT | ISSUED | IHOME IMPROVEMENT & WINDO | 07/18/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2024 | Complete | MAR-KAM ELEC'L CONTR'G IN | 2 meters, 2 new_meters |
| 10/04/2022 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/07/2022 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 09/07/2022 | Mechanical Systems | Robert Truskosky | special |
| 09/07/2022 | Final | Robert Truskosky | progress |
| 09/07/2022 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 09/07/2022 | Fire-Resistance Rated Construction | Robert Truskosky | progress |
| 09/07/2022 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 09/07/2022 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 09/07/2022 | Insulation placement and R values | Robert Truskosky | energy_progress |
| 09/07/2022 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 07/25/2022 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 07/25/2022 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 07/25/2022 | Mechanical Systems | Robert Truskosky | special |
| 07/25/2022 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 07/25/2022 | Final | Robert Truskosky | progress |
| 07/25/2022 | Fire-Resistance Rated Construction | Robert Truskosky | progress |
| 07/25/2022 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 07/25/2022 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 07/25/2022 | Insulation placement and R values | Robert Truskosky | energy_progress |
| 07/15/2022 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 07/15/2022 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 07/06/2022 | Energy Code Compliance Inspections | TIM TSAI | progress |
| 07/06/2022 | Maintenance information | TIM TSAI | energy_progress |
| 07/06/2022 | Duct leakage testing | TIM TSAI | energy_progress |
| 07/06/2022 | Mechanical Systems | TIM TSAI | special |
| 07/06/2022 | Final | TIM TSAI | progress |