| Owner | Filings | Most Recent |
|---|---|---|
| TOPLINE NYC CONTRACTING | 4 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/14/2019 | $1.2M | — | EAST HILL PROPERTIES LLC → Private party | $548/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CRAWFORD PRACTICE | 3 | 08/30/2023 |
| ASR ENGINEERING PC | 1 | 06/27/2023 |
| CL ENGINEERING P.C. | 2 | 12/15/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| H J BUILDING CONSULTING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MR. AIR NYC CORP | General Contractor | 6 | 03/21/2026 |
| SHAARA CONTRACTING INC | General Contractor | 3 | 03/21/2026 |
| TOPLINE NYC CONTRACTING | General Contractor | 3 | 03/21/2026 |
| BROOKYLN SOLARWORKS, LLC | Electrical | 1 | 03/22/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JUST CONSULTING ENGINEERI | 5865 | 3 | 08/30/2023 |
| CL ENGINEERING P.C. | 6781 | 2 | 12/15/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Signed-off | SHAARA CONTRACTING INC | 07/08/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | TOPLINE NYC CONTRACTING | 06/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | MR. AIR NYC CORP | 08/30/2021 |
| DOB NOW | Mechanical Systems | Signed-off | MR. AIR NYC CORP | 08/25/2021 |
| BIS | OT | ISSUED | BROOKLYN SOLARWORKS LLC | 08/31/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/28/2023 | Complete | RICHARD NEU | — |
| 08/24/2021 | Complete | INTELOGIC ELECTRIC, INC. | HVAC Wiring |
| 01/06/2021 | Permit Issued | BROOKYLN SOLARWORKS, LLC | 3 meters |
| 09/10/2020 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/27/2023 | Permit Issued | TOPLINE NYC CONTRACTING | Sidewalk Shed |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/14/2023 | Structural Stability – Alterations of existing buildings | XIAOJUN WANG | special |
| 09/14/2023 | Final | ROBERT CRAWFORD | progress |
| 09/14/2023 | Energy Code Compliance Inspections | ROBERT CRAWFORD | progress |
| 09/14/2023 | Footing and Foundation | ROBERT CRAWFORD | progress |
| 09/14/2023 | Structural Steel - Welding | XIAOJUN WANG | special |
| 09/14/2023 | Structural Steel - Details | XIAOJUN WANG | special |
| 09/14/2023 | Structural Cold-Formed Steel | XIAOJUN WANG | special |
| 09/14/2023 | Concrete - Cast-In-Place | XIAOJUN WANG | special |
| 09/14/2023 | Masonry | XIAOJUN WANG | special |
| 08/30/2023 | Concrete - Cast-In-Place | XIAOJUN WANG | special |
| 08/30/2023 | Masonry | XIAOJUN WANG | special |
| 08/30/2023 | Structural Cold-Formed Steel | XIAOJUN WANG | special |
| 08/30/2023 | Structural Stability – Alterations of existing buildings | XIAOJUN WANG | special |
| 08/30/2023 | Structural Steel - Details | XIAOJUN WANG | special |
| 08/30/2023 | Structural Steel - Welding | XIAOJUN WANG | special |
| 08/30/2023 | Energy Code Compliance Inspections | ROBERT CRAWFORD | progress |
| 08/30/2023 | Final | ROBERT CRAWFORD | progress |
| 08/30/2023 | Footing and Foundation | ROBERT CRAWFORD | progress |
| 06/08/2023 | Structural Stability – Alterations of existing buildings | XIAOJUN WANG | special |
| 06/08/2023 | Structural Steel - Welding | XIAOJUN WANG | special |
| 06/08/2023 | Concrete - Cast-In-Place | XIAOJUN WANG | special |
| 06/08/2023 | Masonry | XIAOJUN WANG | special |
| 06/08/2023 | Structural Cold-Formed Steel | XIAOJUN WANG | special |
| 06/08/2023 | Structural Steel - Details | XIAOJUN WANG | special |
| 06/08/2023 | Energy Code Compliance Inspections | ROBERT CRAWFORD | progress |