| Owner | Filings | Most Recent |
|---|---|---|
| UP CONSTRUCTION RESTORATION | 5 | 07/08/2026 |
| BENENSON CAPITAL PARTNERS, LLC | 31 | 03/22/2026 |
| FT WASH LESSOR LLC | 5 | 03/22/2026 |
| 592 FT WASHINGTON AVE CO. | 2 | 03/22/2026 |
| SHOPWELL INC | 1 | 03/22/2026 |
| BENSON CAPITAL COMPANY | 2 | 03/21/2026 |
| GREAT A P TEA COMPANY | 3 | 03/21/2026 |
| BENENSON CAPITAL | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MAX GORDON ARCHITECTS, PC | 1 | 01/16/2024 |
| MERRITT ENGINEERING CONSULTANTS, DPC | 1 | 03/06/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 02/24/2022 |
| GREEN DESIGN | 2 | 05/18/2021 |
| DOMINICK R. PILLA ASSOCIATES, PC | 1 | 08/31/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| MERRITT ENGINEERING CONSULTANT DPC | 2 | 03/21/2026 |
| GRAND EXPEDITERS NYC | 1 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| UP CONSTRUCTION AND RESTO | General Contractor | 4 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 2 | 03/21/2026 |
| PERFORMANCE MECHANCIAL | General Contractor | 2 | 03/21/2026 |
| WADE RAY & ASSOC CONST IN | General Contractor | 2 | 03/21/2026 |
| JOSEPH WEINSTEIN ELECTRIC | Electrical | 1 | 03/22/2026 |
| VAN VASSELL | Electrical | 1 | 03/21/2026 |
| GREGORY PAPANTONIOU | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MERRITT ENGINEERING CONSU | 460 | 1 | 03/06/2023 |
| LEO Y LEE ASSOCIATES | 2481 | 1 | 02/24/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | WADE RAY & ASSOC CONST IN | 01/25/2024 |
| DOB NOW | Mechanical Systems | Signed-off | PERFORMANCE MECHANCIAL | 03/11/2023 |
| DOB NOW | Supported Scaffold | Signed-off | UP CONSTRUCTION AND RESTO | 10/28/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 11/06/2020 |
| DOB NOW | Construction Fence | Signed-off | UP CONSTRUCTION AND RESTO | 09/28/2018 |
| BIS | OT | ISSUED | UP CONSTRUCTION AND RESTO | 03/31/2021 |
| BIS | OT | ISSUED | UP CONSTRUCTION AND RESTO | 02/04/2021 |
| BIS | OT | ISSUED | UP CONSTRUCTION AND RESTO | 08/29/2018 |
| BIS | OT | ISSUED | UP CONSTRUCTION AND RESTO | 08/29/2018 |
| BIS | OT | ISSUED | UP CONSTRUCTION AND RESTO | 08/29/2018 |
| BIS | OT | ISSUED | CITY DIMENSIONS CONSTRUCT | 05/23/2018 |
| BIS | EQ | ISSUED | CITY DIMENSIONS CONSTRUCT | 03/07/2018 |
| BIS | OT | ISSUED | CITY DIMENSIONS CONSTRUCT | 03/01/2018 |
| BIS | OT | ISSUED | NIETO CONTRACTORS INC | 12/22/2016 |
| BIS | PL | ISSUED | HUDSON PLBG AND HTG CO IN | 11/02/2016 |
| BIS | OT | ISSUED | NIETO CONTRACTORS INC | 10/25/2016 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 09/16/2016 |
| BIS | OT | ISSUED | CITY DIMENSIONS CONSTRUCT | 08/27/2016 |
| BIS | EQ | ISSUED | INTERSYSTEMS CORPORATION | 12/29/2010 |
| BIS | EQ | ISSUED | INTERSYSTEMS CORPORATION | 11/22/2010 |
| BIS | MH | ISSUED | DONNELLY MECHANICAL CORP | 01/05/2009 |
| BIS | EQ | ISSUED | SAHW CONTRACTING INC | 10/17/1995 |
| BIS | MH | ISSUED | SAHW CONTRACTING INC | 10/17/1995 |
| BIS | MH | ISSUED | V.R. MECHANICAL INC | 11/29/1994 |
| BIS | — | ISSUED | ULTIMATEM SIGNS & DESIGNS CORP. | 03/25/1994 |
| BIS | OT | ISSUED | NURMINEN_CONSTRUCTION CORP. | 08/11/1992 |
| BIS | PL | ISSUED | BELLKEY MAINTENANCE CORP | 02/21/1991 |
| BIS | OT | ISSUED | NURMINEN_CONSTRUCTION CORP. | 01/31/1991 |
| BIS | EQ | ISSUED | NURMINEN_CONSTRUCTION CORP. | 01/31/1991 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/11/2024 | Complete | UNITY ELECTRIC CO. INC | — |
| 11/10/2020 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 07/10/2019 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/21/2022 | HVAC-R and service water piping design and insulation | Christopher Krepcio | energy_progress |
| 06/21/2022 | HVAC-R and service water heating system controls | Christopher Krepcio | energy_progress |
| 06/21/2022 | Fire-Resistant Penetrations and Joints | Christopher Krepcio | special |
| 06/21/2022 | Mechanical Systems | Christopher Krepcio | special |
| 06/21/2022 | Energy Code Compliance Inspections | Christopher Krepcio | progress |
| 06/21/2022 | Final | Christopher Krepcio | progress |
| 06/21/2022 | HVAC-R and service water heating equipment | Christopher Krepcio | energy_progress |
| 03/11/2022 | Post-installed Anchors | Leo Lee | special |
| 05/20/2021 | Final | Sunil Saigal | progress |
| 08/28/2018 | Final | Dominick Pilla | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Chase | Retail | Floor 1 | Project M00966247 |