Roof1p · 2 filings · 18 docs
Other
Issued Permit Scope
Supported Scaffold
Terrace Recovery as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
16 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Penthouse3p · 2 filings · 8 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING INCLUSIVE OF CONDENSATE DRAIN PIPING. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 3 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 212p · 2 filings · 8 docs
ArchitecturePlumbing
Issued Permit Scope
Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING INCLUSIVE OF CONDENSATE DRAIN PIPING. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 2 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 20Under Construction3p · 3 filings · 15 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING INCLUSIVE OF CONDENSATE DRAIN PIPING. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 2 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 19Under Construction2p · 3 filings · 15 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING INCLUSIVE OF CONDENSATE DRAIN PIPING. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 18Under Construction3p · 4 filings · 20 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING INCLUSIVE OF CONDENSATE DRAIN PIPING. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
Apt 18F: renovate kitchen, renovate bathroom, filed in conjunction with general construction.
On file for this project
12 documents
Latest 3 of 4 filings on this floor.
Floor 17Under Construction4p · 3 filings · 15 docs
ArchitectureGeneralPlumbing
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING INCLUSIVE OF CONDENSATE DRAIN PIPING. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 3 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 16Under Construction4p · 3 filings · 15 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Interior renovation of APT. 16B consisting of rearrangement of interior partitions, doors and finishes as per plans submitted herewith. No change in use, egress or occupancy.
On file for this project
6 documents
Floor 15Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 14Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 13Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 12Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 11Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 10Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 9Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 8Under Construction6p · 4 filings · 20 docs
ArchitectureDMPlumbing
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
PLUMBING WORK ASSOCIATED WITH INTERIOR RENOVATION TO EXISTING APARTMENT #8BCD FILED UNDER SEPARATE APPLICATION DOB# M00804977. REMOVAL AND INSTALLATION OF PLUMBING FIXTURES. NO CHANGE TO USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
On file for this project
7 documents · 2 drawing sheets
INTERIOR RENOVATION TO EXISTING APARTMENT #8BCD. REMOVAL AND INSTALLATION OF INTERIOR NON-BEARING PARTITIONS, FIXTURES, AND FINISHES. NO CHANGE TO USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents · 4 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 7Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 6Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 5Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 4Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 3Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 2Under Construction2 filings · 9 docs
Architecture
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 1Under Construction2p · 3 filings · 15 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction · Supported Scaffold
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING INCLUSIVE OF CONDENSATE DRAIN PIPING. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
CellarUnder Construction2p · 2 filings · 13 docs
ArchitectureMechanical
Issued Permit Scope
General Construction
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING AND HORIZONTAL HEADER PIPING INCLUSIVE OF CODNENSATE DRAIN PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
REPLACEMENT OF DUAL TEMPERATURE RISER PIPING INCLUSIVE OF CONDENSATE DRAIN PIPING. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet