← Back
Converted dwellings or rooming house
60 WEST 91 STREET
MANHATTAN · BIN 1031614
💬 Discuss this project
1890Year Built
4Stories
C5Building Class
R7-2Zoning
5,870 sfGross Floor Area
9Units
Rent Stabilized0 Open Violations
Converted dwellings or rooming house · Owner of record: 60 WEST 91ST STREET LLC · 2,013 sf lot · 2.92 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof12p · 2 filings · 20 docs
Bulkhead5p · 1 filing · 20 docs
Floor 49p · 2 filings · 20 docs
Floor 35p · 3 filings · 20 docs
Floor 28p · 4 filings · 20 docs
Floor 12p · 1 filing · 20 docs
Cellar13p · 6 filings · 20 docs
Basement3p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
REPUBLIC EXTERIOR SERVICES1004/09/2026
60 WEST 91ST STREET LLC103/22/2026
60 91 STREET CORP103/22/2026
60 WEST 91 ST CORP103/22/2026
60 91ST ST CORP103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/24/2022$4.7M—CROTON GATE, LLC → 60 WEST 91ST STREET LLC$792/sf building
03/22/2021$3.1M—HEIDI J. SORVINO, ESQ., CHAPTER 11 TRUSTEE → CROTON GATE LLC$528/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JENNY FLORES EXPEDITING703/21/2026
Rigid Structural Design, LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRI CONTRACTING INCGeneral Contractor1707/08/2026
REPUBLIC SCAFFOLD&HOIST CGeneral Contractor604/09/2026
APPROVED CHIMNEY LLCGeneral Contractor107/08/2026
J-J PLUMBING CORPPlumbing107/08/2026
ORBIT PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JOSEPH MARTINES PE, PLLC1428701/30/2024
WILLIAM LEGGIO ARCHITECT6848401/17/2024
GEOTECHNICAL ENGINEERING734208/09/2023
NEW AGE ENGINEERING PLLC7746207/12/2023
Building Lifecycle
All (139)Filed (13)Permit Issued (14)Signed Off (11)Violation (53)Inspection (4)Objection (14)Special Inspection (30)
01/13/2026
Signed off — Alteration
Installation of a temporarily heavy-duty sidewalk and overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00953239-I1
01/13/2026
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00942907-I1
01/28/2025
Signed off — Alteration
HEREBY FILING OF THE INSTALLATION OF MECHANICAL EQUIPMENT. NO CHANGE TO USE OCCUPANCY OR EGRESS.
M00843041-I1
01/15/2025
Signed off — Alteration
HEREBY FILING OF THE INSTALLATION OF MECHANICAL EQUIPMENT. NO CHANGE TO USE OCCUPANCY OR EGRESS.
M00843041-S2
10/28/2024
Signed off — Alteration
HEREBY FILING OF THE INSTALLATION OF MECHANICAL EQUIPMENT. NO CHANGE TO USE OCCUPANCY OR EGRESS.
M00843041-S1
07/16/2024
Permit issued — Sidewalk Shed
M00953239-I1-SH
07/16/2024
Permit issued — Supported Scaffold
M00942907-I1-SF
07/15/2024
Signed off — Alteration
AT THE REAR OF THE BUILDING, APPROXIMATELY 7'x9' VERTICAL EXTENSION FROM BASEMENT TO 3RD FLOOR, SHOWN ON THE PLAN.
M00888872-I1
06/25/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/21/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/09/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/22/2024
Special inspection requirement — Post-installed Anchors
JOSEPH MARTINES
03/22/2024
Special inspection requirement — Final
William Leggio
03/22/2024
Special inspection requirement — Masonry
JOSEPH MARTINES
03/22/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOSEPH MARTINES
03/22/2024
Special inspection requirement — Construction Operations Influencing Adjacent Structures
JOSEPH MARTINES
03/22/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
William Leggio
03/20/2024
Signed off — Alteration
Hereby filing support of excavation, no change to use occupancy or egress.
M00897579-I1
03/18/2024
Permit issued — Support of Excavation
M00897579-I1-SE
03/15/2024
Objection resolved — Addressed
02/13/2024
Signed off — Alteration
M08050573-I1
02/09/2024
Objection raised — Scope
02/05/2024
Signed off — Alteration
M00888864-I1
01/31/2024
Special inspection requirement — Post-installed Anchors
JOSEPH MARTINES
01/31/2024
Special inspection requirement — Structural Steel - High Strength Bolting
JOSEPH MARTINES
01/31/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOSEPH MARTINES
01/31/2024
Special inspection requirement — Structural Steel - Welding
JOSEPH MARTINES
01/31/2024
Special inspection requirement — Final
JOSEPH MARTINES
01/31/2024
Special inspection requirement — Structural Cold-Formed Steel
JOSEPH MARTINES
01/31/2024
Special inspection requirement — Structural Steel - Details
JOSEPH MARTINES
01/30/2024
Filed — Alteration
AT THE REAR OF THE BUILDING, APPROXIMATELY 7'x9' VERTICAL EXTENSION FROM BASEMENT TO 3RD FLOOR, SHOWN ON THE PLAN.
M00888872-P1
01/29/2024
Special inspection requirement — Structural Cold-Formed Steel
JOSEPH MARTINES
01/29/2024
Special inspection requirement — Final
JOSEPH MARTINES
01/29/2024
Special inspection requirement — Structural Steel - Welding
JOSEPH MARTINES
01/29/2024
Special inspection requirement — Structural Steel - High Strength Bolting
JOSEPH MARTINES
01/29/2024
Special inspection requirement — Post-installed Anchors
JOSEPH MARTINES
01/29/2024
Special inspection requirement — Structural Steel - Details
JOSEPH MARTINES
01/29/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOSEPH MARTINES
01/24/2024
Permit issued — General Construction
M00843041-I1-GC
01/17/2024
Filed — Alteration
HEREBY FILING OF THE INSTALLATION OF MECHANICAL EQUIPMENT. NO CHANGE TO USE OCCUPANCY OR EGRESS.
M00843041-P1
10/26/2023
Permit issued — Supported Scaffold
M00942907-I1-SF
10/26/2023
Permit issued — Sidewalk Shed
M00953239-I1-SH
10/25/2023
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk and overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00953239-I1
10/25/2023
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00942907-I1
09/29/2023
Permit issued — Mechanical Systems
M00843041-S1-MS
09/27/2023
Permit issued — Plumbing
M00843041-S2-PL
09/22/2023
Permit issued — General Construction
M00843041-I1-GC
09/12/2023
Objection resolved — Addressed
09/12/2023
Objection resolved — Addressed
09/12/2023
Objection resolved — Addressed
09/12/2023
Objection resolved — Addressed
09/05/2023
Filed — Alteration
HEREBY FILING OF THE INSTALLATION OF MECHANICAL EQUIPMENT. NO CHANGE TO USE OCCUPANCY OR EGRESS.
M00843041-S2
09/05/2023
Filed — Alteration
HEREBY FILING OF THE INSTALLATION OF MECHANICAL EQUIPMENT. NO CHANGE TO USE OCCUPANCY OR EGRESS.
M00843041-S1
08/21/2023
Permit issued — Foundation
M00888864-I1-FO
08/16/2023
Objection resolved — Addressed
08/16/2023
Objection resolved — Addressed
08/11/2023
Objection raised — Scope
08/11/2023
Objection raised — Admin
08/11/2023
Objection raised — Structural
08/11/2023
Objection raised — Other
Latest 60 of 139 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedSigned-offREPUBLIC SCAFFOLD&HOIST C07/16/2024
DOB NOWSupported ScaffoldSigned-offREPUBLIC SCAFFOLD&HOIST C07/16/2024
DOB NOWSupport of ExcavationSigned-offTRI CONTRACTING INC03/18/2024
DOB NOWGeneral ConstructionSigned-offTRI CONTRACTING INC01/24/2024
DOB NOWSupported ScaffoldSigned-offREPUBLIC SCAFFOLD&HOIST C10/26/2023
DOB NOWSidewalk ShedSigned-offREPUBLIC SCAFFOLD&HOIST C10/26/2023
DOB NOWMechanical SystemsSigned-offTRI CONTRACTING INC09/29/2023
DOB NOWPlumbingSigned-offORBIT PLBG & HTG INC09/27/2023
DOB NOWGeneral ConstructionSigned-offTRI CONTRACTING INC09/22/2023
DOB NOWFoundationSigned-offTRI CONTRACTING INC08/21/2023
DOB NOWStructuralSigned-offTRI CONTRACTING INC08/02/2023
DOB NOWMechanical SystemsSigned-offAPPROVED CHIMNEY LLC07/12/2023
DOB NOWGeneral ConstructionSigned-offTRI CONTRACTING INC01/31/2023
DOB NOWPlumbingSigned-offJ-J PLUMBING CORP01/27/2023
BISOTISSUEDHARRIS ARCHITECTURE & DESIGN07/13/2010
3 projects · most recent 09/18/2023
General Wiring
FiledStatusContractorScope
09/18/2023CompleteKINGS ELECTRIC CO., INC.General Wiring
06/10/2021CompleteAXCEL ELECTRIC CO., INC.General Wiring
06/02/2021CompleteAXCEL ELECTRIC CO., INC.10 meters, 1 new_meters
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
06/25/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/21/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/09/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/30/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 35
DateRequirementInspectorRole
03/22/2024Post-installed AnchorsJOSEPH MARTINESspecial
03/22/2024FinalWilliam Leggioprogress
03/22/2024MasonryJOSEPH MARTINESspecial
03/22/2024Structural Stability – Alterations of existing buildingsJOSEPH MARTINESspecial
03/22/2024Construction Operations Influencing Adjacent StructuresJOSEPH MARTINESspecial
03/22/2024Fire-Resistant Penetrations and JointsWilliam Leggiospecial
01/31/2024Post-installed AnchorsJOSEPH MARTINESspecial
01/31/2024Structural Steel - High Strength BoltingJOSEPH MARTINESspecial
01/31/2024Structural Stability – Alterations of existing buildingsJOSEPH MARTINESspecial
01/31/2024Structural Steel - WeldingJOSEPH MARTINESspecial
01/31/2024FinalJOSEPH MARTINESprogress
01/31/2024Structural Cold-Formed SteelJOSEPH MARTINESspecial
01/31/2024Structural Steel - DetailsJOSEPH MARTINESspecial
01/29/2024Structural Cold-Formed SteelJOSEPH MARTINESspecial
01/29/2024FinalJOSEPH MARTINESprogress
01/29/2024Structural Steel - WeldingJOSEPH MARTINESspecial
01/29/2024Structural Steel - High Strength BoltingJOSEPH MARTINESspecial
01/29/2024Post-installed AnchorsJOSEPH MARTINESspecial
01/29/2024Structural Steel - DetailsJOSEPH MARTINESspecial
01/29/2024Structural Stability – Alterations of existing buildingsJOSEPH MARTINESspecial
07/24/2023Fire-Resistant Penetrations and JointsWilliam Leggiospecial
07/24/2023Heating SystemsJOSEPH MARTINESspecial
07/24/2023Mechanical SystemsJOSEPH MARTINESspecial
07/24/2023Energy Code Compliance InspectionsJOSEPH MARTINESprogress
07/24/2023Fire-Resistance Rated ConstructionWilliam Leggioprogress
Latest 25 of 35.
▾Documents — 114 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
09/01/2026M08050573-I1Request digital key ↗
09/01/2026M08050574-I1Request digital key ↗
08/29/2026M00880937-I1Request digital key ↗
Showing 3 of 13 on file for this type
▸Applications & Permits13
▸DOB NOWLPC Approval/Permit11
08/29/2026M00888872-I1Open ↗
08/13/2026M00888864-I1Open ↗
08/13/2026M00888872-P1Open ↗
Showing 3 of 11 on file for this type
▸BISWORK PERMIT APPLICATION1
07/15/2010120409058Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
07/15/2010120409058Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026M00843041-I1Open ↗
08/13/2026M00843041-P1Open ↗
▸Seals & Professional Certifications52
▸DOB NOWSpecial Inspector Seal & Signature23
09/01/2026M00897579-I1Open ↗
09/01/2026M00897579-I1Open ↗
09/01/2026M00897579-I1Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
09/01/2026M08050573-I1Open ↗
09/01/2026M08050574-I1Open ↗
08/29/2026M00888864-I1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWProgress Inspector Seal & Signature12
08/29/2026M00843041-S1Open ↗
08/29/2026M00843041-S1Open ↗
08/29/2026M00843041-S1Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
08/12/2010120409058Open ↗
07/12/2010120409058Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
07/12/2010120409058Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
07/12/2010120409058Open ↗
▸Environmental & Asbestos12
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/29/2026M00888864-I1Open ↗
08/29/2026M00888872-I1Open ↗
08/13/2026M00897579-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
09/01/2026M08050573-I1Open ↗
09/01/2026M08050574-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
07/12/2010120409058Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
08/12/2010120409058Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
07/12/2010120409058Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
08/12/2010120409058Open ↗
07/12/2010120409058Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
07/12/2010120409058Open ↗
▸Other Documents17
▸DOB NOWDHCR Document9
08/29/2026M00888872-I1Open ↗
08/13/2026M00843041-I1Open ↗
08/13/2026M00843041-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlot Diagram3
08/13/2026M00888864-I1Open ↗
08/13/2026M00843041-P1Open ↗
08/13/2026M00843041-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026M00843041-I1Open ↗
08/13/2026M00843041-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026M00843041-I1Open ↗
08/13/2026M00843041-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026M00897579-I1Open ↗