0 Active ViolationsFISP: SAFEFDNY Report ↗
Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 4HSS West Sidesports, HSS West Side Sports Medicine Institute13p · 8 filings · 20 docs
Floor 3Outpatient Center HSS West Side, HSS West Side Ambulatory Su8p · 5 filings · 20 docs
Floor 2HSS West Side Abmulatory Surgery Center, HSS West Side Ambul39p · 5 filings · 20 docs
Floor 1HSS Westside, F45 Gym +1Under Construction40p · 11 filings · 20 docs
CellarHSS Westside, HSS West Side Sports Medicine Institute +160p · 7 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
The Durst Organization13008/29/2026
Durst Partners11303/21/2026
58 Corner1703/21/2026
Edison Properties1303/21/2026
Royal Realty1007/08/2026
West 58 St Mini Storage303/21/2026
FPC 57 North103/22/2026
Bigman Brothers103/22/2026
Dunlop Access Systems103/21/2026
Red Apple Real Estate103/21/2026
Chase Manhattan Bank103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Jaros Baum & Bolles1907/16/2026
Severud Associates Consulting Engineering107/15/2026
Perkins Eastman607/14/2026
Desimone Consulting Engineering801/07/2026
Chien Dao Studio111/07/2024
SI Design307/11/2022
Env Architects107/11/2022
MG Engineering107/11/2022
Anchorette103/08/2021
HC Engineering406/17/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
J.A.M. Associates6003/21/2026
JP Expedite803/21/2026
Nexus Consulting NYC303/21/2026
Codegreen203/21/2026
McFarlane Code Consultant103/21/2026
Municipal Expediting203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
L.F. Driscoll CompanyGeneral Contractor1407/08/2026
Skanska USA BuildingGeneral Contractor907/08/2026
Pace PlumbingFire Protection607/08/2026
Signs CadSign hanger407/08/2026
Riehm PlumbingFire Protection307/08/2026
Paul M MaintenanceGeneral Contractor307/23/2026
UglGeneral Contractor303/21/2026
Cross ManagementGeneral Contractor307/08/2026
Pace PlumbingPlumbing207/08/2026
Riehm PlumbingPlumbing207/08/2026
Speedway PlumbingPlumbing107/08/2026
Joseph Weinstein ElectricElectrical103/22/2026
Accurate MechanicalFire Protection107/08/2026
A. Pilato PlumbingPlumbing108/12/2026
Cardoza PlumbingPlumbing107/08/2026
P & D MechanicalFire Protection107/08/2026
R.J.C. MechanicalFire Protection107/08/2026
Bigman BrothersElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Alan Margolin & Associates423407/16/2026
Future Tech Consultants O589308/20/2025
Socotec Engineering4983108/20/2025
Fenagh69422005/05/2025
Bureau Veritas Na6902606/28/2023
Codegreen510107/11/2022
Building Lifecycle
All (239)Filed (45)Permit Issued (42)Signed Off (24)Facade (FISP) (3)Violation (60)Inspection (21)Objection (14)Special Inspection (30)
09/02/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/26/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/11/2026
Permit issued — Plumbing
M01424004-I1-PL
07/22/2026
Permit issued — Structural
M01423980-I1-ST
07/22/2026
Permit issued — General Construction
M01423904-I1-GC
07/22/2026
Permit issued — Mechanical Systems
M01423997-I1-MS
07/16/2026
Filed — Alteration
Plumbing for renovation for HSS Physical Therapy on 1st floor
M01424004-I1
07/15/2026
Filed — Alteration
Structural work for renovation to HSS Physical Therapy on 1st floor. Work to include demo of the existing concrete on metal deck raised slab. Provide new raised slab on gravel fill.
M01423980-I1
07/15/2026
Filed — Alteration
Mechanical work for renovation for HSS Physical Therapy on 1st floor
M01423997-I1
07/14/2026
Filed — Alteration
General construction for renovation for HSS Physical Therapy on 1st floor
M01423904-I1
07/07/2026
Special inspection requirement — Energy Code Compliance Inspections
Young Suh
07/07/2026
Special inspection requirement — Interior lighting power
Young Suh
07/07/2026
Special inspection requirement — Duct leakage testing, insulation and design
Young Suh
07/07/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Young Suh
07/07/2026
Special inspection requirement — Lighting controls
Young Suh
07/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Young Suh
07/07/2026
Special inspection requirement — Energy Code Compliance Inspections
Young Suh
07/07/2026
Special inspection requirement — Metering
Young Suh
07/07/2026
Special inspection requirement — Post-installed Anchors
Young Suh
07/07/2026
Special inspection requirement — Post-installed Anchors
Young Suh
07/07/2026
Special inspection requirement — Maintenance information
Young Suh
07/07/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Young Suh
07/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
Young Suh
07/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
Young Suh
07/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
Young Suh
07/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
Young Suh
06/29/2026
Special inspection requirement — Final
Young Suh
06/29/2026
Special inspection requirement — Final
Young Suh
06/29/2026
Special inspection requirement — Final
SUNG JONG PARK
06/29/2026
Special inspection requirement — Mechanical Systems
Young Suh
06/29/2026
Special inspection requirement — Concrete - Cast-In-Place
Young Suh
01/14/2026
Signed off — Alteration
M01072683-I1
01/08/2026
Special inspection requirement — Final
AILANTO DANIEL MINAWI
01/08/2026
Special inspection requirement — Tenant Protection Plan Compliance
AILANTO DANIEL MINAWI
01/08/2026
Special inspection requirement — Post-installed Anchors
AILANTO DANIEL MINAWI
01/07/2026
Filed — Alteration
M01072683-P2
01/06/2026
Special inspection requirement — Final
AILANTO DANIEL MINAWI
01/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
01/06/2026
Special inspection requirement — Post-installed Anchors
09/24/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/09/2025
Objection resolved — Addressed
09/09/2025
Objection resolved — Addressed
09/08/2025
Violation issued (HPD, closed)
C
09/08/2025
Objection raised — Admin
09/08/2025
Objection raised — Scope
09/08/2025
Objection raised — Fire_Protection
09/08/2025
Objection raised — Mechanical
08/20/2025
Filed — Alteration
M01235281-I1
08/20/2025
Filed — Alteration
M01235287-I1
07/14/2025
Special inspection requirement — Chimneys and vents
MARISA HARTE
07/14/2025
Special inspection requirement — Post-installed Anchors
MARISA HARTE
07/14/2025
Special inspection requirement — Tenant Protection Plan Compliance
MARISA HARTE
06/14/2025
Violation issued (HPD, closed)
C
06/13/2025
Violation issued (HPD, closed)
A
05/29/2025
Signed off — Alteration
Structural work for HSS on 4th floor
M01068447-I1
05/20/2025
Signed off — Alteration
M01072674-I1
05/13/2025
Signed off — Alteration
M01072691-I1
05/07/2025
Signed off — Alteration
Mechanical work for HSS on 4th floor
M01067670-I1
05/06/2025
Signed off — Alteration
Plumbing work for HSS in cellar
M01072686-I1
Latest 60 of 239 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offA. Pilato Plumbing08/11/2026
DOB NOWStructuralPermit IssuedPaul M Maintenance07/22/2026
DOB NOWGeneral ConstructionPermit IssuedPaul M Maintenance07/22/2026
DOB NOWMechanical SystemsPermit IssuedPaul M Maintenance07/22/2026
DOB NOWBoiler EquipmentPermit IssuedNew York Heating04/25/2025
DOB NOWSprinklersSigned-offRiehm Plumbing02/27/2025
DOB NOWSprinklersSigned-offRiehm Plumbing02/18/2025
DOB NOWPlumbingSigned-offRiehm Plumbing02/18/2025
DOB NOWSprinklersSigned-offRiehm Plumbing02/18/2025
DOB NOWPlumbingSigned-offRiehm Plumbing02/14/2025
DOB NOWSprinklersSigned-offManengeering Bureau12/13/2024
DOB NOWSprinklersSigned-offManengeering Bureau12/13/2024
DOB NOWSprinklersSigned-offManengeering Bureau12/13/2024
DOB NOWSprinklersSigned-offManengeering Bureau11/08/2024
DOB NOWPlumbingSigned-offPace Plumbing09/17/2024
DOB NOWPlumbingSigned-offPace Plumbing09/17/2024
DOB NOWStructuralSigned-offSkanska USA Building09/12/2024
DOB NOWStructuralSigned-offSkanska USA Building09/09/2024
DOB NOWMechanical SystemsSigned-offSkanska USA Building09/09/2024
DOB NOWGeneral ConstructionSigned-offSkanska USA Building09/09/2024
DOB NOWGeneral ConstructionSigned-offSkanska USA Building09/09/2024
DOB NOWMechanical SystemsSigned-offSkanska USA Building09/06/2024
DOB NOWSprinklersSigned-offManengeering Bureau09/05/2024
DOB NOWSprinklersSigned-offManengeering Bureau09/05/2024
DOB NOWSprinklersSigned-offR.J.C. Mechanical02/01/2024
DOB NOWSprinklersSigned-offAccurate Mechanical08/02/2023
DOB NOWGeneral ConstructionSigned-offL.F. Driscoll Company01/05/2023
DOB NOWStructuralSigned-offL.F. Driscoll Company01/05/2023
DOB NOWMechanical SystemsSigned-offL.F. Driscoll Company01/05/2023
DOB NOWSprinklersSigned-offP & D Mechanical12/02/2022
DOB NOWPlumbingSigned-offCardoza Plumbing11/07/2022
DOB NOWStructuralSigned-offL.F. Driscoll Company10/18/2022
DOB NOWGeneral ConstructionSigned-offL.F. Driscoll Company10/18/2022
DOB NOWMechanical SystemsSigned-offL.F. Driscoll Company10/18/2022
DOB NOWPlumbingSigned-offSpeedway Plumbing09/26/2022
DOB NOWMechanical SystemsSigned-offCross Management08/09/2022
DOB NOWGeneral ConstructionSigned-offCross Management08/04/2022
DOB NOWGeneral ConstructionSigned-offUgl07/07/2021
DOB NOWSignSigned-offSigns Cad06/17/2019
DOB NOWSignSigned-offSigns Cad06/17/2019
+ 52 more permits on file
2 projects · most recent 07/16/2026
Water/Sanitary
FiledStatusContractorScope
07/16/2026Signed-offA. Pilato PlumbingWater/Sanitary
07/11/2022Signed-offSpeedway PlumbingWater/Sanitary
20 projects · most recent 07/23/2026
General Wiring Lighting Boiler Controls
FiledStatusContractorScope
07/23/2026Permit IssuedPM Electrical MaintenanceGeneral Wiring
07/17/2026Permit IssuedRigid Electric—
01/31/2025CompleteBigman BrothersGeneral Wiring, Lighting
09/26/2024CompleteBigman BrothersGeneral Wiring, Lighting
09/05/2024CompleteBigman BrothersGeneral Wiring, Lighting
01/03/2023CompletePM Electrical MaintenanceGeneral Wiring
10/28/2022CompleteSJ Electrical ServicesGeneral Wiring
11/12/2021CompleteRigid ElectricBoiler Controls
06/16/2021CompleteRoz-A-Lite Electrical Contg IGeneral Wiring, Lighting
03/31/2020CompleteE-J Electric Installation CoGeneral Wiring
10/24/2019CompleteRigid ElectricBoiler Controls
09/05/2019CompleteAmpere Electrical Services—
09/05/2019CompleteAmpere Electrical Services—
09/05/2019CompleteAmpere Electrical Services—
09/05/2019CompleteAmpere Electrical Services—
1 project · most recent 07/15/2026
Concrete
FiledStatusContractorScope
07/15/2026Permit IssuedPaul M MaintenanceConcrete
▾Field Inspections (DOB CAP) — 21
DateTypeResultReport
09/02/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/26/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/01/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/01/2025Certified Sprinkler - SP - RoughingCertifiedView ↗
03/13/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/11/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/10/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/04/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/04/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/11/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/08/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/13/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/07/2023Pass-Final SP - Up to 3 Requested FloorsPassView ↗
08/04/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/08/2023Certified Medical Gas - MG - PL - FinishCertifiedView ↗
05/08/2023Certified Medical Gas - MG - PL - RoughingCertifiedView ↗
05/08/2023Certified Medical Gas - MG - PL - TestCertifiedView ↗
05/08/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/17/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/17/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/11/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
07/07/2026HVAC-R and service water piping design and insulationYoung Suhenergy_progress
07/07/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
07/07/2026Post-installed AnchorsYoung Suhspecial
07/07/2026Energy Code Compliance InspectionsYoung Suhprogress
07/07/2026Maintenance informationYoung Suhenergy_progress
07/07/2026HVAC-R and service water piping design and insulationYoung Suhenergy_progress
07/07/2026Lighting controlsYoung Suhenergy_progress
07/07/2026Energy Code Compliance InspectionsYoung Suhprogress
07/07/2026Post-installed AnchorsYoung Suhspecial
07/07/2026Duct leakage testing, insulation and designYoung Suhenergy_progress
07/07/2026Interior lighting powerYoung Suhenergy_progress
07/07/2026MeteringYoung Suhenergy_progress
07/06/2026Tenant Protection Plan ComplianceYoung Suhspecial
07/06/2026Tenant Protection Plan ComplianceYoung Suhspecial
07/06/2026Tenant Protection Plan ComplianceYoung Suhspecial
07/06/2026Tenant Protection Plan ComplianceYoung Suhspecial
06/29/2026Mechanical SystemsYoung Suhspecial
06/29/2026FinalYoung Suhprogress
06/29/2026FinalSUNG JONG PARKprogress
06/29/2026FinalYoung Suhprogress
06/29/2026Concrete - Cast-In-PlaceYoung Suhspecial
01/08/2026FinalAILANTO DANIEL MINAWIprogress
01/08/2026Tenant Protection Plan ComplianceAILANTO DANIEL MINAWIspecial
01/08/2026Post-installed AnchorsAILANTO DANIEL MINAWIspecial
01/06/2026FinalAILANTO DANIEL MINAWIprogress
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
HSS WestsideMedical / HealthcareCellar, Floor 1
Project M01424004 Alteration · Permit Entire · 07/16/2026
Project M01423980 Alteration · Permit Entire · 07/15/2026
Project M01423997 Alteration · Permit Entire · 07/15/2026
Project M01423904 Alteration · Permit Entire · 07/14/2026
Outpatient Center HSS West SideMedical / HealthcareFloor 3
Project M01235281 Alteration · Approved · 08/20/2025
Project M01235287 Alteration · Approved · 08/20/2025
Project M01143956 Alteration · Approved · 01/23/2025
Project M01077540 Alteration · Permit Entire · 12/16/2024
HSS West SidesportsOfficeFloor 4
Project M01136169 Alteration · LOC Issued · 11/07/2024
HSS West Side Sports Medicine InstituteMedical / HealthcareCellar, Floor 4
Project M01072683 Alteration · LOC Issued · 08/30/2024
Project M01072674 Alteration · LOC Issued · 08/08/2024
Project M01067676 Alteration · LOC Issued · 08/05/2024
Project M01067700 Alteration · LOC Issued · 08/05/2024
Project M01072686 Alteration · LOC Issued · 08/05/2024
Project M01072691 Alteration · LOC Issued · 08/05/2024
HSS West Side Outpatient CenterMedical / HealthcareCellar, Floor 4
Project M01068447 Alteration · LOC Issued · 08/16/2024
Project M01068442 Alteration · LOC Issued · 07/23/2024
Project M01072668 Alteration · LOC Issued · 07/23/2024
HSS West Side NstituteMedical / HealthcareFloor 4
Project M01067670 Alteration · LOC Issued · 08/12/2024
HSS West Side Ambulatory Surgery CenterMedical / HealthcareFloors 2, 3
Project M00766660 Alteration · LOC Issued · 08/31/2022
Project M00785183 Alteration · LOC Issued · 08/30/2022
HSS West Side Abmulatory Surgery CenterMedical / HealthcareFloor 2
Project M00766260 Alteration · LOC Issued · 08/30/2022
Project M00766267 Alteration · LOC Issued · 08/30/2022
F45 GymFitness / RecreationFloor 1
Project M00692258 Alteration · LOC Issued · 05/20/2022
Hospital for Special SurgeryMedical / HealthcareFloor 2
Project M00464557 Alteration · LOC Issued · 03/08/2021
HSS Sports Medisine InstituteMedical / HealthcareFloor 1
Project M00177060 Alteration · LOC Issued · 06/17/2019
Project M00177090 Alteration · LOC Issued · 06/17/2019
Project M00177050 Alteration · LOC Issued · 06/14/2019
Project M00177077 Alteration · LOC Issued · 06/14/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 1,469 on file (BIS + DOB NOW)
▸Plans & Drawings44
▸DOB NOWPlans/Sketch39
09/02/2026M00681121-I1Request digital key ↗
09/02/2026M00677785-I1Request digital key ↗
09/02/2026M00692258-S2Request digital key ↗
Showing 3 of 39 on file for this type
▸DOB NOWPlans/Sketch - Sign4
09/05/2026M00177050-I1Request digital key ↗
09/05/2026M00177077-I1Request digital key ↗
09/05/2026M00177060-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - General Construction1
09/04/2026M00464557-I1Request digital key ↗
▸Applications & Permits275
▸BISPLAN / WORK APPROVAL APPLICATION183
03/13/2025123361619Open ↗
02/28/2025123361619Open ↗
02/27/2025123361619Open ↗
Showing 3 of 183 on file for this type
▸BISWORK PERMIT APPLICATION92
03/12/2025123361600Open ↗
02/21/2020123853829Open ↗
11/21/2019123853829Open ↗
Showing 3 of 92 on file for this type
▸Zoning, Tax Lot & Property Records3
▸BISZONING DIAGRAM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications363
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION125
02/07/2020140708982Open ↗
02/07/2020140709062Open ↗
02/03/2020123471180Open ↗
Showing 3 of 125 on file for this type
▸DOB NOWProgress Inspector Seal & Signature63
10/02/2026M01068442-P1Open ↗
10/02/2026M01068442-P1Open ↗
09/23/2026M00177050-I1Open ↗
Showing 3 of 63 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature46
10/02/2026M01068442-P1Open ↗
09/23/2026M01077540-I1Open ↗
09/03/2026M01067670-P1Open ↗
Showing 3 of 46 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature44
09/04/2026M00464557-I1Open ↗
09/02/2026M00677785-I1Open ↗
09/02/2026M00692258-S1Open ↗
Showing 3 of 44 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT32
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 32 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST21
01/16/2020123471180Open ↗
Showing 1 of 21 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISAPPLICANT OWNER SIGNATURE9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISProfessional and Owner Certification (POC3)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment62
▸BISSCHEDULE B - PLUMBING20
05/05/2021140796388Open ↗
05/04/2021140796388Open ↗
Showing 2 of 20 on file for this type
▸BISEQUIPMENT USE PERMITS16
01/07/2020123471206Open ↗
01/07/2020123471206Open ↗
01/03/2020123471206Open ↗
Showing 3 of 16 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT7
01/07/2020123471206Open ↗
01/03/2020123471206Open ↗
07/25/2019140708982Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA5
12/22/2021123258795Open ↗
09/15/2020123463527Open ↗
06/17/2019122368393Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT5
05/28/2019140708982Open ↗
Showing 1 of 5 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection93
▸DOB NOWHPD-2: Clinton Special District Anti-Harassment Checklist44
09/04/2026M00464557-I1Open ↗
09/02/2026M00677785-I1Open ↗
09/02/2026M00692258-S2Open ↗
Showing 3 of 44 on file for this type
▸BISANTI-HARASSMENT CHECKLIST: CLINTON32
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 32 on file for this type
▸BISTenant Protection Plan and Notes14
09/30/2019123853829Open ↗
03/07/2023140708973Open ↗
12/12/2022140709062Open ↗
Showing 3 of 14 on file for this type
▸BISCLINTON DISTRICT: ANTI-HARASSMENT CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos69
▸DOB NOWOER: Notice to Proceed25
09/04/2026M00464557-I1Open ↗
09/02/2026M00677785-I1Open ↗
08/15/2026M00692258-S1Open ↗
Showing 3 of 25 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸DOB NOWOER: Notice of Satisfaction12
09/04/2026M00464557-I1Open ↗
09/02/2026M00677785-I1Open ↗
08/15/2026M00692258-S1Open ↗
Showing 3 of 12 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION10
04/09/2025123361600Open ↗
03/24/2025123361619Open ↗
03/02/2023140708973Open ↗
Showing 3 of 10 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Energy Compliance52
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS30
01/07/2020123471206Open ↗
01/07/2020123471206Open ↗
01/03/2020123471206Open ↗
Showing 3 of 30 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY9
02/27/2025123361619Open ↗
Showing 1 of 9 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
01/07/2020123471206Open ↗
01/03/2020123471206Open ↗
08/09/2019140708982Open ↗
Showing 3 of 8 on file for this type
▸BISNYCECC ANALYSIS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.1
09/04/2026M00464557-I1Open ↗
▸Inspections & Test Reports40
▸BISTECHNICAL REPORT: RESPONSIBILITY25
02/27/2025123361619Open ↗
02/24/2025123361600Open ↗
05/12/2021140796388Open ↗
Showing 3 of 25 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER5
11/17/2023140708973Open ↗
Showing 1 of 5 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTECHNICAL REPORT: PILE DRIVING3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
10/12/2023140708973Open ↗
▸Approvals, Objections & Sign-offs129
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST69
04/09/2025123361600Open ↗
03/25/2025123361619Open ↗
11/17/2023140708973Open ↗
Showing 3 of 69 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION37
03/04/2022140365593Open ↗
03/03/2022140365593Open ↗
03/03/2022140365593Open ↗
Showing 3 of 37 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSUPERSEDING LETTER7
03/12/2025123361600Open ↗
02/27/2025123361600Open ↗
Showing 2 of 7 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFINAL2
03/24/2025123361619Open ↗
10/10/2023140708973Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Cost, Insurance & Ownership65
▸BISCOST AFFIDAVIT49
06/15/2021122935137Open ↗
05/04/2021123853829Open ↗
01/20/2021140709035Open ↗
Showing 3 of 49 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
04/09/2025123361600Open ↗
03/24/2025123361619Open ↗
10/26/2022140708937Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms214
▸BISADDITIONAL INFORMATION84
03/07/2022140365593Open ↗
05/12/2021140709062Open ↗
05/05/2021140796388Open ↗
Showing 3 of 84 on file for this type
▸BISBOROUGH INTAKE FORM73
03/12/2025123361600Open ↗
02/27/2025123361600Open ↗
03/16/2020121184609Open ↗
Showing 3 of 73 on file for this type
▸BISEFILING COVER SHEET37
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 37 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET20
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 20 on file for this type
▸Other Documents24
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION8
01/03/2020123471206Open ↗
Showing 1 of 8 on file for this type
▸DOB NOWMultiple Dwelling Special District Notice to Community Board4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWMultiple Dwelling Special District Feasibility of Government Funded Rehabilitation4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISPLOT DIAGRAM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISENVIRONMENTAL 'E' DEP NOTICE TO PROCEED2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISOTCR MONITOR CERTFICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSupporting Document: Fee Deferment1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BIS* ENVIRONMENTAL 'E' DEP NOTICE OF SATISFACTION1
06/08/2020121184609Open ↗
▸DOB NOWDHCR Document1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type