1924Year Built
4Stories
W6Building Class
R6BZoning
120,000 sfGross Floor Area
1Units
LL97 Covered0 Active ViolationsFISP: SWARMPFDNY Report ↗
Other college and university · 30,000 sf lot · 4 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofPratt Institute11p · 1 filing · 6 docs
Floor 35Pratt Institute2p · 1 filing · 8 docs
Floor 34Pratt Institute2p · 1 filing · 8 docs
Floor 33Pratt Institute1p · 1 filing · 8 docs
Floor 32
Floor 31
Floor 30
Floor 29
Floor 28
Floor 27
Floor 26
Floor 25
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20
Floor 19
Floor 18
Floor 17
Floor 16
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1Pratt Institute30p · 2 filings · 18 docs
Sub-BasementPratt Institute1p · 1 filing · 5 docs
Site & exteriorPratt Institute36p · 3 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Pratt Institute4003/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
J.A.M. Associates203/21/2026
KM Associates of New York203/21/2026
Lombardo Building Consultants1203/21/2026
Yao W Guo Architect403/21/2026
K & M Associates203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SHR GroupScaffold1407/08/2026
L & M Construction/DRY WAGeneral Contractor407/08/2026
SHR GroupGeneral Contractor407/08/2026
Vintage Electric ServiceElectrical203/21/2026
Preserv BLD Restoration ManagementGeneral Contractor203/21/2026
SJS Construction CoGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SGM Engineering2366211/04/2024
Fenagh6942104/25/2023
Crosscheck Inspection Services544101/03/2022
Building Lifecycle
All (122)Filed (11)Permit Issued (13)Signed Off (4)Facade (FISP) (18)Violation (60)Special Inspection (16)
03/02/2026
Violation issued (FDNY_NOV, closed)
03/02/2026
Violation issued (FDNY_ORDER, closed)
03/02/2026
Violation issued (FDNY_ORDER, closed)
03/02/2026
Violation issued (FDNY_NOV, closed)
08/12/2025
Violation issued (FDNY_ORDER, closed)
08/12/2025
Violation issued (FDNY_ORDER, closed)
01/17/2025
Signed off — Alteration
HEREWITH FILING FOR MECHANICAL SYSTEM MODIFICATION AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01095322-S1
01/14/2025
Signed off — Alteration
HEREWITH FILING FOR MECHANICAL SYSTEM MODIFICATION AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01095322-I1
12/31/2024
Permit issued — General Construction
B01095322-I1-GC
12/31/2024
Permit issued — Mechanical Systems
B01095322-S1-MS
11/04/2024
Filed — Alteration
HEREWITH FILING FOR MECHANICAL SYSTEM MODIFICATION AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01095322-S1
11/04/2024
Filed — Alteration
HEREWITH FILING FOR MECHANICAL SYSTEM MODIFICATION AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01095322-I1
08/13/2024
Special inspection requirement — Mechanical Systems
steven Giammona
08/13/2024
Special inspection requirement — Final
steven Giammona
08/13/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
steven Giammona
08/13/2024
Special inspection requirement — Final
steven Giammona
06/13/2024
Permit issued — General Construction
B08020043-I1-GC-CX
01/29/2024
Cycle 9 facade report submitted
01/29/2024
Cycle 9 facade report signed — SWARMP
01/25/2024
Signed off — Alteration
Facade repairs and roofing replacement as per plans submitted herewith. No change in use, egress or occupancy.
B00696643-I1
01/22/2024
Cycle 9 facade inspection completed
01/16/2024
Violation issued (ECB, closed)
Local Law
12/28/2023
Cycle 9 facade report submitted
12/28/2023
Cycle 9 facade report signed — UNSAFE
12/22/2023
Cycle 9 facade inspection completed
11/01/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/11/2023
Violation issued (ECB, closed)
Construction
06/29/2023
Permit issued — Sidewalk Shed
B00767527-I1-SH
06/29/2023
Permit issued — General Construction
B00696643-I1-GC
06/29/2023
Permit issued — Supported Scaffold
B00767527-S1-SF
05/20/2023
Permit issued — Supported Scaffold
B00767527-S1-SF
05/19/2023
Permit issued — Sidewalk Shed
B00767527-I1-SH
04/25/2023
Filed — Alteration
Concrete slab and tile repairs as per plans filed herewith. no change to use, egress or occupancy.
B08020043-I1
02/21/2023
Cycle 9 facade report submitted
02/21/2023
Cycle 9 facade report signed — UNSAFE
02/21/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/15/2023
Filed — Alteration
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLDING AS PER PLANS FILED HEREWITH. NO CAHNGE TO USE, EGRESS OR OCCUPANCY.
B00767527-P4
02/14/2023
Cycle 9 facade inspection completed
01/13/2023
Filed — Alteration
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLDING AS PER PLANS FILED HEREWITH. NO CAHNGE TO USE, EGRESS OR OCCUPANCY.
B00767527-P3
12/07/2022
Filed — Alteration
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLDING AS PER PLANS FILED HEREWITH. NO CAHNGE TO USE, EGRESS OR OCCUPANCY.
B00767527-P2
12/01/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
AILANTO DANIEL MINAWI
12/01/2022
Special inspection requirement — Structural Steel - Details
AILANTO DANIEL MINAWI
12/01/2022
Special inspection requirement — Structural Steel - High Strength Bolting
AILANTO DANIEL MINAWI
12/01/2022
Special inspection requirement — Structural Steel - Welding
AILANTO DANIEL MINAWI
12/01/2022
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
AILANTO DANIEL MINAWI
12/01/2022
Special inspection requirement — Subgrade Inspections
AILANTO DANIEL MINAWI
12/01/2022
Special inspection requirement — Concrete - Cast-In-Place
AILANTO DANIEL MINAWI
12/01/2022
Special inspection requirement — Post-installed Anchors
AILANTO DANIEL MINAWI
12/01/2022
Special inspection requirement — Sprayed fire-resistant materials
AILANTO DANIEL MINAWI
11/11/2022
Violation issued (ECB, closed)
Construction
10/12/2022
Special inspection requirement — Footing and Foundation
AILANTO DANIEL MINAWI
10/12/2022
Special inspection requirement — Final
mahendradat sitaram
10/05/2022
Permit issued — General Construction
B00696643-I1-GC
09/06/2022
Filed — Alteration
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLDING AS PER PLANS FILED HEREWITH. NO CAHNGE TO USE, EGRESS OR OCCUPANCY.
B00767527-P1
08/21/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/20/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/14/2022
Filed — Alteration
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLDING AS PER PLANS FILED HEREWITH. NO CAHNGE TO USE, EGRESS OR OCCUPANCY.
B00767527-S1
07/14/2022
Permit issued — Supported Scaffold
B00767527-S1-SF
06/30/2022
Filed — Alteration
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLDING AS PER PLANS FILED HEREWITH. NO CAHNGE TO USE, EGRESS OR OCCUPANCY.
B00767527-I1
06/30/2022
Permit issued — Sidewalk Shed
B00767527-I1-SH
Latest 60 of 122 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offL & M Construction/DRY WA12/31/2024
DOB NOWMechanical SystemsSigned-offL & M Construction/DRY WA12/31/2024
DOB NOWGeneral ConstructionPermit IssuedPreserv BLD Restoration Management06/13/2024
DOB NOWSidewalk ShedPermit IssuedSHR Group06/29/2023
DOB NOWGeneral ConstructionSigned-offSHR Group06/29/2023
DOB NOWSupported ScaffoldPermit IssuedSHR Group06/29/2023
DOB NOWSupported ScaffoldPermit IssuedSHR Group05/20/2023
DOB NOWSidewalk ShedPermit IssuedSHR Group05/19/2023
DOB NOWGeneral ConstructionSigned-offSHR Group10/05/2022
DOB NOWSupported ScaffoldPermit IssuedSHR Group07/14/2022
DOB NOWSidewalk ShedPermit IssuedSHR Group06/30/2022
DOB NOWStructuralSigned-offSJS Construction Co01/27/2022
DOB NOWStructuralSigned-offSJS Construction Co01/19/2022
BISOTISSUEDAll HVAC Service Co11/14/2013
BISEQISSUEDLusheba Contracting11/13/2013
BISOTISSUEDAll HVAC Service Co10/17/2013
BISOTISSUEDLegacy Builders/Developers07/25/2012
BISOTISSUEDMCC Construction & Development07/23/2012
BISOTISSUEDAlpine Construction & Development07/21/2008
BISOTISSUEDAlpine06/15/2007
BISEQISSUEDRockledge Scaffold05/07/2007
BISEQISSUEDRockledge Scaffold05/01/2007
BISEQISSUEDAtlantic Heydt11/29/2006
BISEQISSUEDAtlantic Heydt01/03/2006
BISOTISSUEDPratt Institute12/21/2005
BISSPISSUEDSirina Fire Protection07/15/2005
BISMHISSUEDG A Energy Maintenance07/06/2005
BISSDISSUEDJohn's Plumbing & Heating07/01/2005
BISPLISSUEDJohn's Plumbing & Heating07/01/2005
BISMHISSUEDF J Sciame Construction Co06/21/2005
BISPLISSUEDOlympic Plumbing & Heating Service05/27/2005
BISFSISSUEDAce Atlas03/24/2005
BISBLISSUEDAce Atlas03/24/2005
BISSDISSUEDBest PBG Heating & Cool03/22/2005
BISEQISSUEDAtlantic Heydt03/04/2005
BISOTISSUEDF J Sciame Construction Co06/23/2004
BISMHISSUEDF J Sciame Construction Co06/23/2004
BISPLISSUEDOlympic Plumbing & Heating Service06/03/2004
BISEQISSUEDAtlantic Heydt05/13/2004
BISOTISSUEDF J Sciame Construction Co04/21/2004
+ 23 more permits on file
3 projects · most recent 06/19/2024
General Wiring
FiledStatusContractorScope
06/19/2024CompleteShuir Electrical ContractorsGeneral Wiring
07/08/2022Permit IssuedV Electric NY—
01/28/2020Permit IssuedWilldan Electrical of NYGeneral Wiring
1 project · most recent 04/25/2023
FiledStatusContractorScope
04/25/2023Permit IssuedPreserv BLD Restoration Management1 scope_items
1 project · most recent 02/15/2023
Scaffold Sidewalk Shed
FiledStatusContractorScope
02/15/2023Permit IssuedSHR GroupScaffold, Sidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
08/13/2024Mechanical Systemssteven Giammonaspecial
08/13/2024Finalsteven Giammonaprogress
08/13/2024Fire-Resistant Penetrations and Jointssteven Giammonaspecial
08/13/2024Finalsteven Giammonaprogress
12/01/2022Structural Stability – Alterations of existing buildingsAILANTO DANIEL MINAWIspecial
12/01/2022Structural Steel - DetailsAILANTO DANIEL MINAWIspecial
12/01/2022Structural Steel - High Strength BoltingAILANTO DANIEL MINAWIspecial
12/01/2022Structural Steel - WeldingAILANTO DANIEL MINAWIspecial
12/01/2022Subsurface Conditions – Fill Placement & In-Place DensityAILANTO DANIEL MINAWIspecial
12/01/2022Subgrade InspectionsAILANTO DANIEL MINAWIspecial
12/01/2022Concrete - Cast-In-PlaceAILANTO DANIEL MINAWIspecial
12/01/2022Post-installed AnchorsAILANTO DANIEL MINAWIspecial
12/01/2022Sprayed fire-resistant materialsAILANTO DANIEL MINAWIspecial
10/12/2022Footing and FoundationAILANTO DANIEL MINAWIprogress
10/12/2022Finalmahendradat sitaramprogress
03/11/2022Finalmahendradat sitaramprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Pratt InstituteEducationEntire building
Project B01095322 Alteration · LOC Issued · 11/04/2024
Project B08020043 Alteration · Permit Entire · 04/25/2023
Project B00767527 Alteration · Permit Entire · 06/30/2022
Project B00696643 Alteration · LOC Issued · 04/08/2022
Project B00641546 Alteration · LOC Issued · 01/03/2022
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 117 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/31/2026B00641546-I1Request digital key ↗
08/30/2026B00696643-I1Request digital key ↗
08/28/2026B00767527-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits15
▸BISWORK PERMIT APPLICATION5
11/13/2013340098753Open ↗
11/13/2013340098753Open ↗
10/29/2013320901770Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION5
11/13/2013340098753Open ↗
09/05/2013320901770Open ↗
07/25/2012320458580Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLPC Approval/Permit5
08/30/2026B00696643-I1Open ↗
08/13/2026B01095322-S1Open ↗
08/13/2026B00641546-I1Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications46
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/31/2026B00641546-I1Open ↗
08/30/2026B00696643-I1Open ↗
08/28/2026B00767527-P3Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
08/24/2026B01095322-I1Open ↗
08/23/2026B08020043-I1Open ↗
08/23/2026B08020043-I1Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION8
09/05/2013320901770Open ↗
12/11/2012320458580Open ↗
11/29/2012320503950Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
09/05/2013320901770Open ↗
09/05/2013320901770Open ↗
09/05/2013320901770Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
08/28/2026B00696643-I1Open ↗
08/24/2026B01095322-I1Open ↗
08/23/2026B08020043-I1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
09/05/2013320901770Open ↗
07/25/2012320503950Open ↗
06/30/2012320458580Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
11/13/2013340098753Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/13/2013340098753Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
11/13/2013340098753Open ↗
▸Environmental & Asbestos8
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
11/13/2013340098753Open ↗
09/05/2013320901770Open ↗
07/25/2012320503950Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/31/2026B00641546-I1Open ↗
08/13/2026B01095322-S1Open ↗
08/13/2026B01095322-I1Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
09/05/2013320901770Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/30/2026B00696643-I1Open ↗
▸Energy Compliance4
▸BISAS-BUILT ENERGY ANALYSIS2
09/05/2013320901770Open ↗
02/10/2015320901770Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
09/05/2013320901770Open ↗
▸BISTR8: Energy Code Progress Inspections1
02/10/2015320901770Open ↗
▸Approvals, Objections & Sign-offs19
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
08/31/2026B00641546-I1Open ↗
08/30/2026B00696643-I1Open ↗
08/28/2026B00767527-I1Open ↗
Showing 3 of 7 on file for this type
▸BISLANDMARKS APPROVAL6
02/10/2015320901770Open ↗
11/13/2013340098753Open ↗
09/05/2013320901770Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
09/05/2013320901770Open ↗
07/24/2012320503950Open ↗
06/29/2012320458580Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
12/11/2012320458580Open ↗
12/04/2012320503950Open ↗
02/10/2015320901770Open ↗
▸Cost, Insurance & Ownership6
▸BISCOST AFFIDAVIT6
02/10/2015320901770Open ↗
09/05/2013320901770Open ↗
12/11/2012320458580Open ↗
Showing 3 of 6 on file for this type
▸Filing & Intake Forms4
▸BISEFILING COVER SHEET3
09/05/2013320901770Open ↗
07/25/2012320503950Open ↗
06/30/2012320458580Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
11/13/2013340098753Open ↗
▸Other Documents4
▸DOB NOWProof of Historic Building4
08/30/2026B00696643-I1Open ↗
08/13/2026B08020043-I1Open ↗
08/13/2026B01095322-I1Open ↗
Showing 3 of 4 on file for this type