← Back
Office with commercial, 7-19 stories
Rockefeller Center
610 5 AVENUE · BIN 1082656
💬 Discuss this project
1937Year Built
9Stories
O6Building Class
C5-2.5Zoning
272,637 sfGross Floor Area
61Units
LL97 Covered3 Open Violations ▸FISP: SAFE
Office with commercial, 7-19 stories · Owner of record: RCPI LANDMARK PROPERTIES, LLC ATTN: TRACEY FRAZZETTA · 63,261 sf lot · 4.31 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionCivilGeneralOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction23p · 14 filings · 20 docs
Bulkhead2p · 1 filing · 2 docs
Floor 9Under Construction1p · 1 filing · 4 docs
Floor 8
Floor 7Under Construction8p · 7 filings · 20 docs
Floor 6Under Construction53p · 7 filings · 20 docs
Floor 522p · 7 filings · 20 docs
Floor 4Under Construction33p · 13 filings · 20 docs
Floor 312p · 7 filings · 20 docs
Floor 2
Floor 140p · 6 filings · 20 docs
Cellar58p · 29 filings · 20 docs
Sub-Cellar34p · 6 filings · 20 docs
Sub-Basement3p · 3 filings · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TISHMAN SPEYER24809/24/2026
NBCUNIVERSAL209/13/2026
RCPI LANDMARK PROPERTIES, LLC48007/08/2026
OWNERS REP407/08/2026
CATBIRD NYC LLC503/22/2026
RCPL LANDMARK PROPERTIES103/22/2026
RCP TRUST C/O TISHMAN103/22/2026
TISHMAN SPEYER PROPERTIES LLC403/21/2026
OSMAN203/21/2026
RCIP LANDMARK PROPERTIES LLC1203/21/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GILLMAN CONSULTING6003/21/2026
WALTER T. GORMAN, PE, PC6303/21/2026
MUNICIPAL BUILDING CONSULTANTS2803/21/2026
RIZZO GROUP603/21/2026
EA DESIGN GROUP803/21/2026
M G MCLAREN ENGINEERING203/21/2026
CONSTRUCTION PERMIT SERVICES103/21/2026
TK ARCDESIGN203/21/2026
OUTSOURCE CONSULTANTS, INC.603/21/2026
SAM MATHER ARCHITECT403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
COYLE CONTRACTING CORPGeneral Contractor3207/08/2026
WINICK PRODUCTIONS, LLCGeneral Contractor1707/08/2026
CORE FOUR CONSTRUCTION INGeneral Contractor1507/28/2026
A&A PLUMBING CORPPlumbing1309/13/2026
W.J. REGAN & COMPANY LLCGeneral Contractor1107/08/2026
SCHIMENTI CONSTRUCTION COGeneral Contractor907/08/2026
TURNER CONSTRUCTION COMPANYGeneral Contractor707/08/2026
PACE PLUMBING CORPFire Protection707/08/2026
TRISTATE PLBG SVCS CORPPlumbing607/08/2026
PSI PARTNERS, LLCFire Protection507/08/2026
ROYAL CONCRETE AND MASON*General Contractor404/09/2026
JRM CONSTRUCTION MGMT LLCGeneral Contractor304/09/2026
KLE CONSTRUCTION INCGeneral Contractor303/21/2026
BNW RIGGING INCGeneral Contractor303/21/2026
FINALY GENL CONTR CORPGeneral Contractor307/08/2026
REEM PLBG & HTG CORPPlumbing307/08/2026
WALKER DESIGN STUDIOS LLCGeneral Contractor207/08/2026
ROBERT HINDMAN, INCGeneral Contractor203/21/2026
L.E.A. ELECTRIC CORP.Electrical203/22/2026
TRI-STATE DISMANTLING CORPGeneral Contractor207/08/2026
SKH MECHANICAL CORPFire Protection207/08/2026
REEM PLBG & HTG CORPFire Protection207/08/2026
INTEGRAL CONSTRUCTION OFGeneral Contractor208/18/2026
NUCOR CONSTRUCTION CORPGeneral Contractor207/08/2026
ARTHUR GROSSMANElectrical203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
WALTER T. GORMAN, P.E., P2683808/10/2026
AK ENGINEERING PC678309/19/2025
METRIC CONSULTING AND INS1803407/23/2025
RICHARD H. BALSER ENGINEE3028207/03/2025
KMB DESIGN GROUP, LLC513104/28/2025
INTEGRITY CONSULTING SERV666412/19/2023
WELLDONE INSPECTION INC.8628105/25/2023
CNS INSPECTION SERVICES7566105/19/2023
FUTURE TECH CONSULTANTS O5891301/14/2022
CODEGREEN510510/14/2021
Building Lifecycle
All (300)Filed (74)Permit Issued (59)Signed Off (32)Inspection (48)Objection (57)Special Inspection (30)
09/23/2026
Permit issued — Mechanical Systems
M01411228-I1-MS
09/11/2026
Permit issued — Plumbing
M01411239-I1-PL
09/02/2026
Permit issued — General Construction
M01447310-I1-GC
08/27/2026
Permit issued — Sprinklers
M01411234-I1-EW-SP
08/26/2026
Filed — Alteration
Install of temp Truss structure, prod equip, no alt to exist structures for GAP NYFW Pop-Up Activation. TPA not required. Producer is responsible to monitor site safety & implement HWAP. All production equipment removed upon event complete
M01447310-I1
08/18/2026
Filed — No Work
M01445999-I1
08/18/2026
Special inspection requirement — Final
DANNY TRUJILLO
08/17/2026
Permit issued — General Construction
M01411219-I1-GC
08/10/2026
Filed — Alteration
Alterations to sprinkler system on 6th floor as per plans. No change to use, egress or occupancy.
M01411234-I1
08/10/2026
Filed — Alteration
M01411228-I1
08/07/2026
Filed — Alteration
General construction work on entire 6th floor as per plans. No change to use. egress or occupancy.
M01411219-I1
08/06/2026
Filed — Alteration
Alterations to plumbing system on 6th floor as per plans. No change to use, egress or occupancy.
M01411239-I1
08/05/2026
Permit issued — Sprinklers
M01407874-I1-EW-SP
08/05/2026
Permit issued — Plumbing
M01407884-I1-PL
08/03/2026
Signed off — Alteration
Installation of new AT&T site on the roof. Install 2 antennas, 10 RRH units, 1 GPS antenna and 1 equipment platform with cabinets. Related conduits through 7th-8th floor and service connection in the sub-basement.
M01184824-I1
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walter Gorman
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walter Gorman
07/30/2026
Special inspection requirement — Maintenance information
07/30/2026
Special inspection requirement — Final
SARAH VITEK
07/30/2026
Special inspection requirement — Fire-Resistance Rated Construction
Walter Gorman
07/30/2026
Special inspection requirement — Post-installed Anchors
Walter Gorman
07/30/2026
Special inspection requirement — Metering
07/30/2026
Special inspection requirement — Interior lighting power
07/30/2026
Special inspection requirement — Duct leakage testing, insulation and design
07/30/2026
Special inspection requirement — Lighting controls
07/27/2026
Permit issued — General Construction
M01243803-I1-GC
07/22/2026
Permit issued — Mechanical Systems
M01407840-I1-MS
07/21/2026
Filed — Alteration
Alterations to plumbing system in partial 4th floor as per plans. No change to use, egress or occupancy.
M01407884-I1
07/21/2026
Filed — Alteration
Demolition and general construction on the partial 4th floor as per plans. No change to use. egress or occupancy.
M01243803-I1
07/21/2026
Filed — Alteration
Alterations to sprinkler system in partial 4th floor as per plans. No change to use, egress or occupancy.
M01407874-I1
07/21/2026
Filed — Alteration
Alterations to mechanical system in 4th floor as per plans. No change to use, egress or occupancy.
M01407840-I1
07/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walter Gorman
07/17/2026
Special inspection requirement — Post-installed Anchors
Walter Gorman
07/17/2026
Special inspection requirement — Energy Code Compliance Inspections
Walter Gorman
07/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walter Gorman
07/10/2026
Filed — No Work
M01428893-I1
06/30/2026
Signed off — Alteration
Installation of temp truss video screen, no alt to exist structures for Annual Rink Video Display. No TPA required. Producer is responsible to monitor site safety & implement HWAP. All production equipment removed upon event completion
M01268774-I1
06/25/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/23/2026
Permit issued — General Construction
M01417445-I1-GC
06/22/2026
Filed — No Work
M01417446-I1
06/22/2026
Filed — Alteration
Alterations to 7th floor terrace as per plans. No change to use, egress or occupancy.
M01103866-P1
06/22/2026
Special inspection requirement — Final
Richard DeMarco
06/18/2026
Filed — Alteration
M01417445-I1
06/17/2026
Special inspection requirement — Final
Richard DeMarco
06/16/2026
Special inspection requirement — Final
DANNY TRUJILLO
06/09/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/04/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/03/2026
Special inspection requirement — Mechanical Systems
06/03/2026
Special inspection requirement — Final
06/03/2026
Special inspection requirement — Sprinkler Systems
Walter Gorman
06/02/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
05/27/2026
Special inspection requirement — Final
Walter Gorman
05/27/2026
Special inspection requirement — Mechanical Systems
Walter Gorman
05/27/2026
Special inspection requirement — Sprinkler Systems
Walter Gorman
05/20/2026
Filed — No Work
M01354552-P1
05/18/2026
Filed — Alteration
IRA to assist with Condition Assessment
M01403775-I1
05/15/2026
Permit issued — General Construction
M01399329-I1-GC
05/14/2026
Objection resolved — Addressed
05/14/2026
Objection resolved — Addressed
05/13/2026
Signed off — Alteration
Structural work on 7th floor terrace as per plans. No change to use, egress or occupancy.
M01332069-I1
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedIRVING HAASE & CO, INC09/23/2026
DOB NOWPlumbingPermit IssuedA&A PLUMBING CORP09/11/2026
DOB NOWGeneral ConstructionPermit IssuedNYFF EVENTS LLC09/02/2026
DOB NOWSprinklersPermit IssuedMILL BROOK FIRE PROTECTION08/27/2026
DOB NOWGeneral ConstructionPermit IssuedINTEGRAL CONSTRUCTION OF08/17/2026
DOB NOWPlumbingPermit IssuedMEGA PLBG CORP08/05/2026
DOB NOWSprinklersPermit IssuedMEGA PLBG CORP08/05/2026
DOB NOWGeneral ConstructionPermit IssuedCORE FOUR CONSTRUCTION IN07/27/2026
DOB NOWMechanical SystemsPermit IssuedCORE FOUR CONSTRUCTION IN07/22/2026
DOB NOWGeneral ConstructionPermit IssuedWINICK PRODUCTIONS, LLC06/23/2026
DOB NOWGeneral ConstructionPermit IssuedSCONDA CANVAS PRODUCTS05/15/2026
DOB NOWGeneral ConstructionPermit IssuedWINICK PRODUCTIONS, LLC04/10/2026
DOB NOWGeneral ConstructionPermit IssuedWINICK PRODUCTIONS, LLC03/09/2026
DOB NOWPlumbingPermit IssuedA&A PLUMBING CORP02/03/2026
DOB NOWGeneral ConstructionPermit IssuedWINICK PRODUCTIONS, LLC01/27/2026
DOB NOWGeneral ConstructionPermit IssuedROYAL CONCRETE AND MASON*01/27/2026
DOB NOWStructuralSigned-offROYAL CONCRETE AND MASON*01/27/2026
DOB NOWGeneral ConstructionPermit IssuedWINICK PRODUCTIONS, LLC10/16/2025
DOB NOWPlumbingSigned-offA&A PLUMBING CORP10/02/2025
DOB NOWSprinklersSigned-offANCHOR PIPING LTD09/24/2025
DOB NOWGeneral ConstructionSigned-offINTEGRAL CONSTRUCTION OF09/23/2025
DOB NOWMechanical SystemsSigned-off4IR IDEAL09/23/2025
DOB NOWGeneral ConstructionPermit IssuedWINICK PRODUCTIONS, LLC09/22/2025
DOB NOWGeneral ConstructionSigned-offWINICK PRODUCTIONS, LLC09/15/2025
DOB NOWGeneral ConstructionSigned-offWINICK PRODUCTIONS, LLC09/09/2025
DOB NOWSprinklersSigned-offDEPENDABLE MECHANICAL COR08/15/2025
DOB NOWSprinklersSigned-offA + SPRINKLER CORP07/25/2025
DOB NOWMechanical SystemsPermit IssuedJRM CONSTRUCTION MGMT LLC07/25/2025
DOB NOWPlumbingSigned-offA PLUS PLUMBING CORP07/25/2025
DOB NOWGeneral ConstructionPermit IssuedJRM CONSTRUCTION MGMT LLC07/18/2025
DOB NOWPlumbingSigned-offA&A PLUMBING CORP07/15/2025
DOB NOWGeneral ConstructionPermit IssuedJRM CONSTRUCTION MGMT LLC07/10/2025
DOB NOWConstruction FenceSigned-offSPRING SCAFFOLDING LLC07/03/2025
DOB NOWAntennaSigned-offDIGITAL CONSTRUCTION TECH06/30/2025
DOB NOWGeneral ConstructionPermit IssuedWINICK PRODUCTIONS, LLC04/22/2025
DOB NOWGeneral ConstructionSigned-offWALKER DESIGN STUDIOS LLC04/18/2025
DOB NOWMechanical SystemsSigned-offWALKER DESIGN STUDIOS LLC04/18/2025
DOB NOWPlumbingSigned-offA&A PLUMBING CORP02/18/2025
DOB NOWGeneral ConstructionSigned-offWINICK PRODUCTIONS, LLC09/03/2024
DOB NOWSprinklersSigned-offREEM PLBG & HTG CORP08/06/2024
+ 60 more permits on file
1 project · most recent 07/23/2025
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/23/2025Permit IssuedJRM CONSTRUCTION MGMT LLCAir Conditioning Systems
Cooling
Aaon H3-ERB-8-0-28FC-000 244,700 BTU · Ahu ×1
5 projects · most recent 08/10/2026
FiledStatusContractorScope
08/10/2026Permit IssuedLEGUCI PIPING&HEATING LLC122 heads
07/21/2026Permit IssuedREAL PLUMBING CORP19 heads
09/19/2025Signed-offANCHOR PIPING LTD113 heads
07/23/2025Signed-offA + SPRINKLER CORP22 heads
01/08/2021Signed-offA&M WARSHAW SERVICES LLC—
7 projects · most recent 08/10/2026
Water/Sanitary Gas
FiledStatusContractorScope
08/10/2026———
08/06/2026Permit IssuedA&A PLUMBING CORPWater/Sanitary
07/21/2026Permit IssuedREAL PLUMBING CORPWater/Sanitary
09/19/2025Signed-offA&A PLUMBING CORPWater/Sanitary
07/23/2025Signed-offA PLUS PLUMBING CORPWater/Sanitary
09/16/2022Permit IssuedMCLNY PLBG & HEATING LLCGas, Water/Sanitary
01/29/2020——Water/Sanitary
25 projects · most recent 09/10/2026
General Wiring Lighting
FiledStatusContractorScope
09/10/2026Permit IssuedZEREM ELECTRIC CORP.General Wiring
09/02/2026Permit IssuedZEREM ELECTRIC CORP.—
02/04/2026Permit IssuedTITAN ELEC'L & ELEV CONTRGeneral Wiring
10/07/2025Permit IssuedL.E.A. ELECTRIC CORP.General Wiring
10/07/2025Permit IssuedL.E.A. ELECTRIC CORP.—
07/28/2025Permit IssuedOMTA TECH INC—
07/18/2025Permit IssuedCITI-WIDE ELECTRIC INCGeneral Wiring
12/11/2024CompletePREMIER ELECTRIC, INCGeneral Wiring
08/04/2023CompleteERNE VALLEY ELECTRIC INCGeneral Wiring
07/18/2023CompleteEMPIRE STATE ELEC MAINT &General Wiring, Lighting
02/06/2023CompleteEMPIRE STATE ELEC MAINT &—
09/09/2022Permit IssuedMRD ELEC'L SERVICES, INCGeneral Wiring
05/18/2022CompleteD&D ELECTL CONST CO INCGeneral Wiring
11/02/2021CompleteM.C. ELECTRICAL NY INCGeneral Wiring
10/14/2021Permit IssuedLIVE WIRE ELECTRIC 1 LLCGeneral Wiring
2 projects · most recent 07/21/2026
Steel Concrete
FiledStatusContractorScope
07/21/2026Permit IssuedCORE FOUR CONSTRUCTION IN1 scope_items
01/19/2026Signed-offROYAL CONCRETE AND MASON*Steel, Concrete
1 project · most recent 05/18/2026
FiledStatusContractorScope
05/18/2026———
▾Field Inspections (DOB CAP) — 66
DateTypeResultReport
06/25/2026Pass-Final CND-Occupancy InspectionPassView ↗
06/09/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/04/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/02/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/29/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/18/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/23/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/23/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/08/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/06/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/06/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/31/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
12/30/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/30/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/24/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/24/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/03/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/08/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/22/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/19/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/10/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/12/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/07/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/27/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/21/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
Latest 25 of 66.
▾Special Inspection Requirements (DOB NOW) — 142
DateRequirementInspectorRole
08/18/2026FinalDANNY TRUJILLOprogress
07/30/2026Fire-Resistance Rated ConstructionWalter Gormanprogress
07/30/2026Fire-Resistant Penetrations and JointsWalter Gormanspecial
07/30/2026Post-installed AnchorsWalter Gormanspecial
07/30/2026Metering—energy_progress
07/30/2026Duct leakage testing, insulation and design—energy_progress
07/30/2026Maintenance information—energy_progress
07/30/2026Lighting controls—energy_progress
07/30/2026Fire-Resistant Penetrations and JointsWalter Gormanspecial
07/30/2026FinalSARAH VITEKprogress
07/30/2026Interior lighting power—energy_progress
07/17/2026Fire-Resistant Penetrations and JointsWalter Gormanspecial
07/17/2026Energy Code Compliance InspectionsWalter Gormanprogress
07/17/2026Post-installed AnchorsWalter Gormanspecial
07/15/2026Fire-Resistant Penetrations and JointsWalter Gormanspecial
06/22/2026FinalRichard DeMarcoprogress
06/17/2026FinalRichard DeMarcoprogress
06/16/2026FinalDANNY TRUJILLOprogress
06/03/2026Final—progress
06/03/2026Mechanical Systems—special
06/03/2026Sprinkler SystemsWalter Gormanspecial
05/27/2026Mechanical SystemsWalter Gormanspecial
05/27/2026FinalWalter Gormanprogress
05/27/2026Sprinkler SystemsWalter Gormanspecial
04/01/2026FinalDANNY TRUJILLOprogress
Latest 25 of 142.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
L CattertonOfficeFloors 4–6
Project M01411228 Alteration · QA Failed · 08/10/2026
Project M01411234 Alteration · Permit Entire · 08/10/2026
Project M01411219 Alteration · Permit Entire · 08/07/2026
Project M01411239 Alteration · Approved · 08/06/2026
Project M00986106 Alteration · LOC Issued · 01/08/2024
Project M00872423 Alteration · LOC Issued · 07/26/2023
Project M00873827 Alteration · LOC Issued · 07/26/2023
Project M00873834 Alteration · LOC Issued · 07/26/2023
Project M00873825 Alteration · LOC Issued · 07/19/2023
Project M08035946 Alteration · LOC Issued · 11/10/2022
Project M00564762 Alteration · LOC Issued · 09/08/2021
Project M00564765 Alteration · LOC Issued · 09/08/2021
Hamilton LaneOfficeFloor 4
Project M01407840 Alteration · Permit Entire · 07/21/2026
Project M01407874 Alteration · Permit Entire · 07/21/2026
Project M01407884 Alteration · Permit Entire · 07/21/2026
Project M08052575 Alteration · LOC Issued · 01/20/2023
Project M08052553 Alteration · LOC Issued · 01/12/2023
World Cup Telemundo Fan VillageOther—
Project M01417445 Alteration · Permit Entire · 06/18/2026
Van Cleef & ArpelsRetail—
Project M01381473 Alteration · Permit Entire · 04/09/2026
Capri HoldingsRetailGround, Floor 1
Project M01248988 Alteration · Permit Entire · 07/23/2025
Project M01245280 Alteration · Permit Entire · 07/02/2025
AesopRetailCellar, Ground
Project M00988473 Alteration · LOC Issued · 03/07/2024
Project M00988648 Alteration · LOC Issued · 03/05/2024
Johyun Gallery & Tishman SpeyerOther—
Project M00878277 Alteration · Permit Entire · 05/19/2023
Michael KorsUnknown—
Project M08029170 Alteration · Permit Entire · 11/22/2022
AtomixRestaurant / Food ServiceSub-cellar, Cellar
Project M00539715 Alteration · LOC Issued · 07/20/2021
Project M00539824 Alteration · Permit Entire · 07/20/2021
Project M00541205 Alteration · LOC Issued · 07/20/2021
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 2,857 on file (BIS + DOB NOW)
▸Plans & Drawings158
▸DOB NOWPlans/Sketch105
09/06/2026M01381473-I1Request digital key ↗
09/04/2026M00477853-I1Request digital key ↗
09/04/2026M00477853-P1Request digital key ↗
Showing 3 of 105 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸DOB NOWPlans/Sketch - Plumbing15
09/05/2026M00250979-I1Request digital key ↗
09/05/2026M00250973-I1Request digital key ↗
09/04/2026M00352746-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems7
09/05/2026M00250969-I1Request digital key ↗
09/05/2026M00273113-P1Request digital key ↗
09/05/2026M00273113-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler7
09/04/2026M00352747-I1Request digital key ↗
09/04/2026M00413460-I1Request digital key ↗
09/04/2026M00432347-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Protection of Mechanical Methods1
09/04/2026M00457543-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWPlans/Sketch - General Construction1
09/04/2026M00449551-I1Request digital key ↗
▸Applications & Permits558
▸BISPLAN / WORK APPROVAL APPLICATION284
10/23/2025122971276Open ↗
05/21/2025102824847Open ↗
05/19/2025102824847Open ↗
Showing 3 of 284 on file for this type
▸BISWORK PERMIT APPLICATION184
08/15/2022122139444Open ↗
01/27/2021140995127Open ↗
01/21/2021140994912Open ↗
Showing 3 of 184 on file for this type
▸DOB NOWLPC Approval/Permit90
09/05/2026M00250979-I1Open ↗
09/05/2026M00273113-I1Open ↗
09/05/2026M00273113-P1Open ↗
Showing 3 of 90 on file for this type
▸Zoning, Tax Lot & Property Records1
▸BISZoning Diagram (ZD1)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications848
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION370
03/27/2020123829250Open ↗
03/27/2020123829250Open ↗
Showing 2 of 370 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature155
09/06/2026M01381473-I1Open ↗
09/05/2026M00250979-I1Open ↗
09/05/2026M00250969-I1Open ↗
Showing 3 of 155 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST84
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 84 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT63
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 63 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM57
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 57 on file for this type
▸DOB NOWProgress Inspector Seal & Signature55
09/29/2026M00903673-I1Open ↗
09/23/2026M01447310-I1Open ↗
09/23/2026M01332069-I1Open ↗
Showing 3 of 55 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature49
09/23/2026M01248988-S2Open ↗
09/23/2026M00273160-I1Open ↗
09/23/2026M01248988-I1Open ↗
Showing 3 of 49 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION7
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY6
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 6 on file for this type
▸BISPC FULL REPORT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Trade Schedules & Equipment166
▸BISSELF-CERT PLUMBING NOTICE61
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 61 on file for this type
▸BISSCHEDULE B - PLUMBING40
09/29/2020123552921Open ↗
08/15/2020123552921Open ↗
Showing 2 of 40 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE40
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 40 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISSPRINKLER INSP REPORT : FP-857
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸Environmental & Asbestos256
▸DOB NOWDEP ACP-5: Asbestos Assessment Report109
09/05/2026M00250979-I1Open ↗
09/05/2026M00250969-I1Open ↗
09/05/2026M00273113-I1Open ↗
Showing 3 of 109 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)80
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 80 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'56
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 56 on file for this type
▸BISASBESTOS INSPECTION REPORT6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance56
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS27
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 27 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISNYCECC EXEMPTION5
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 5 on file for this type
▸BISENERGY CODE 1ST REVIEW COMPLETE4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTR8: Energy Code Progress Inspections3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.1
09/04/2026M00413350-I1Open ↗
▸Inspections & Test Reports38
▸BISTECHNICAL REPORT: RESPONSIBILITY18
04/11/2023140957579Open ↗
09/22/2021140937360Open ↗
09/03/2021123748908Open ↗
Showing 3 of 18 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSPRAYED FIRE-RESISTANT MATERIALS2
11/13/2023140995127Open ↗
11/13/2023140994912Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
11/13/2023140995127Open ↗
11/13/2023140994912Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTRUCTURAL STEEL - WELDING1
11/13/2023140995314Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
11/13/2023140994912Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
11/13/2023140995314Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
11/13/2023140995314Open ↗
▸BISSTRUCTURAL STEEL - DETAILS1
11/13/2023140995314Open ↗
▸Approvals, Objections & Sign-offs283
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST106
07/02/2024101881689Open ↗
07/02/2024101407158Open ↗
04/29/2024101745033Open ↗
Showing 3 of 106 on file for this type
▸BISLANDMARKS APPROVAL89
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 89 on file for this type
▸BISADMINISTRATIVE OBJECTIONS62
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 62 on file for this type
▸BISLANDMARKS SIGNOFF8
11/14/2023140995314Open ↗
11/14/2023140995127Open ↗
11/14/2023140994912Open ↗
Showing 3 of 8 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION7
08/15/2022122139444Open ↗
Showing 1 of 7 on file for this type
▸BISFINAL5
11/13/2023140995314Open ↗
11/13/2023140995127Open ↗
11/13/2023140994912Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
04/03/2024102824847Open ↗
04/02/2024102824847Open ↗
03/22/2024102824847Open ↗
▸BISCCD1-Construction Code Determination1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISLETTERS - APPRVD FAB CERT-INTENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWLandmark Approval1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership236
▸BISCOST AFFIDAVIT229
11/02/2022140957579Open ↗
09/03/2021123748908Open ↗
02/04/2021123829250Open ↗
Showing 3 of 229 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW37
11/13/2023140995314Open ↗
11/13/2023140995127Open ↗
11/13/2023140994912Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms238
▸BISEFILING COVER SHEET146
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 146 on file for this type
▸BISBOROUGH INTAKE FORM48
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 48 on file for this type
▸BISADDITIONAL INFORMATION32
09/29/2020123552921Open ↗
07/17/2020123829250Open ↗
07/01/2020123829250Open ↗
Showing 3 of 32 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET12
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 12 on file for this type
▸Other Documents17
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION7
10/06/2020140957579Open ↗
Showing 1 of 7 on file for this type
▸DOB NOWProof of Historic Building7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
12/04/2020123552921Open ↗
▸DOB NOWIRA Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type