← Back
Factory, light manufacturing
638 EAST 12 STREET
MANHATTAN · East Village · BIN 1079054
💬 Discuss this project
1958Year Built
3Stories
F5Building Class
R8BZoning
4,532 sfGross Floor Area
1Units
4 Open Violations ▸
Factory, light manufacturing · Owner of record: 638 EAST 12TH LP · 2,237 sf lot · 2.03 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction8p · 2 filings · 20 docs
Bulkhead8p · 1 filing · 20 docs
Floor 6Under Construction6p · 2 filings · 20 docs
Floor 5Under Construction6p · 2 filings · 20 docs
Floor 4Under Construction5p · 2 filings · 20 docs
Floor 3Under Construction4p · 2 filings · 20 docs
Floor 2Under Construction4p · 2 filings · 20 docs
Floor 1Under Construction6p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
OWNERS REP609/13/2026
PATOMA2508/29/2026
638 EAST 12TH LP C/O PATO303/22/2026
SKY EAST LLC103/22/2026
432 E 11 ST CORP403/22/2026
432 EAST 11TH STREET403/22/2026
432 E 11TH ST CORP103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/18/2023$2.8M—432 EAST 11TH ST. CORP. → 638 EAST 12TH LP$618/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
METROPOLIS GROUP INC2403/21/2026
AE DESIGN SOLUTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CORE SCAFFOLD SYSTEMS INC.General Contractor507/08/2026
YOUNG, GElectrical203/21/2026
DOWNEY, CONORElectrical103/21/2026
TODARO JOSEPHElectrical103/21/2026
Building Lifecycle
All (148)Filed (17)Permit Issued (3)Signed Off (1)Violation (19)Objection (78)Special Inspection (30)
08/06/2026
Objection resolved — Resolved
08/06/2026
Objection resolved — Resolved
07/07/2026
Objection raised — Other
07/07/2026
Objection raised — Other
06/11/2026
Permit issued — Construction Fence
M01410286-I1-FN
06/05/2026
Filed — Alteration CO
Existing 3-story building enlarged to 6-story building with installation of new sprinkler system. New sprinklers shall be provided as per NFPA 13 & NYC Building Code.
M00978388-A1
06/02/2026
Filed — Alteration
INSTALLATION OF TEMPORARY FENCE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01410286-I1
06/02/2026
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01410285-I1
06/02/2026
Permit issued — Supported Scaffold
M01410285-I1-SF
06/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/02/2026
Special inspection requirement — Energy Code Compliance Inspections
06/02/2026
Special inspection requirement — Maintenance information
06/02/2026
Special inspection requirement — Energy Code Compliance Inspections
06/02/2026
Special inspection requirement — Duct leakage testing, insulation and design
06/02/2026
Special inspection requirement — HVAC-R and service water heating equipment
06/02/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
06/02/2026
Special inspection requirement — Fire-Resistance Rated Construction
06/02/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
06/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/02/2026
Special inspection requirement — HVAC-R and service water heating system controls
06/02/2026
Special inspection requirement — Mechanical Systems
06/02/2026
Special inspection requirement — Shutoff dampers
06/02/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
06/02/2026
Special inspection requirement — Final
05/29/2026
Special inspection requirement — Sprinkler Systems
05/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/01/2026
Objection resolved — Resolved
04/01/2026
Objection resolved — Resolved
03/30/2026
Objection raised — Cost
03/30/2026
Objection raised — Cost
03/30/2026
Objection raised — Cost
03/30/2026
Objection raised — Cost
03/26/2026
Special inspection requirement — Final
03/26/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
03/26/2026
Special inspection requirement — Footing and Foundation
03/26/2026
Special inspection requirement — Concrete - Cast-In-Place
03/26/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
03/26/2026
Special inspection requirement — Deep Foundation Elements
03/26/2026
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
03/26/2026
Special inspection requirement — Subgrade Inspections
03/23/2026
Objection resolved — Addressed
03/23/2026
Objection resolved — Addressed
03/20/2026
Objection raised — Other
03/20/2026
Objection raised — Admin
03/16/2026
Filed — Alteration CO
Existing 3-story building enlarged to 6-story building with installation of new sprinkler system. New sprinklers shall be provided as per NFPA 13 & NYC Building Code.
M00978388-P8
03/16/2026
Special inspection requirement — Air barrier - visual inspection
03/16/2026
Special inspection requirement — HVAC-R and service water heating equipment
03/16/2026
Special inspection requirement — Exterior lighting power
03/16/2026
Special inspection requirement — Maintenance information
03/16/2026
Special inspection requirement — Metering
03/12/2026
Filed — Alteration CO
Existing 3-story building enlarged to 6-story building with installation of new sprinkler system. New sprinklers shall be provided as per NFPA 13 & NYC Building Code.
M00978388-P6
03/12/2026
Filed — Alteration CO
Existing 3-story building enlarged to 6-story building with installation of new sprinkler system. New sprinklers shall be provided as per NFPA 13 & NYC Building Code.
M00978388-P7
03/11/2026
Filed — Alteration CO
Existing 3-story building enlarged to 6-story building with installation of new sprinkler system. New sprinklers shall be provided as per NFPA 13 & NYC Building Code.
M00978388-P5
02/02/2026
Filed — Alteration CO
Existing 3-story building enlarged to 6-story building with installation of new sprinkler system. New sprinklers shall be provided as per NFPA 13 & NYC Building Code.
M00978388-P3
01/09/2026
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/09/2026
Violation issued (ECB, open)
Construction
11/03/2025
Objection resolved — Addressed
06/06/2025
Objection raised — Other
06/05/2025
Objection resolved — Addressed
01/30/2025
Objection resolved — Addressed
Latest 60 of 148 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedCORE SCAFFOLD SYSTEMS INC.06/11/2026
DOB NOWSupported ScaffoldPermit IssuedCORE SCAFFOLD SYSTEMS INC.06/02/2026
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC01/12/2024
BISOTISSUEDGIURDANELLA BROS INC.04/12/2004
1 project · most recent 06/05/2026
Air Conditioning Systems Heating and Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
06/05/2026——Air Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Friedrich UCT10B10A 10,000 BTU · Ptac ×3
Heat / Cool
Daikin FXDQ09MVJU 10,500 BTU · Vrf Indoor ×20
RXTQ48TAVJUA 49,500 BTU · Vrf Outdoor ×14
FXDQ12MVJU 13,500 BTU · Vrf Indoor ×10
FXDQ18MVJU 20,000 BTU · Vrf Indoor ×10
ZRNU093L1GA 10,900 BTU · Vrf Indoor ×2
Lg ZRNU093L1GA 10,900 BTU · Vrf Indoor ×18
ZRNU183L2GA 21,500 BTU · Vrf Indoor ×7
ZRUM048GSS0 54,000 BTU · Vrf Outdoor ×6
Heating
Qmark AWH4408F 10,239 BTU · Electric Heater ×3
Ventilation
Panasonic FV-0511VFC1 50 CFM · Condensing Unit ×64
1 project · most recent 06/05/2026
Sprinkler System
FiledStatusContractorScope
06/05/2026——Sprinkler System
1 project · most recent 06/05/2026
Storm Water/Sanitary
FiledStatusContractorScope
06/05/2026——Storm, Water/Sanitary
1 project · most recent 01/23/2024
FiledStatusContractorScope
01/23/2024CompleteSOLAS ELECTRICAL CORP—
1 project · most recent 06/05/2026
Steel Concrete
FiledStatusContractorScope
06/05/2026——Steel, Concrete
2 projects · most recent 06/02/2026
Scaffold Fence
FiledStatusContractorScope
06/02/2026Permit IssuedCORE SCAFFOLD SYSTEMS INCScaffold
06/02/2026Permit IssuedCORE SCAFFOLD SYSTEMS INCFence
▾Special Inspection Requirements (DOB NOW) — 111
DateRequirementInspectorRole
06/02/2026Maintenance information—energy_progress
06/02/2026Fire-Resistance Rated Construction—progress
06/02/2026Energy Code Compliance Inspections—progress
06/02/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)—special
06/02/2026Fire-Resistant Penetrations and Joints—special
06/02/2026HVAC-R and service water heating equipment—energy_progress
06/02/2026Shutoff dampers—energy_progress
06/02/2026Mechanical Systems—special
06/02/2026Fire-Resistant Penetrations and Joints—special
06/02/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)—special
06/02/2026Final—progress
06/02/2026Energy Code Compliance Inspections—progress
06/02/2026Duct leakage testing, insulation and design—energy_progress
06/02/2026HVAC-R and service water heating system controls—energy_progress
06/02/2026HVAC-R and service water piping design and insulation—energy_progress
05/29/2026Sprinkler Systems—special
05/29/2026Fire-Resistant Penetrations and Joints—special
03/26/2026Concrete - Cast-In-Place—special
03/26/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)—special
03/26/2026Subgrade Inspections—special
03/26/2026Subsurface Conditions – Fill Placement & In-Place Density—special
03/26/2026Footing and Foundation—progress
03/26/2026Deep Foundation Elements—special
03/26/2026Final—progress
03/26/2026Subsurface Investigations (Borings/Test Pits)—special
Latest 25 of 111.
▾Documents — 38 on file (BIS + DOB NOW)
▸Plans & Drawings17
▸DOB NOWPlans/Sketch17
08/28/2026M00988952-I1Request digital key ↗
08/17/2026M01410286-I1Request digital key ↗
08/17/2026M01410285-I1Request digital key ↗
Showing 3 of 17 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/14/2026M00978388-A1Open ↗
▸Seals & Professional Certifications17
▸DOB NOWDPL-1: Design Professional Seal & Signature17
08/17/2026M01410286-I1Open ↗
08/17/2026M01410285-I1Open ↗
08/16/2026M00978388-S2Open ↗
Showing 3 of 17 on file for this type
▸Other Documents3
▸DOB NOWProperty Ownership Certification3
08/16/2026M00978388-I1Open ↗
08/16/2026M00978388-P3Open ↗
08/14/2026M00978388-A1Open ↗